LawPlayer
My bookmarks
Source

Strata Management Act 2013 Part VII — DEPOSIT TO RECTIFY DEFECTS

s 92 · 1 section

Developer to pay deposit to rectify defects on common property

s 92

Open ↗

(1) A developer of a building shall deposit in cash or bank guarantee with the Commissioner such sum as may be determined by the Commissioner for the purpose of carrying out any work to rectify any defects in the common property of the development area after the completion of the common property. (2) The deposit referred to in subsection (1) shall be paid to the Commissioner upon the handing over of vacant possession. (3) The Commissioner may use the deposit for the purpose of carrying out any work which is necessary to rectify any defects in the common property of the development area. (4) Where the Commissioner has determined that the deposit is insufficient for rectifying the defects to the common property, the Commissioner may direct the developer to deposit within fourteen days such further sums as the Commissioner may determine. (5) Any unexpended deposit shall be refunded to the developer on the expiry of the defect liability period for the development area. (6) Any developer who fails to comply with subsection (1) commits an offence and shall, on conviction, be liable to a fine not exceeding five thousand ringgit and to a further fine not exceeding fifty ringgit for every day or part thereof during which the offence continues after conviction.

What to look at next

DATA NOTES

About the data

Sources

Sources

Provisions on this page are reproduced verbatim from official open data. See the attribution line. · Source: Laws of Malaysia, Attorney General's Chambers of Malaysia (lom.agc.gov.my). Not a copy of the Gazette printed by the Government Printer (Interpretation Acts 1948 and 1967, s 61).Read the official text ↗