法律人 LawPlayer logo

資料由法律人 LawPlayer整理提供·UK legislation / curated by LawPlayer from legislation.gov.uk

Statutory Instrument

The West Burton Solar Project Order 2025

Citation
S.I. 2025/116
As at
Sections
353
Section 1Citation and commencement

This Order may be cited as the West Burton Solar Project Order 2025 and comes into force on 15th February 2025.

Section 2Interpretation

(1) In this Order—

“ the 1961 Act ” means the Land Compensation Act 1961 ;

“ the 1965 Act ” means the Compulsory Purchase Act 1965 ;

“ the 1980 Act ” means the Highways Act 1980 ;

“ the 1981 Act ” means the Compulsory Purchase (Vesting Declarations) Act 1981 ;

“ the 1984 Act ” means the Road Traffic Regulation Act 1984 ;

“ the 1989 Act ” means the Electricity Act 1989 ;

“ the 1990 Act ” means the Town and Country Planning Act 1990 ;

“ the 1991 Act ” means the New Roads and Street Works Act 1991 ;

“ the 2008 Act ” means the Planning Act 2008 ;

“ access plan ” means the plan of that name identified in the table at Schedule 13 (documents and plans to be certified) and which is certified by the Secretary of State as the access plan for the purposes of this Order;

“ address ” includes any number or address used for the purposes of electronic transmission;

“ apparatus ” has the same meaning as in Part 3 (street works in England and Wales) of the 1991 Act except that, unless otherwise provided, it further includes pipelines (and parts of them), aerial markers, cathodic protection test posts, field boundary markers, transformer rectifier kiosks, electricity cables, telecommunications equipment and electricity cabinets;

“ authorised development ” means the development and associated development, which is development within the meaning of section 32 (meaning of “ development ”) of the 2008 Act, authorised by this Order and as described in Schedule 1 (authorised development);

“ book of reference ” means the document of that name identified in the table at Schedule 13 (documents and plans to be certified) and which is certified by the Secretary of State as the book of reference for the purposes of this Order;

“ building ” includes any structure or erection or any part of a building, structure or erection;

“ carriageway ” has the same meaning as in the 1980 Act;

“ commence ” means beginning to carry out a material operation, as defined in section 155 (when development begins) of the 2008 Act, comprised in or carried out or for the purposes of the authorised development other than the permitted preliminary works (except where stated to the contrary) and “commencement”, “commenced” and cognate expressions are to be construed accordingly;

“ concept design parameters and principles ” means the document of that name identified in the table of Schedule 13 (documents and plans to be certified) and which is certified by the Secretary of State as the concept design parameters and principles document for the purposes of this Order;

“ the Cottam Solar Project Order ” means the Cottam Solar Project Order 2024 ;

“ crown land plan ” means the plan of that name identified in the table at Schedule 13 (documents and plans to be certified) and which is certified by the Secretary of State as the crown land plan for the purposes of this Order;

“ date of decommissioning ” means in respect of each part of the authorised development ..., the date on which that part of the authorised development has permanently ceased to generate electricity on a commercial basis;

“ date of final commissioning ” means in respect of each phase of the authorised development as submitted under requirement 2 of Schedule 2 (requirements) the date on which that part of the authorised development commences operation by generating electricity on a commercial basis but excluding the generation of electricity during commissioning and testing;

“ definitive map and statement ” has the same meaning as in Part III of the Wildlife and Countryside Act 1981 ;

“ electronic transmission ” means a communication transmitted—

by means of an electronic communications network; or

by other means but while in electronic form;

“ environmental statement ” means the document of that name identified in the table at Schedule 13 (documents and plans to be certified) and which is certified by the Secretary of State as the environmental statement for the purposes of this Order;

“ footpath ” and “ footway ” have the same meaning as in the 1980 Act;

“ the Gate Burton Energy Park Order ” means the Gate Burton Energy Park Order 2024 ;

“ highway ” and “ highway authority ” have the same meaning as in the 1980 Act ;

“ holding company ” has the same meaning as in section 1159 of the Companies Act 2006 ;

“ important hedgerows plan ” means the plan of that name identified in the table at Schedule 13 (documents and plans to be certified) and which is certified by the Secretary of State as the important hedgerows plan for the purposes of this Order;

