(1) These Regulations may be cited as the Building Safety (Registration of Higher-Risk Buildings and Review of Decisions) (England) Regulations 2023 and come into force on 6th April 2023.
(2) These Regulations extend to England and Wales and apply to England only.
(3) In these Regulations—
“ the 2022 Act ” means the Building Safety Act 2022;
“ AP ” means accountable person ;
“ building certificate ” means a completion certificate or, as the case may be, a final certificate in relation to a building;
“ building control body ” means—
where the certificate is a completion certificate, the building control authority for the building;
where the certificate is a final certificate, the approved inspector or, as the case may be, registered building control approver who gave the initial notice to which the final certificate relates;
“ change of use ” has the same meaning as in The Town and Country Planning (Use Classes) Order 1987 ;
“ completed ” in relation to a building means—
in the case of a newly built higher-risk building , when the construction of that building is completed;
in the case of a building which was not a higher-risk building when built and which becomes a higher-risk building following a change of use, when the change of use occurs that causes that building to become a higher-risk building;
in the case of a building which was not a higher-risk building when built and which becomes a higher-risk building following works which cause it to become a higher-risk building, when those works are completed;
“ completion certificate ” means—
a certificate issued in accordance with regulation 17 (completion certificates) of the Building Regulations 2010 ,
a certificate issued in accordance with regulation 44 (completion certificate applications: decisions) of the Building (Higher-Risk Buildings Procedures) (England) Regulations 2023;
where paragraph 5, 10 or 11 of Schedule 3 to the Building (Higher-Risk Buildings Procedures) (England) Regulations 2023 applies in relation to a building, a transfer and completion certificate provided for by virtue of modifications set out in paragraph 5(9), 10(4), or, as the case may be, 11(4) of Schedule 3 to those Regulations;
a certificate issued in accordance with the equivalent provision of earlier regulations made under section 1 of the Building Act 1984 or section 4 of the Public Health Act 1961 , or
a certificate issued under an equivalent provision of byelaws made under section 61 of the Public Health Act 1936 ;
“ final certificate ” has the same meaning as in section 51 of the Building Act 1984 ;
“ leaseholder ” means a tenant under a lease of a dwelling in a building;
“ PAP ” means principal accountable person ;
“ the register ” means the register of higher-risk buildings ;
“ registration information ” means the information described in regulations 11 to 17, 18(1)(a) to (c) and (2) and 19;
“ relevant day ” means any day other than Christmas Day, Good Friday or a day which is a bank holiday under the Banking and Financial Dealings Act 1971 in England and Wales ;
“ start date ” means the day on which section 32 of the 2022 Act (building control authorities) comes into force in relation to England, ignoring any commencement of that section for the purpose only of making regulations;
“ transitional building ” means a higher-risk building in relation to which section 91ZA(1) of the Building Act 1984 does not apply (by virtue of regulations made under paragraph 10 of Schedule 1 to the Building Act 1984) on the day the application for registration of that building is submitted.