The Electricity Works (Environmental Impact Assessment) (England and Wales) Regulations 2017

The Electricity Works (Environmental Impact Assessment) (England and Wales) Regulations 2017 Sch 1 para 1

Sch 1 para 1

Development to provide any of the following— (a) a nuclear generating station; (b) a thermal generating station with a heat output of 300 megawatts or more; (c) an electric line installed above ground with— (i) a voltage of 220 kilovolts or more; and (ii) a length of more than 15 kilometres.

Read this section in the full act → · Open its part →

Read the official text ↗

Contains public sector information licensed under the Open Government Licence v3.0.