“ land plan ” means the plan of that name identified in the table at Schedule 13 (documents and plans to be certified) and which is certified by the Secretary of State as the land plan for the purposes of this Order;

“ maintain ” includes inspect, repair, adjust, alter, remove, refurbish, reconstruct, replace and improve any part of but not remove, reconstruct or replace the whole of, the authorised development, and “maintenance” and “maintaining” are to be construed accordingly;

“ National Grid ” means National Grid Electricity Transmission plc (company number 2366977) whose registered office is at 1-3 Strand, London, WC2N 5EH or any successor as a licence holder within the meaning of Part 1 of the 1989 Act;

“ Order land ” means the land which is required for or is required to facilitate or is incidental to the authorised development and shown coloured pink, blue or yellow on the land plan and which is within the limits of land to be acquired or used and which is described in the book of reference;

“ Order limits ” means the limits shown on the works plan within which the authorised development may be carried out and land acquired or used;

“ outline battery storage safety management plan ” means the document of that name identified in the table at Schedule 13 (documents and plans to be certified) and which is certified by the Secretary of State as the battery storage safety management plan for the purposes of this Order;

“ outline construction environmental management plan ” means the document of that name identified in the table at Schedule 13 (documents and plans to be certified) and which is certified by the Secretary of State as the outline construction environmental management plan for the purposes of this Order;

“ outline construction traffic management plan ” means the document of that name identified in the table at Schedule 13 (documents and plans to be certified) and which is certified by the Secretary of State as the outline construction traffic management plan for the purposes of this Order;

“ outline decommissioning statement ” means the document of that name identified in the table at Schedule 13 (documents and plans to be certified) and which is certified by the Secretary of State as the outline decommissioning statement for the purposes of this Order;

“ outline drainage strategy ” means the document of that name identified in the table at Schedule 13 (documents and plans to be certified) and which is certified by the Secretary of State as the outline drainage strategy for the purposes of this Order;

“ outline ecological protection and mitigation strategy ” means the document of that name identified in the table at Schedule 13 (documents and plans to be certified) and which is certified by the Secretary of State as the outline ecological protection and mitigation strategy for the purposes of this Order;

“ outline landscape and ecological management plan ” means the document of that name identified in the table at Schedule 13 (documents and plans to be certified) and which is certified by the Secretary of State as the outline landscape and ecological management plan for the purposes of this Order;

“ outline operational environmental management plan ” means the document of that name identified in the table at Schedule 13 (documents and plans to be certified) and which is certified by the Secretary of State as the outline operational environmental management plan for the purposes of this Order;

“ outline public rights of way management plan ” means the document of that name identified in the table at Schedule 13 (documents and plans to be certified) and which is certified by the Secretary of State as the outline public rights of way management plan for the purposes of this Order;

“ outline skills, supply chain and employment plan ” means the plan of that name identified in the table at Schedule 13 (documents and plans to be certified) and which is certified by the Secretary of State as the outline skills, supply chain and employment plan for the purposes of this Order;

“ outline soil management plan ” means the document of that name identified in the table at Schedule 13 (documents and plans to be certified) and which is certified by the Secretary of State as the outline soil management plan for the purposes of this Order;

“ owner ”, in relation to land, has the same meaning as in section 7 (interpretation) of the Acquisition of Land Act 1981 ;

“ permitted preliminary works ” means all or any of—

environmental surveys, geotechnical surveys, intrusive archaeological surveys and other investigations for the purpose of assessing ground conditions;

removal of plant and machinery;

above ground site preparation for temporary facilities for the use of contractors;

remedial work in respect of any contamination or other adverse ground conditions;

diversion and laying of apparatus;

the provision of temporary means of enclosure and site security for construction;

the temporary display of site notices or advertisements; or

site clearance (including vegetation removal, demolition of existing buildings and structures);

“ plot ” means any plot as may be identified by reference to a number and which is listed in the book of reference and shown on the land plan;

“ public right of way ” includes any public right of way that is added to the definitive map and statement after the making of the Order;

“ public rights of way plan ” means the plan of that name identified in the table at Schedule 13 (documents and plans to be certified) and which is certified by the Secretary of State as the public rights of way plan for the purposes of this Order;

“ relevant planning authority ” means the local planning authority for the area in which the land to which the provisions of this Order apply is situated and as more particularly described for the purposes of the requirements in Schedule 2 (requirements);

