Regulation (EU) 2026/2381 of the European Parliament and of the Council of 21 October 2026 on the acceleration of permit-granting processes for defence readiness projects

Regulation (EU) 2026/2381 of the European Parliament and of the Council of 21 October 2026 on the acceleration of permit-granting processes for defence readiness projects

Regulation (EU) 2026/2381 · Regulation · 14 articles

Data as of 2026-11-23 · Compiled from an official source version. Later amendments or repeals may not be reflected; the official text prevails. · Read the official text ↗

Subject matter

Article 1

Open ↗

This Regulation establishes common rules for the acceleration of permit-granting processes for defence readiness projects.

Definitions

Article 2

Open ↗

For the purposes of this Regulation, the following definitions apply: (1) ‘defence readiness project’ means a set of activities, investments and measures aimed at enhancing the defence readiness of one Member State or of more Member States jointly, including through the development or modernisation of the defence industry; (2) ‘defence industry’ means all undertakings engaged in the research, development, production, manufacture or supply of defence-related products as defined in Article 3, point (1), of Directive 2009/43/EC or in the provision of services directly related to those products for any and all elements of their life cycle; (3) ‘defence readiness’ means the state of preparedness of a Member State or several Member States to anticipate, prevent or respond to a crisis as defined in Article 1, point (10), of Directive 2009/81/EC, which relates to defence; (4) ‘middle capitalisation company’ or ‘mid-cap’ means middle capitalisation company as defined in Article 2, point (15), of Regulation (EU) 2021/697 of the European Parliament and of the Council  ( 9 ) ; (5) ‘small mid-cap enterprise’ or ‘small mid-cap’ means a small mid-cap enterprise as defined in the Annex to Commission Recommendation (EU) 2025/1099  ( 10 ) ; (6) ‘small and medium-sized enterprise’ or ‘SME’ means small and medium-sized enterprise as defined in Article 2 of the Annex to Commission Recommendation 2003/361/EC  ( 11 ) ; (7) ‘permit-granting process’ means a process that covers all relevant permits, including approvals or licences, necessary to build, expand, convert and operate defence readiness projects or to repurpose any installation, equipment or activity into a defence readiness project and all the necessary administrative steps from the confirmation that the permit application is complete to the notification of the comprehensive decision on the outcome of the process by the single point of contact concerned; (8) ‘project promoter’ means any undertaking or consortium of undertakings developing a defence readiness project; (9) ‘comprehensive decision’ means the decision taken by competent authorities that determines whether a project promoter is authorised to implement a defence readiness project, without prejudice to any decision taken in the context of an appeal procedure.

Designation of a defence readiness project

Article 3

Open ↗

Member States shall determine which projects qualify as a defence readiness project under this Regulation.

Single point of contact

Article 4

Open ↗

1.   By 24 February 2027, each Member State shall establish or designate one authority as single point of contact at the relevant administrative level. The single point of contact shall be the sole point of contact for a defence readiness project. 2.   Where necessary to reflect its decentralised administrative organisation, a Member State may establish or designate more than one single point of contact pursuant to paragraph 1. That Member State shall ensure that effective coordination mechanisms are established and that they provide tools to help project promoters identify the appropriate single point of contact for a defence readiness project and that that single point of contact acts as the sole interface for that project. 3.   The single point of contact shall be responsible for facilitating and coordinating the permit-granting process and for providing information on streamlining the administrative processes in accordance with Article 5, including information to the project promoter on when an application is considered to be complete in accordance with Article 7(1). At the request of the project promoter, prior to the permit application, the single point of contact shall also provide information on the permit-granting process, including the documentation to be submitted as part of the application and the requirements under which a project could be considered a defence readiness project under this Regulation. The provision of such information shall not prejudge the decision of the competent authorities to determine whether a project qualifies as a defence readiness project. 4.   As the sole point of contact for the project promoter in the permit-granting process for a defence readiness project, the single point of contact shall coordinate and facilitate the submission of all relevant documents and information and shall notify the project promoter of the comprehensive decision. Where so provided for by Member States, the single point of contact may also act as a competent authority and issue comprehensive decisions. 5.   Project promoters shall be allowed to submit any documents relevant to the permit-granting process in electronic form. Member States shall ensure the digital exchange, including via an interoperable portal where available, of documentation between the competent authority, the single point of contact and the project promoters. 6.   The competent authorities, coordinated by the single point of contact, shall ensure that any relevant studies carried out, or permits or authorisations issued, for a given project and for project promoters are taken into account and that no duplicate studies, permits or authorisations are required, unless otherwise required under Union or national law. 7.   Member States shall ensure that the single point of contact and all competent authorities responsible for any step in the permit-granting processes, including all procedural steps, have sufficient qualified staff and sufficient financial, technical and digital resources, including, where appropriate, for up-skilling and re-skilling, for the effective performance of their tasks under this Regulation. 8.   The competent authorities involved in the permit-granting process and other authorities concerned shall specify and make available to the single point of contact concerned, the requirements and all information requested of a project promoter before the permit-granting process commences. 9.   Upon request by a Member State, the Commission shall assist the authorities of that Member State with capacity building in support of implementation of this Regulation, in particular with technical assistance in establishing or operating a single point of contact and an interoperable portal. The Commission shall make best efforts to treat such requests as priority. 10.   Where a defence readiness project is cross-border within the Union, the Member States concerned shall ensure coordination and the timely exchange of information, without prejudice to national security and confidentiality requirements.

