Sustainable Energy Development Authority Act 2011 s 1
Sustainable Energy Development Authority Act 2011 s 1
s 1 Short title and commencement
(1) This Act may be cited as the Sustainable Energy Development Authority Act 2011.
(2) This Act comes into operation on a date to be appointed by the Minister by notification in the Gazette, and the Minister may appoint different dates—
(a) for the coming into operation of this Act in different parts of Malaysia;
(b) for the coming into operation of different provisions or Parts of this Act; and
(c) for the coming into operation of different provisions of this Act in different parts of Malaysia.
(3) The Minister may, by order published in the Gazette, suspend the operation of the whole or any of the provisions of this Act in different parts of Malaysia.
Malay text (authoritative)
Tajuk ringkas dan permulaan kuat kuasa
(1) Akta ini bolehlah dinamakan Akta Pihak Berkuasa Pembangunan Tenaga Lestari 2011.
(2) Akta ini mula berkuat kuasa pada tarikh yang ditetapkan oleh Menteri melalui pemberitahuan dalam Warta, dan Menteri boleh menetapkan tarikh-tarikh yang berlainan—
(a) bagi permulaan kuat kuasa Akta ini di bahagian-bahagian yang berlainan di Malaysia;
(b) bagi permulaan kuat kuasa peruntukan-peruntukan atau Bahagian-Bahagian yang berlainan dalam Akta ini; dan
(c) bagi permulaan kuat kuasa peruntukan-peruntukan yang berlainan dalam Akta ini di bahagian-bahagian yang berlainan di Malaysia.
(3) Menteri boleh, melalui perintah yang disiarkan dalam Warta, menggantung kuat kuasa keseluruhan atau mana-mana peruntukan Akta ini di bahagian-bahagian yang berlainan di Malaysia.
Text as at 10 November 2023 (LOM reprint); amendments made after that date may not be incorporated.
Source: Laws of Malaysia, Attorney General's Chambers of Malaysia (lom.agc.gov.my). Not a copy of the Gazette printed by the Government Printer (Interpretation Acts 1948 and 1967, s 61).