“ requirements ” means those matters set out at Schedule 2 (requirements) and any reference to a numbered requirement is to be construed accordingly;

“ statutory undertaker ” means any person falling within section 127(8) (statutory undertakers’ land) of the 2008 Act and includes a public communications provider defined by section 151(1) (interpretation of chapter 1) of the Communications Act 2003 ;

“ street ” means a street within the meaning of section 48 (streets, street works and undertakers) of the 1991 Act, together with land on the verge of a street or between two carriageways, and includes any footpath and part of a street;

“ street authority ”, in relation to a street, has the same meaning as in Part 3 of the 1991 Act ;

“ streets plan ” means the plan of that name identified in the table at Schedule 13 (documents and plans to be certified) and which is certified by the Secretary of State as the streets plan for the purposes of this Order;

“ street works ” means the works listed in article ‎8(1) (street works);

“ subsidiary ” has the same meaning as in section 1159 of the Companies Act 2006 ;

“ the Tillbridge Solar Order ” means any development consent order for the project known as Tillbridge Solar Project and given reference number EN010142 by the Planning Inspectorate, if granted by the Secretary of State;

“ traffic authority ” has the same meaning as in section 121A (traffic authorities) of the 1984 Act ;

“ undertaker ” means West Burton Solar Project Limited (company number 13049324) and any other person who for the time being has the benefit of this Order in accordance with article ‎34 (benefit of the Order) or article ‎35 (consent to transfer the benefit of the Order);

“ Upper Tribunal ” means the Lands Chamber of the Upper Tribunal;

“ watercourse ” includes every river, stream, creek, ditch, drain, canal, cut, culvert, dyke, sluice, sewer and passage through which water flows except a public sewer or drain;

“ working day ” means any day other than a Saturday, Sunday or English bank or public holiday;

“ works plan ” means the plan of that name identified in the table at Schedule 13 (documents and plans to be certified) and which is certified by the Secretary of State as the works plan for the purposes of this Order; and

“ written scheme of investigation ” means the document of that name identified in the table at Schedule 13 (documents and plans to be certified) and which is certified by the Secretary of State as the written scheme of investigation for the purposes of this Order.

(2) References in this Order to rights over land include references to rights to do or restrain or to place and maintain anything in, on or under land or in the airspace above its surface and to any trusts or incidents (including restrictive covenants) to which the land is subject and references in this Order to the imposition of restrictive covenants are references to the creation of rights over land which interfere with the interests or rights of another and are for the benefit of land which is acquired under this Order or over which rights are created and acquired under this Order or is otherwise comprised in this Order.

(3) In this Order, references to the purposes of the authorised development include the construction, maintenance, operation, use and decommissioning of the authorised development.

(4) All distances, directions, capacities and lengths referred to in this Order are approximate and distances between lines or points on a numbered work comprised in the authorised development and shown on the works plan, access plan and public rights of way plan are to be taken to be measured along that work.

(5) References in this Order to numbered works are references to the works comprising the authorised development as numbered in Schedule 1 (authorised development) and shown on the works plan and a reference in this Order to a work designated by a number, or by a combination of letters and numbers, is a reference to the work so designated in that Schedule and a reference to “Work No. 1” or “ numbered work 1 ” means numbered works 1A, 1B and 1C inclusive and the same principle applies to such numbered works that contain letters.

(6) In this Order, the expression “ includes ” is to be construed without limitation.

(7) In this Order, references to any statutory body include that body’s successor bodies.

(8) All areas described in square metres in the book of reference are approximate.

Section 3Development consent etc. granted by this Order

(1) Subject to the provisions of this Order and the requirements in Schedule 2 (requirements), the undertaker is granted development consent for the authorised development to be carried out within the Order limits.

(2) Each numbered work must be situated within the corresponding numbered area shown on the works plan.

Section 4Operation of generating station

(1) The undertaker is authorised to use and operate the generating station comprised in the authorised development.

(2) This article does not relieve the undertaker of any requirement to obtain any permit or licence under any other legislation that may be required from time to time to authorise the operation of an electricity generating station.

Section 5Power to maintain the authorised development

(1) The undertaker may at any time maintain the authorised development.

(2) This article only authorises the carrying out of maintenance works within the Order limits.

(3) This article does not authorise the carrying out of any maintenance works which are likely to give rise to any materially new or materially different effects that have not been assessed in the environmental statement.

