New interconnectors
1. New direct current interconnectors may, upon request, be exempted, for a limited period, from Article 19(2) and (3) of this Regulation and from Articles 6 and 43, Article 59(7) and Article 60(1) of Directive (EU) 2019/944 provided that the following conditions are met:
(a)
the investment enhances competition in electricity supply;
(b)
the level of risk attached to the investment is such that the investment would not take place unless an exemption is granted;
(c)
the interconnector is owned by a natural or legal person which is separate, at least in terms of its legal form, from the system operators in whose systems that interconnector is to be built;
(d)
charges are levied on users of that interconnector;
(e)
since the partial market opening referred to in Article 19 of Directive 96/92/EC of the European Parliament and of the Council ( 24 ) , no part of the capital or operating costs of the interconnector has been recovered from any component of charges made for the use of transmission or distribution systems linked by the interconnector; and
(f)
an exemption would not be to the detriment of competition or the effective functioning of the internal market for electricity, or the efficient functioning of the regulated system to which the interconnector is linked.
2. Paragraph 1 shall also apply, in exceptional cases, to alternating current interconnectors provided that the costs and risks of the investment in question are particularly high when compared with the costs and risks normally incurred when connecting two neighbouring national transmission systems by an alternating current interconnector.
3. Paragraph 1 shall also apply to significant increases of capacity in existing interconnectors.
4. The decision granting an exemption as referred to in paragraphs 1, 2 and 3 shall be taken on a case-by-case basis by the regulatory authorities of the Member States concerned. An exemption may cover all or part of the capacity of the new interconnector, or of the existing interconnector with significantly increased capacity.
Within two months of receipt of the request for exemption by the last of the regulatory authorities concerned, ACER may provide those regulatory authorities with an opinion. The regulatory authorities may base their decision on that opinion.
In deciding to grant an exemption, regulatory authorities shall take into consideration, on a case-by-case basis, the need to impose conditions regarding the duration of the exemption and non-discriminatory access to the interconnector. When deciding on those conditions, regulatory authorities shall, in particular, take account of additional capacity to be built or the modification of existing capacity, the time-frame of the project and national circumstances.
Before granting an exemption, the regulatory authorities of the Member States concerned shall decide on the rules and mechanisms for management and allocation of capacity. Those congestion-management rules shall include the obligation to offer unused capacity on the market and users of the facility shall be entitled to trade their contracted capacities on the secondary market. In the assessment of the criteria referred to in points (a), (b) and (f) of paragraph 1, the results of the capacity-allocation procedure shall be taken into account.
Where all the regulatory authorities concerned have reached agreement on the exemption decision within six months of receipt of the request, they shall inform ACER of that decision.
The exemption decision, including any conditions referred to in the third subparagraph of this paragraph, shall be duly reasoned and published.
5. The decision referred to in paragraph 4 shall be taken by ACER:
(a)
where the regulatory authorities concerned have not been able to reach an agreement within six months from the date on which the last of those regulatory authorities received the exemption request; or
(b)
upon a joint request from the regulatory authorities concerned.
Before taking such a decision, ACER shall consult the regulatory authorities concerned and the applicants.
6. Notwithstanding paragraphs 4 and 5, Member States may provide for the regulatory authority or ACER, as the case may be, to submit, for a formal decision, to the relevant body in the Member State, its opinion on the request for an exemption. That opinion shall be published together with the decision.
7. A copy of every request for exemption shall be transmitted for information without delay by the regulatory authorities to the Commission and ACER on receipt. The decision shall be notified, without delay, by the regulatory authorities concerned or by ACER (the notifying bodies), to the Commission, together with all the relevant information with respect to the decision. That information may be submitted to the Commission in aggregate form, enabling the Commission to reach a well-founded decision. In particular, the information shall contain:
(a)
the detailed reasons on the basis of which the exemption was granted or refused, including the financial information justifying the need for the exemption;
(b)
the analysis undertaken of the effect on competition and the effective functioning of the internal market for electricity resulting from the grant of the exemption;
(c)
the reasons for the time period and the share of the total capacity of the interconnector in question for which the exemption is granted; and
(d)
the result of the consultation of the regulatory authorities concerned.
8. Within 50 working days of the day following that of receipt of the notification under paragraph 7, the Commission may take a decision requesting the notifying bodies to amend or withdraw the decision to grant an exemption. That period may be extended by an additional 50 working days where further information is requested by the Commission. The additional period shall begin on the day following receipt of the complete information. The initial period may also be extended by consent of both the Commission and the notifying bodies.
Where the requested information is not provided within the period set out in the Commission's request, the notification shall be deemed to be withdrawn unless, before the expiry of that period, either the period is extended by consent of both the Commission and the notifying bodies, or the notifying bodies, in a duly reasoned statement, inform the Commission that they consider the notification to be complete.
The notifying bodies shall comply with a Commission decision to amend or withdraw the exemption decision within one month of receipt and shall inform the Commission accordingly.
The Commission shall protect the confidentiality of commercially sensitive information.
