(1) This Order may be cited as the Offshore Installations (Safety Zones) Order 2023.
(2) This Order comes into force 21 days after the day on which it is made.
資料由法律人 LawPlayer整理提供·UK legislation / curated by LawPlayer from legislation.gov.uk
(1) This Order may be cited as the Offshore Installations (Safety Zones) Order 2023.
(2) This Order comes into force 21 days after the day on which it is made.
A safety zone is established around each installation specified in column 1 of the table in the Schedule (being an installation stationed in waters to which subsection (7) of section 21 of the Petroleum Act 1987 applies) having a radius of five hundred metres, as respects that installation, from the point which has the co-ordinates of latitude and longitude according to the World Geodetic System 1984 specified in columns 2 and 3 of the table in the Schedule.
(1) The Offshore Installations (Safety Zones) Order 1997 is amended as follows.
(2) In Schedule 1 (safety zones), omit the entry relating to “Orwell Subsea Structure”.
(1) The Offshore Installations (Safety Zones) Order 2013 is amended as follows.
(2) In the Schedule (installations), in Part 1, omit the entry relating to “Curlew CUC-P1 Drill Site”.
(1) The Offshore Installations (Safety Zones) (No. 2) Order 2016 is amended as follows.
(2) In the Schedule (installations), in Part 1, omit the entry relating to “Curlew Development, Block 29/7a, Curlew Field”.
(1) The Offshore Installations (Safety Zones) (No. 3) Order 2017 is amended as follows.
(2) In the Schedule (installations), in Part 1, omit the entry relating to “Horne and Wren, Block 53/3c, Horne and Wren Field”.
The Offshore Installations (Safety Zones) Order 2023 (legislation.gov.uk, OGL v3.0). Retrieved via LawPlayer, https://lawplayer.com/uk/act/uksi-2023-838 (accessed 2026-07-06)
Contains public sector information licensed under the Open Government Licence v3.0.
本頁資料來源:legislation.gov.uk (The National Archives)·整理提供:法律人 LawPlayer· lawplayer.com