Section 6Application and modification of statutory provisions

(1) The following provisions do not apply in relation to the construction of any work or the carrying out of any operation required for the purposes of, or in connection with, the construction, operation or maintenance of any part of the authorised development—

(a) section 23 (prohibition of obstructions, etc. in watercourses) of the Land Drainage Act 1991 ;

(b) section 32 (variation of awards) of the Land Drainage Act 1991;

(c) the provisions of any byelaws made under section 66 (powers to make byelaws) of the Land Drainage Act 1991;

(d) the provisions of any byelaws made under, or having effect as if made under, paragraphs 5, 6 or 6A of Schedule 25 (byelaw making powers of the appropriate agency) to the Water Resources Act 1991;

(e) section 118 (consent request for discharge of trade effluent into public sewer) of the Water Industry Act 1991 ;

(f) regulation 12 (requirement for environmental permit) of the Environmental Permitting (England and Wales) Regulations 2016 in respect of a flood risk activity only;

(g) the legislation listed in Schedule 3 (legislation to be disapplied) in so far as the provisions still in force are incompatible with the powers contained within this Order and do not impact on the operation or maintenance of the River Trent as a navigable river; and

(h) the provisions of the Neighbourhood Planning Act 2017 insofar as they relate to the temporary possession of land under articles ‎29 (temporary use of land for constructing the authorised development) and ‎30 (temporary use of land for maintaining the authorised development) of this Order.

(2) For the purposes of section 9 (requirement of licence for felling) of the Forestry Act 1967 any felling comprised in the carrying out of any work or operation required for the purposes of, or in connection with, the construction of the authorised development is deemed to be immediately required for the purpose of carrying out development authorised by planning permission granted under the 1990 Act.

(3) Notwithstanding the provisions of section 208 (liability) of the 2008 Act, for the purposes of regulation 6 (meaning of “ development ”) of the Community Infrastructure Levy Regulations 2010 any building comprised in the authorised development is deemed to be—

(a) a building into which people do not normally go; or

(b) a building into which people go only intermittently for the purpose of inspecting or maintaining fixed plant or machinery.

Section 7Defence to proceedings in respect of statutory nuisance

(1) Where proceedings are brought under section 82(1) (summary proceedings by a person aggrieved by statutory nuisance) of the Environmental Protection Act 1990 in relation to a nuisance falling within sub-paragraph (g) of section 79(1) (noise emitted from premises so as to be prejudicial to health or a nuisance) of that Act no order may be made, and no fine may be imposed, under section 82(2) of that Act if—

(a) the defendant shows that the nuisance—

(i) relates to premises used by the undertaker for the purposes of or in connection with the construction or maintenance of the authorised development and that the nuisance is attributable to the construction or maintenance of the authorised development in accordance with a notice served under section 60 (control of noise on construction site) of the Control of Pollution Act 1974 or a consent given under section 61 (prior consent for work on construction site) of that Act; or

(ii) is a consequence of the construction or maintenance of the authorised development and that it cannot reasonably be avoided; or

(b) the nuisance is a consequence of the use of the authorised development and that it cannot be reasonably avoided.

(2) Section 61(9) (consent for work on construction sites to include statement that it does not of itself constitute a defence to proceedings under section 82 of the Environmental Protection Act 1990) of the Control of Pollution Act 1974 does not apply where the consent relates to the use of the premises by the undertaker for the purposes of, or in connection with, the construction or maintenance of the authorised development.

Section 8Street works

(1) The undertaker may, for the purposes of the authorised development, enter on so much of any of the streets specified in Schedule 4 (streets subject to street works) and may—

(a) break up or open the street, or any sewer, drain or tunnel under it;

(b) drill, tunnel or bore under the street;

(c) place and keep apparatus in the street;

(d) maintain apparatus in the street, change its position or remove it;

(e) repair, replace or otherwise alter the surface or structure of the street or any culvert under the street; and

(f) execute any works required for or incidental to any works referred to in sub-paragraphs ‎(a) to ‎(e) .

(2) The authority given by paragraph ‎(1) is a statutory right or licence for the purposes of sections 48(3) (streets, street works and undertakers) and 51(1) (prohibition of unauthorised street works) of the 1991 Act.

