Statutory Instrument

The Electricity (Individual Exemptions from the Requirement for a Transmission Licence) (Coronavirus) Order 2020

Citation
S.I. 2020/815
As at
Sections
5
Section 1Citation, commencement and interpretation

(1) This Order may be cited as the Electricity (Individual Exemptions from the Requirement for a Transmission Licence) (Coronavirus) Order 2020 and comes into force on 3rd October 2020.

(2) In this Order—

(a) “the Act” means the Electricity Act 1989;

(b) “successful bidder” means, in relation to the transfer of a transmission system, a person to whom, as a result of a tender exercise, an offshore transmission licence within the meaning of section 6C(5) of the Act (competitive tenders for offshore transmission licences) has been or is to be granted in respect of that transmission system.

Section 2Exemption from section 4(1)(b) of the Act (prohibition on unlicensed transmission of electricity for supply) for Beatrice Offshore Windfarm Limited

(1) Exemption is granted from section 4(1)(b) of the Act (prohibition on unlicensed transmission of electricity for supply) to Beatrice Offshore Windfarm Limited in respect of transmission taking place over the transmission system connected to the Beatrice Offshore Wind Farm.

(2) The exemption in paragraph (1) of this Article shall apply for the period beginning with 3rd October 2020 and ending with the earlier of—

(a) the day after the day on which the transmission system connected to Beatrice Offshore Wind Farm is transferred to a successful bidder;

(b) 2nd October 2021.

(3) In this Article—

(a) “Beatrice Offshore Windfarm Limited” means Beatrice Offshore Windfarm Limited, a company registered in Scotland with the company number SC350248;

(b) “Beatrice Offshore Wind Farm” means the generating station located approximately 13.4 kilometres to 24.8 kilometres from the shore, in the Moray Firth, off the Sarclet coast in Caithness, its coordinates at its central point being Latitude 58.254063 and Longitude -2.884543.

Section 3Exemption from section 4(1)(b) of the Act (prohibition on unlicensed transmission of electricity for supply) for Rampion Offshore Wind Limited

(1) Exemption is granted from section 4(1)(b) of the Act (prohibition on unlicensed transmission of electricity for supply) to Rampion Offshore Wind Limited in respect of transmission taking place over the transmission system connected to the Rampion Offshore Wind Farm.

(2) The exemption in paragraph (1) of this Article shall apply for the period beginning with 28th November 2020 and ending with the earlier of—

(a) the day after the day on which the transmission system connected to Rampion Offshore Wind Farm is transferred to a successful bidder;

(b) 27th November 2021.

(3) In this Article—

(a) “Rampion Offshore Wind Limited” means Rampion Offshore Wind Limited, a company registered in England and Wales with the company number 07199847;

(b) “Rampion Offshore Wind Farm” means the generating station located approximately 13.5 kilometres to 19.6 kilometres from the shore, in the English Channel, off the Sussex coast, its coordinates at its central point being Latitude 50.668 and Longitude -0.276.

Section 4Exemption from section 4(1)(b) of the Act (prohibition on unlicensed transmission of electricity for supply) for Hornsea 1 Limited

(1) Exemption is granted from section 4(1)(b) of the Act (prohibition on unlicensed transmission of electricity for supply) to Hornsea 1 Limited in respect of transmission taking place over the transmission system connected to the Hornsea 1 Offshore Wind Farm.

(2) The exemption in paragraph (1) of this Article shall apply for the period beginning with 15th January 2021 and ending with the earlier of—

(a) the day after the day on which the transmission system connected to Hornsea 1 Offshore Wind Farm is transferred to a successful bidder;

(b) 14th July 2021.

(3) In this Article—

(a) “Hornsea 1 Limited” means Hornsea 1 Limited, a company registered in England and Wales with the company number 07640868;

(b) “Hornsea 1 Offshore Wind Farm” means the generating station located approximately 102 kilometers to 126 kilometres from the shore, in the Southern North Sea, off the coast of East Yorkshire, its coordinates at its central point being Latitude 53.88328274 and Longitude 1.9218357.

Section 5Exemption from section 4(1)(b) of the Act (prohibition on unlicensed transmission of electricity for supply) for East Anglia One Limited

(1) Exemption is granted from section 4(1)(b) of the Act (prohibition on unlicensed transmission of electricity for supply) to East Anglia One Limited in respect of transmission taking place over the transmission system connected to the East Anglia One Offshore Wind Farm.

(2) The exemption in paragraph (1) of this Article shall apply for the period beginning with 14th September 2021 and ending with the earlier of—

(a) the day after the day on which the transmission system connected to East Anglia One Offshore Wind Farm is transferred to a successful bidder;

(b) 13th December 2021.

(3) In this Article—

(a) “East Anglia One Limited” means East Anglia One Limited, a company registered in England and Wales with the company number 07366753;

(b) “East Anglia One Offshore Wind Farm” means the generating station located approximately 48.3 kilometres to 63.1 kilometres from the shore, in the Southern North Sea, off the Suffolk coast, its coordinates at its central point being Latitude 52.2282999 and Longitude 2.4935852.

5 sections

Cite this legislation

The Electricity (Individual Exemptions from the Requirement for a Transmission Licence) (Coronavirus) Order 2020 (legislation.gov.uk, OGL v3.0). Retrieved via LawPlayer, https://lawplayer.com/uk/act/uksi-2020-815 (accessed 2026-07-06)

Contains public sector information licensed under the Open Government Licence v3.0.