s 14 Specific performance of part of contract where part unperformed is large
Where a party to a contract is unable to perform the whole of his part of it, and the part which must be left unperformed forms a considerable portion of the whole, or does not admit of compensation in money, he is not entitled to obtain a decree for specific performance. But the court may, at the suit of the other party, direct the party in default to perform specifically so much of his part of the contract as he can perform, provided that the plaintiff relinquishes all claim to further performance, and all right to compensation either for the deficiency, or for the loss or damage sustained by him through the default of the defendant.
Malay text (authoritative)
Pelaksanaan spesifik sebahagian daripada kontrak jika bahagian yang tidak dilaksanakan adalah besar
Jika suatu pihak kepada sesuatu kontrak tidak dapat melaksanakan keseluruhan bahagian kontraknya, dan bahagian yang mesti ditinggalkan tanpa dilaksanakan itu merupakan suatu bahagian yang besar kepada keseluruhan kontrak itu, atau tidak membenarkan pampasan dalam bentuk wang, dia tidak berhak mendapat suatu dekri bagi pelaksanaan spesifik. Tetapi mahkamah boleh, atas guaman pihak yang satu lagi itu, mengarahkan pihak yang ingkar untuk melaksanakan secara spesifik seberapa banyak daripada bahagian kontraknya yang boleh dilaksanakannya, dengan syarat bahawa plaintif melepaskan semua tuntutan bagi pelaksanaan selanjutnya, dan semua hak terhadap pampasan sama ada bagi kekurangan itu, atau bagi kehilangan atau kerugian yang ditanggung olehnya oleh sebab keingkaran defendan.
Text as at 1 January 2006 (LOM reprint); amendments made after that date may not be incorporated.
Source: Laws of Malaysia, Attorney General's Chambers of Malaysia (lom.agc.gov.my). Not a copy of the Gazette printed by the Government Printer (Interpretation Acts 1948 and 1967, s 61).