Online accessibility of information

Article 5

Open ↗

Member States shall provide public access to the following information on permit-granting processes relevant to defence readiness projects, online and in a centralised and easily accessible manner, to the extent that such publication is without prejudice to national security and with due regard to confidentiality requirements: (a) the single points of contact referred to in Article 4(1); (b) the permit-granting process, including information on dispute settlement concerning the permit-granting process and, where applicable, on alternative dispute resolution mechanisms, if such procedures are provided for by national law; (c) financing and investment services for defence readiness projects; (d) funding possibilities at Union and Member State level for defence readiness projects; (e) business support services, including but not limited to support services for corporate tax declaration, local tax laws or, where relevant and in accordance with national practices, labour law, for defence readiness projects; (f) guidelines and templates provided for standardised permit applications where available.

Accelerating implementation

Article 6

Open ↗

Member States shall provide administrative support for defence readiness projects located on their territory, paying particular attention to SMEs and mid-caps, including small mid-cap enterprises, involved in those projects, by providing, inter alia: (a) assistance regarding compliance with applicable administrative and reporting obligations, including under Union and national health, environmental, safety, social and labour law, where relevant; (b) assistance to project promoters in informing the public about the project; (c) assistance to project promoters throughout the permit-granting process; (d) coordination and assistance to project promoters of defence readiness projects with cross-border dimension.

Completeness check of the permit application

Article 7

Open ↗

1.   No later than 14 working days from receiving the permit application, the single point of contact shall inform the applicant whether this Regulation applies and confirm whether the permit application received is complete. 2.   If during the period referred to in paragraph 1 it is determined that information is missing from the permit application, the single point of contact shall request the project promoter to submit the missing information, specifying which information is missing. If the submitted permit application is deemed to be incomplete for a second time, the single point of contact may, within 10 working days of the second submission, make a second and final request for information. The single point of contact shall not request information in areas not covered in the first request for information and shall be entitled only to request further evidence to complete the identified missing information. If the submitted permit application is deemed incomplete for a third time, the process shall be considered terminated for the purposes of this Regulation. 3.   Where an environmental impact assessment report or other assessments are required as part of the permit application, a permit application shall be considered to be complete for the purposes of this Regulation only once the part of those assessments falling under the responsibility of the project promoter have been carried out and included in the permit application. 4.   The date on which the single point of contact notifies the project promoter that it has received a complete permit application shall serve as the start of the permit-granting process.

