These Regulations may be cited as the Contracts for Difference (Miscellaneous Amendments) Regulations 2018 and come into force on the day after the day on which they are made.
資料由法律人 LawPlayer整理提供·UK legislation / curated by LawPlayer from legislation.gov.uk
The Contracts for Difference (Miscellaneous Amendments) Regulations 2018
(1) The Contracts for Difference (Allocation) Regulations 2014 are amended as follows.
(2) In regulation 2, after the definition of “relevant works”, insert—
“remote island wind CFD unit” means a CFD unit which satisfies the remote island wind conditions in regulation 27A(3);
(3) After regulation 27, insert—
Remote island wind units
(27A)
(1) This regulation applies where the relevant CFD unit is to be a remote island wind CFD unit.
(2) The applicant must demonstrate that the relevant CFD unit is expected, by the target commissioning date, to satisfy the remote island wind conditions.
(3) The remote island wind conditions referred to in paragraph (2) are that—
(a) the CFD unit generates electricity by the use of wind;
(b) the CFD unit is located on a remote island;
(c) the CFD unit is connected to the national transmission system for Great Britain or to a distribution system; and
(d) either—
(i) where the CFD unit is connected to the national transmission system for Great Britain, the generation circuit between the CFD unit and the main interconnected transmission system consists of not less than 50 kilometres of cabling, not less than 20 kilometres of which is subsea cabling; or
(ii) where the CFD unit is connected to a distribution system, the electrical connection between its grid supply point and the main interconnected transmission system consists of not less than 50 kilometres of cabling, not less than 20 kilometres of which is subsea cabling.
(4) In this regulation—
“cabling” means a conductor used for the carrying of electricity;
“generation circuit” has the meaning given to that term in the NETS SQSS;
“grid supply point” has the meaning given to that term in the NETS SQSS;
“main interconnected transmission system” has the meaning given to that term in the NETS SQSS;
“NETS SQSS” means the means the National Electricity Transmission System Security and Quality of Supply Standard, version 2.3, February 2017 issued by National Grid Electricity Transmission plc (registered company number 2366977) ;
“remote island” means an island—
located in offshore waters: and
the entirety of the coastline (measured from the mean low water mark) of which is situated not less than 10 kilometres from mainland Great Britain; and
“subsea cabling” means cabling which is laid on or under the sea bed.
(1) Regulation 2(1) of the Contracts for Difference (Definition of Eligible Generator) Regulations 2014 is amended as follows.
(2) Omit the definition of “accredited CHP station”.
(3) Omit the definition of “CHPQA”.
(4) In the definition of “dedicated biomass with CHP station”, in sub-paragraph (a), for “is an accredited CHP station” substitute “is a CHP station”.
(5) In the definition of “energy from waste with CHP station”, in sub-paragraph (a), for “is an accredited CHP station” substitute “is a CHP station”.
(6) For the definition of “waste” substitute—
“waste” has the meaning given in Article 3(1) of Directive 2008/98/EC of the European Parliament and of the Council on waste but does not include—
landfill gas;
sewage gas; or
any substance intentionally modified or contaminated to fall within the meaning given in Article 3(1) of that Directive.
Cite this legislation
The Contracts for Difference (Miscellaneous Amendments) Regulations 2018 (legislation.gov.uk, OGL v3.0). Retrieved via LawPlayer, https://lawplayer.com/uk/act/uksi-2018-895 (accessed 2026-07-07)