Determination of start-up and shut-down periods for heat generating combustion plants using load thresholds

Article 7

1.   For heat-generating combustion plants, the start-up period shall be considered to end when the plant reaches the minimum start-up load for stable generation and heat can be safely and reliably delivered to a distributing network, to a heat accumulator or used directly on a local industrial site. 2.   The shut-down period shall be considered to begin after reaching the minimum shut-down load for stable generation when heat can no longer be safely and reliably delivered to a network or used directly on a local industrial site. 3.   The load thresholds to be used for determining the end of the start-up period and the beginning of the shut-down period for heat generating combustion plants and to be included in the plant’s permit shall be a fixed percentage of the rated thermal output of the combustion plant. 4.   Periods in which heat-generating plants are heating up an accumulator or reservoir without exporting heat shall be considered as operating hours and not as start-up or shut-down periods.

Read the full instrument →

Other provisions in 2012/249/EU: Commission Implementing Decision of 7 May 2012…

Compiled from an official source version. Later amendments or repeals may not be reflected; the official text prevails. · Read the official text ↗ · Data as of 2026-07-04

CitationArticle 7 of 2012/249/EU: Commission Implementing Decision of 7 May 2012… (LawPlayer, data as of 2026-07-04)

© European Union, https://eur-lex.europa.eu, 1998-2026. Reuse authorised under Commission Decision 2011/833/EU, provided the source is acknowledged.

What to look at next