The Commission's approval of an exemption decision shall expire two years after the date of its adoption in the event that construction of the interconnector has not started by that date, and five years after the date of its adoption if the interconnector has not become operational by that date, unless the Commission decides, on the basis of a reasoned request by the notifying bodies, that any delay is due to major obstacles beyond the control of the person to whom the exemption has been granted.
9. Where the regulatory authorities of the Member States concerned decide to modify an exemption decision, they shall notify their decision to the Commission without delay, together with all the relevant information with respect to the decision. Paragraphs 1 to 8 shall apply to the decision to modify an exemption decision, taking into account the particularities of the existing exemption.
10. The Commission may, on request or on its own initiative, reopen proceedings relating to an exemption request where:
(a)
taking due account of the legitimate expectations of the parties and of the economic balance achieved in the original exemption decision, there has been a material change in any of the facts on which the decision was based;
(b)
the undertakings concerned act contrary to their commitments; or
(c)
the decision was based on incomplete, incorrect or misleading information, which was provided by the parties.
11. The Commission is empowered to adopt delegated acts in accordance with Article 68 supplementing this Regulation by specifying guidelines for the application of the conditions laid down in paragraph 1 of this Article and setting out the procedure to be followed for the application of paragraphs 4 and 7 to 10 of this Article.
Derogations
1. Member States may apply for derogations from the relevant provisions of Articles 3 and 6, Article 7(1), Article 8(1) and (4), Articles 9, 10 and 11, Articles 14 to 17, Articles 19 to 27, Articles 35 to 47 and Article 51 provided that:
(a)
the Member State can demonstrate that there are substantial problems for the operation of small isolated systems and small connected systems;
(b)
outermost regions within the meaning of Article 349 TFEU cannot be interconnected with the Union's energy market for evident physical reasons.
In the situation referred to in point (a) of the first subparagraph, the derogation shall be limited in time and shall subject to conditions aiming to increase competition and integration with the internal market for electricity.
In the situation referred to in point (b) of the first subparagraph, the derogation shall not be limited in time.
The Commission shall inform the Member States of those applications before adopting the decision, protecting the confidentiality of commercially sensitive information.
A derogation granted under this Article shall aim to ensure that it does not obstruct the transition towards renewable energy, increased flexibility, energy storage, electromobility and demand response.
In its decision granting a derogation the Commission shall set out to what extent the derogation is to take into account the application of the network codes and guidelines.
2. Articles 3, 5 and 6, Article 7(1), points (c) and (g) of Article 7(2)) Articles 8 to 17, Article 18(5) and (6), Articles 19 and 20, Article 21(1), (2) and (4) to (8), point (c) of Article 22(1), points (b) and (c) of Article 22(2), the last subparagraph of Article 22 (2), Articles 23 to 27, Article 34(1), (2) and (3), Articles 35 to 47, Article 48(2) and Articles 49 and 51 shall not apply to Cyprus until its transmission system is connected to other Member States' transmission systems via interconnections.
If the transmission system of Cyprus is not connected to other Member States' transmission systems by means of interconnections by 1 January 2026, Cyprus shall assess the need for derogation from those provisions and may submit a request to prolong the derogation to the Commission. The Commission shall assess whether the application of the provisions risks causing substantial problems to the operation of the electricity system in Cyprus or whether their application in Cyprus is expected to provide benefits to the functioning of the market. On the basis of that assessment, the Commission shall issue a reasoned decision to prolong the derogation in full or in part. The decision shall be published in the Official Journal of the European Union .
3. This Regulation shall not affect the application of the derogations granted under Article 66 of Directive (EU) 2019/944.
4. In relation to the attainment of the 2030 interconnection target, as stipulated under Regulation (EU) 2018/1999, the electricity link between Malta and Italy shall be duly taken into account.
Provision of information and confidentiality
1. Member States and the regulatory authorities shall, on request, provide the Commission with all the information necessary for the purposes of enforcing this Regulation.
The Commission shall set a reasonable time limit within which the information is to be provided, taking into account the complexity and urgency of the information required.
2. If the Member State or the regulatory authority concerned does not provide the information referred to in paragraph 1 within the time limit referred to in paragraph 1 the Commission may request all the information necessary for the purpose of enforcing this Regulation directly from the undertakings concerned.
When sending a request for information to an undertaking, the Commission shall, at the same time, forward a copy of the request to the regulatory authorities of the Member State in whose territory the seat of the undertaking is situated.
3. In its request for information under paragraph 1, the Commission shall state the legal basis of the request, the time limit within which the information is to be provided, the purpose of the request, and the penalties provided for in Article 66(2) for supplying incorrect, incomplete or misleading information.
4. The owners of the undertakings or their representatives and, in the case of legal persons, the natural persons authorised to represent the undertaking by law or by their instrument of incorporation, shall supply the information requested. Where lawyers are authorised to supply the information on behalf of their client, the client shall remain fully responsible in the event that the information supplied is incomplete, incorrect or misleading.
