This Order may be cited as the Thurrock Flexible Generation Plant Consent (Amendment) Order 2023 and comes into force on 8th March 2023.
資料由法律人 LawPlayer整理提供·UK legislation / curated by LawPlayer from legislation.gov.uk
The Thurrock Flexible Generation Plant Consent (Amendment) Order 2023
The Thurrock Flexible Generation Plant Development Consent Order 2022 (“ the 2022 Order ”) is amended in accordance with this Order.
In Schedule 1 to the 2022 Order (Authorised Development), in the description of Work no. 1 in 1B replace “with a net rated electrical output of up to 150 MW for four hours consisting of” with “having a combination of net rated electrical output and duration that delivers an electrical capacity of up to 600MWh, which may comprise—
(i) a net rated electrical output of 150MW for up to 4 hours
(ii) a net rated electrical output of 240MW for up to 2 hours and 30 minutes;
(iii) a net rated electrical output of 300MW for up to 2 hours;
(iv) a net rated electrical output of 400MW for up to 1 hour and 30 minutes; or
(v) a net rated electrical output of 600MW for up to 1 hour; and which consists of;
Cite this legislation
The Thurrock Flexible Generation Plant Consent (Amendment) Order 2023 (legislation.gov.uk, OGL v3.0). Retrieved via LawPlayer, https://lawplayer.com/uk/act/uksi-2023-289
Contains public sector information licensed under the Open Government Licence v3.0.
本頁資料來源:legislation.gov.uk (The National Archives)·整理提供:法律人 LawPlayer· lawplayer.com