This Order may be cited as the East Anglia THREE Offshore Wind Farm (Amendment) Order 2022 and comes into force on 1st October 2022.
資料由法律人 LawPlayer整理提供·UK legislation / curated by LawPlayer from legislation.gov.uk
The East Anglia THREE Offshore Wind Farm (Amendment) Order 2022
The East Anglia THREE Offshore Wind Farm Order 2017 (“ the 2017 Order ”) is amended in accordance with this Order.
In Part 1 (Authorised development) of Schedule 1 (Authorised project) to the 2017 Order, in paragraph (a) of the description of Work No. 1—
(a) omit the words “with a gross electrical output capacity of up to 1,400 MW”; and
(b) for “121” substitute “100” .
Part 3 (Requirements) of Schedule 1 (Authorised project) to the 2017 Order is amended as follows—
(a) in paragraph 2(1)(a), for “262” substitute “282” ;
(b) in paragraph 2(1)(c), for “230” substitute “250” ;
(c) in paragraph 3(8)(a), omit the words “with a gross electrical output capacity of up to 1,400 MW” and for “121” Substitute “100”;
(d) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
(e) in paragraph 33(2)(a) for “Trimingham” substitute “Neatishead” ; and
(f) in paragraph 33(2)(c) (Ministry of Defence surveillance operations), for “Kington Road, Sutton Coldfield, B75 7RL” substitute “St George’s House, DIO Head Office, DMS Whittington, Lichfield, Staffordshire WS14 9PY” .
Cite this legislation
The East Anglia THREE Offshore Wind Farm (Amendment) Order 2022 (legislation.gov.uk, OGL v3.0). Retrieved via LawPlayer, https://lawplayer.com/uk/act/uksi-2022-1015 (accessed 2026-07-07)
Contains public sector information licensed under the Open Government Licence v3.0.