5. Where an undertaking does not provide the information requested within the time limit set by the Commission or supplies incomplete information, the Commission may by decision require the information to be provided. That decision shall specify what information is required and set an appropriate time limit within which it is to be supplied. It shall indicate the penalties provided for in Article 66(2). It shall also indicate the right to have the decision reviewed by the Court of Justice of the European Union.
The Commission shall, at the same time, send a copy of its decision to the regulatory authorities of the Member State within the territory of which the person is resident or the seat of the undertaking is situated.
6. The information referred to in paragraphs 1 and 2 shall be used only for the purposes of enforcing this Regulation.
The Commission shall not disclose information acquired pursuant to this Regulation where that information is covered by the obligation of professional secrecy.
Penalties
1. Without prejudice to paragraph 2 of this Article, the Member States shall lay down the rules on penalties applicable to infringements of this Regulation, the network codes adopted pursuant to Article 59, and the guidelines adopted pursuant to Article 61 and shall take all measures necessary to ensure that they are implemented. The penalties provided for shall be effective, proportionate and dissuasive. Member States shall, without delay, notify the Commission of those rules and of those measures and shall notify it without delay of any subsequent amendment affecting them.
2. The Commission may, by decision, impose on undertakings fines not exceeding 1 % of the total turnover in the preceding business year where, intentionally or negligently, those undertakings supply incorrect, incomplete or misleading information in response to a request made pursuant to Article 65(3) or fail to supply information within the time-limit set in a decision adopted pursuant to the first subparagraph of Article 65(5). In setting the amount of a fine, the Commission shall have regard to the gravity of the failure to comply with the requirements referred to in paragraph 1 of this Article.
3. The penalties provided for pursuant to paragraph 1 and any decisions taken pursuant to paragraph 2 shall not be of a criminal law nature.
Committee procedure
1. The Commission shall be assisted by the committee set up by Article 68 of Directive (EU) 2019/944. That committee shall be a committee within the meaning of Regulation (EU) No 182/2011.
2. Where reference is made to this paragraph, Article 5 of Regulation (EU) No 182/2011 shall apply.
Exercise of the delegation
1. The power to adopt delegated acts is conferred on the Commission subject to the conditions laid down in this Article.
2. The power to adopt delegated acts referred to in Article 34(3), Article 49(4), Article 59(2), Article 61(2) and Article 63(11) shall be conferred on the Commission until 31 December 2028. The Commission shall draw up a report in respect of the delegation of power not later than nine months before the end of that period and, if applicable, before the end of subsequent periods. The delegation of power shall be tacitly extended for periods of eight years, unless the European Parliament or the Council opposes such extension not later than three months before the end of each period.
3. The delegation of power referred to in Article 34(3), Article 49(4), Article 59(2), Article 61(2) and Article 63(11) may be revoked at any time by the European Parliament or by the Council. A decision to revoke shall put an end to the delegation of power specified in that decision. It shall take effect on the day following the publication of the decision in the Official Journal of the European Union or at a later date specified therein. It shall not affect the validity of any delegated act already in force.
4. Before adopting a delegated act, the Commission shall consult experts designated by each Member State in accordance with the principles laid down in the Interinstitutional Agreement of 13 April 2016 on Better Law-Making.
5. As soon as it adopts a delegated act, the Commission shall notify it simultaneously to the European Parliament and to the Council.
6. A delegated act adopted pursuant to Article 34(3), Article 49(4), Article 59(2), Article 61(2) and Article 63(11) shall enter into force only if no objection has been expressed either by the European Parliament or by the Council within a period of two months of notification of that act to the European Parliament and the Council or if, before the expiry of that period, the European Parliament and the Council have both informed the Commission that they will not object. That period shall be extended by two months at the initiative of the European Parliament or of the Council.
Commission reviews and reports
1. By 1 July 2025, the Commission shall review the existing network codes and guidelines in order to assess which of their provisions could be appropriately incorporated into legislative acts of the Union concerning the internal electricity market and how the empowerments for network codes and guidelines laid down in Articles 59 and 61 could be revised.
The Commission shall submit a detailed report of its assessment to the European Parliament and to the Council by the same date.
By 31 December 2026, the Commission shall, where appropriate, submit legislative proposals on the basis of its assessment.
2. By 31 December 2030 the Commission shall review this Regulation and shall submit a report to the European Parliament and to the Council on the basis of that review, accompanied by a legislative proposal where appropriate.
Repeal
Regulation (EC) No 714/2009 is repealed. References to the repealed Regulation shall be construed as references to this Regulation and shall be read in accordance with the correlation table set out in Annex III.
Entry into force
1. This Regulation shall enter into force on the twentieth day following that of its publication in the Official Journal of the European Union .
2. It shall apply from 1 January 2020.
Notwithstanding the first subparagraph, Articles 14, 15, 22(4), 23(3) and (6), 35, 36 and 62 shall apply from the date of entry into force of this Regulation. For the purpose of implementing Article 14(7) and Article 15(2), Article 16 shall apply from that date.