Duration of the permit-granting process

Article 8

Open ↗

1.   The permit-granting process, including the granting of the relevant permit, shall not exceed 42 working days from the date on which the single point of contact notifies the project promoter that it has received a complete permit application in accordance with Article 7(1) and (4). 2.   The single point of contact shall, in close cooperation with the competent authorities, draw up a schedule for the permit-granting process and share that schedule with the project promoter, at the start of the permit-granting process. 3.   Where a defence readiness project involves a modification or extension of an existing facility already authorised under national law, the competent authority shall determine whether the modification requires a new or updated permit, or whether it may proceed under the existing authorisation, provided that environmental, health and safety standards are not affected. 4.   Where a defence readiness project requires the construction of several facilities or units, whether located on a single site or across multiple sites, the project promoter may, in agreement with the single point of contact, split the project into smaller projects for the purpose of complying with the applicable time limits. For such split projects, the start date of the permit-granting process for all projects remains the date on which the single point of contact notifies the project promoter that it has received a complete permit application in accordance with Article 7 (1) and (4). 5.   By way of derogation from paragraph 1, and on a case-by-case basis, the competent authority may extend the time limit referred to in paragraph 1 twice, up to a maximum of 60 working days, where: (a) the exceptional nature, complexity, location, or size of the project so requires; or (b) the defence readiness project raises exceptional risks to the health and safety of workers or the general population, or an exceptional environmental risk, and additional time is necessary to adequately assess those risks. In the cases referred to in the first subparagraph, the total duration of the permit-granting process shall not exceed 102 working days. 6.   Any extension of the time limit referred to in paragraph 1 shall be notified in writing by the single point of contact to the project promoter within reasonable time before the expiry of that time limit. That notification shall include the substantiated explanation of the reasons for the extension and the expected date of the comprehensive decision. 7.   The time limits set out in this Article for any of the permit-granting processes shall be without prejudice to any shorter time limits established by Member States. 8.   Where the single point of contact does not inform the project promoter of the outcome of the permit-granting process within the time limit set out in paragraph 1 or, where applicable, the extended time limit, in accordance with paragraph 5, the permits covered by the application shall be deemed to be granted. 9.   Where permits are deemed to be granted pursuant to paragraph 8, the single point of contact shall within eight working days from the expiry of the time limits set out pursuant to paragraphs 1 and 5, inform the project promoter thereof and, where relevant, specify the conditions and requirements to which those permits are subject, in accordance with applicable Union or national law. Member States shall ensure that permits deemed to be granted pursuant to paragraph 8 may be challenged by affected parties. 10.   By way of derogation from paragraph 8, Member States may, in national law adopted by 24 November 2027, provide that tacit approval in accordance with paragraph 8 shall not apply in strictly limited and exceptional cases. A decision not to apply tacit approval shall be made only following a case-by-case assessment, where the competent authority demonstrates, on the basis of duly substantiated and verifiable evidence, that the specific project raises a grave risk to human health or national security. Any derogation shall be limited to what is strictly necessary to address the identified risk. Member States shall notify the Commission of the adoption of such national law without undue delay, and at the latest one month before it becomes applicable. Any decision not to apply tacit approval to an individual permit application shall be without prejudice to the time limits set out in paragraphs 1 and 5 and shall be adopted and notified to the project promoter before the expiry of the time limits set out therein. It shall include a detailed, evidence-based justification demonstrating compliance with the conditions set out in this paragraph.

Planning

Article 9

Open ↗

1.   National, regional and local authorities responsible for preparing plans, including zoning, spatial plans and land use plans, shall include in such plans, where appropriate, provisions for the development of defence readiness projects and necessary infrastructure. To facilitate the development of defence readiness projects, Member States shall ensure that non-confidential relevant spatial planning data are available online in accordance with Article 5 as well as with applicable Union and national law. 2.   Where plans include provisions for the development of defence readiness projects, and their required infrastructure, and are subject to an assessment pursuant to Directive 2001/42/EC of the European Parliament and of the Council  ( 12 ) and pursuant to Article 6 of Council Directive 92/43/EEC  ( 13 ) , those assessments shall be combined. Where applicable, the combined assessment shall also address the impact on potentially affected water bodies referred to in Directive 2000/60/EC of the European Parliament and of the Council  ( 14 ) . Where relevant Member States are required to assess the impact of existing and future activities on the marine environment, including land-sea interactions, as referred to in Article 4 of Directive 2014/89/EU of the European Parliament and of the Council  ( 15 ) , that impact shall also be covered in the combined assessment. The fact that assessments are combined pursuant to this paragraph shall not affect their content or quality. The combined assessment shall be carried out in a manner that does not lead to a prolongation of the time limits set out in this Regulation.

Priority status of defence readiness projects

Article 10

Open ↗

All dispute resolution procedures, litigation, appeals and judicial remedies as well as all administrative proceedings related to defence readiness projects before any national courts, tribunals, bodies or panels, including with regard to mediation or arbitration, where they exist in national law, shall be treated as urgent if and to the extent to which national law concerning relevant permit-granting processes provides for urgency procedures, provided that the applicable rights of defence and the right to an effective remedy of individuals or of local communities are respected. Project promoters shall participate in such urgency procedures, where applicable.

Applicability of UNECE Conventions

Article 11

Open ↗

This Regulation is without prejudice, where relevant, to the obligations under the United Nations Economic Commission for Europe (UNECE) Convention on Access to Information, Public Participation in Decision-making and Access to Justice in Environmental Matters, signed at Aarhus on 25 June 1998, and under the UNECE Convention on Environmental Impact Assessment in a Transboundary Context, signed at Espoo on 25 February 1991 and its Protocol on Strategic Environmental Assessment, signed in Kyiv on 21 May 2003.

Monitoring and reporting

Article 12

Open ↗

1.   Each Member State shall submit to the Commission, annually, a statistical report on the application of this Regulation, including the total number of permit applications granted, including those granted tacitly, pursuant to the procedures established by this Regulation. 2.   Member States shall inform the Commission about specific measures adopted to encourage and facilitate the participation of SMEs in defence readiness projects in accordance with Article 6. 3.   The Commission shall, in cooperation with Member States, assess the performance of the single points of contact, based on the data reported pursuant to paragraph 1. The Commission shall make the aggregated results referred to in paragraph 1 publicly available online, without prejudice to the protection of sensitive information relevant to national security and confidentiality requirements.

Review and evaluation

Article 13

Open ↗

1.   By 31 December 2028 and every four years thereafter, the Commission shall carry out an evaluation of the implementation of this Regulation. The Commission shall present a report on the main findings of the evaluation to the European Parliament and the Council. The evaluation shall include, at least, an assessment of: (a) whether the procedures established by this Regulation effectively contribute to the objectives of this Regulation, in particular as regards the timeline of the permit-granting process and the participation of SMEs in defence readiness projects; (b) the application of the tacit approval mechanism across Member States and its contribution to the objectives of this Regulation. 2.   Member States may provide to the Commission any information that the Commission may require to draw up the report referred to in paragraph 1, without prejudice to the protection of sensitive information relevant to national security and confidentiality requirements. Where the Commission considers it appropriate, the report shall be accompanied by a legislative proposal.

Entry into force and application

Article 14

Open ↗

This Regulation shall enter into force on the twentieth day following that of its publication in the Official Journal of the European Union . It shall apply only to permit applications for defence readiness projects submitted from 24 February 2027.

Other acts of the same type
Commission Implementing Regulation (EU) 2025/1890 of 18 September 2025 imposing a definitive anti-dumping duty on imports of threaded tube or pipe cast fittings, of malleable cast iron and spheroidal graphite cast iron originating in the People’s Republic of China and Thailand following an expiry review pursuant to Article 11(2) of Regulation (EU) 2016/1036 of the European Parliament and of the CouncilRegulation (EU) 2025/1913 of the European Parliament and of the Council of 18 September 2025 amending Regulation (EU) 2021/1057 establishing the European Social Fund Plus (ESF+) as regards specific measures to address strategic challengesRegulation (EU) 2025/1914 of the European Parliament and of the Council of 18 September 2025 amending Regulations (EU) 2021/1058 and (EU) 2021/1056 as regards specific measures to address strategic challenges in the context of the mid-term reviewCommission Implementing Regulation (EU) 2025/1887 of 17 September 2025 granting a Union authorisation for the single biocidal product CLARMARIN® 350 LD in accordance with Regulation (EU) No 528/2012 of the European Parliament and of the CouncilCommission Regulation (EU) 2025/1891 of 17 September 2025 amending Regulation (EU) 2023/915 as regards maximum levels of inorganic arsenic in fish and other seafoodCommission Implementing Regulation (EU) 2025/1893 of 17 September 2025 establishing, pursuant to Regulation (EU) 2024/573 of the European Parliament and of the Council, minimum requirements for training attestations of natural persons and the conditions for the mutual recognition of such training attestations as regards certain mobile equipment containing fluorinated greenhouse gases or their alternatives and repealing Commission Regulation (EC) No 307/2008Commission Implementing Regulation (EU) 2025/1876 of 16 September 2025 granting a Union authorisation for the single biocidal product Septihol IPA products in accordance with Regulation (EU) No 528/2012 of the European Parliament and of the CouncilCommission Implementing Regulation (EU) 2025/1878 of 16 September 2025 granting a Union authorisation for the biocidal product family BPF Propanol in accordance with Regulation (EU) No 528/2012 of the European Parliament and of the CouncilCommission Implementing Regulation (EU) 2025/1879 of 16 September 2025 renewing the approval of the low-risk active substance rape seed oil in accordance with Regulation (EC) No 1107/2009 of the European Parliament and of the Council, and amending Commission Implementing Regulation (EU) No 540/2011Commission Implementing Regulation (EU) 2025/1903 of 15 September 2025 on the approval of an amendment to the product specification of the protected designation of origin Vesuvio pursuant to Regulation (EU) 2024/1143 of the European Parliament and of the CouncilCommission Implementing Regulation (EU) 2025/1853 of 12 September 2025 amending Regulation (EU) No 468/2010 establishing the EU list of vessels engaged in illegal, unreported and unregulated fishingCommission Implementing Regulation (EU) 2025/1861 of 12 September 2025 correcting Commission Implementing Regulation (EU) 2021/1266 imposing a definitive anti-dumping duty on imports of biodiesel originating in the United States of America following an expiry review pursuant to Article 11(2) of Regulation (EU) 2016/1036 of the European Parliament and of the Council
Contents

What to look at next

DATA NOTES

About the data

Sources

This page

The full text of Regulation (EU) 2026/2381 is reproduced on LawPlayer from EUR-Lex, with a separate page for each article.