(3) Where the undertaker is not the street authority, the provisions of sections 54 (notice of certain works) to 106 (index of defined expressions) of the 1991 Act apply to any street works carried out under paragraph ‎(1) .

Section 9Power to alter layout, etc., of streets

(1) The undertaker may for the purposes of the authorised development alter the layout of or carry out any works in the street—

(a) in the case of the streets specified in column 2 of the table in Part 1 (permanent alteration of layout) of Schedule 5 (alteration of streets) permanently in the manner specified in relation to that street in column 3; and

(b) in the case of the streets as specified in column 2 of the table in Part 2 (temporary alteration of layout) of Schedule 5 (alteration of streets) temporarily in the manner specified in relation to that street in column 3.

(2) Without prejudice to the specific powers conferred by paragraph ‎(1) , but subject to paragraphs ‎(3) and ‎(4) , the undertaker may, for the purposes of constructing, operating or maintaining the authorised development, alter the layout of any street and, without limitation on the scope of this paragraph, the undertaker may—

(a) alter the level or increase the width of any kerb, footway, cycle track or verge; and

(b) make and maintain passing places.

(3) The undertaker must restore any street that has been temporarily altered under this Order to the reasonable satisfaction of the street authority.

(4) The powers conferred by paragraph ‎(2) may not be exercised without the consent of the street authority, such consent to be in a form reasonably required by the street authority.

(5) Paragraphs ‎(3) and ‎(4) do not apply where the undertaker is the street authority for a street in which the works are being carried out.

Section 10Construction and maintenance of altered streets

(1) The permanent alterations to each of the streets specified in Part 1 (permanent alteration of layout) of Schedule 5 (alteration of streets) to this Order that are maintained by the highway authority must be completed to the reasonable satisfaction of the highway authority where applicable and, unless otherwise agreed by the highway authority, the alterations must be maintained by and at the expense of the undertaker for a period of 12 months from their completion and from the expiry of that period by and at the expense of the highway authority.

(2) The permanent alterations to each of the streets specified in Part 1 (permanent alteration of layout) of Schedule 5 (alteration of streets) to this Order that are maintained by the street authority must be completed to the reasonable satisfaction of the street authority where applicable and, unless otherwise agreed by the street authority, the alterations must be maintained by the undertaker for a period of 12 months from their completion and from the expiry of that period by and at the expense of the street authority.

(3) Subject to paragraph ‎(4) , the temporary alterations to each of the streets specified in Part 2 (temporary alteration of layout) of Schedule 5 (alteration of streets) must be completed to the reasonable satisfaction of the street authority and the temporary alterations must be maintained by and at the expense of the undertaker.

(4) Those restoration works carried out pursuant to article ‎9(3) (power to alter layout, etc., of streets) must be completed to the reasonable satisfaction of the street authority and must be maintained by the undertaker for a period of 12 months from their completion and from the expiry of that period by and at the expense of the street authority.

(5) In any action against the undertaker in respect of loss or damage resulting from any failure by it to maintain a street under this article, it is a defence (without prejudice to any other defence or the application of the law relating to contributory negligence) to prove that the undertaker had taken such care as in all the circumstances was reasonably required to secure that the part of the street to which the action relates was not dangerous to traffic.

(6) For the purposes of a defence under paragraph ‎(5) , a court must in particular have regard to the following matters—

(a) the character of the street including the traffic which was reasonably to be expected to use it;

(b) the standard of maintenance appropriate for a street of that character and used by such traffic;

(c) the state of repair in which a reasonable person would have expected to find the street;

(d) whether the undertaker knew, or could reasonably have been expected to know, that the condition of the part of the street to which the action relates was likely to cause danger to users of the street; and

(e) where the undertaker could not reasonably have been expected to repair that part of the street before the cause of action arose, what warning notices of its condition had been displayed,

but for the purposes of such a defence it is not relevant that the undertaker had arranged for a competent person to carry out or supervise the maintenance of that part of the street to which the action relates unless it is also proved that the undertaker had given that person proper instructions with regard to the maintenance of the street and that those instructions had been carried out.

(7) Paragraphs ‎(2) to ‎(6) do not apply where the undertaker is the street authority for a street in which the works are being carried out.

Section 11Temporary prohibition or restriction of use of streets and public rights of way

(1) The undertaker, during and for the purposes of constructing or maintaining the authorised development, may temporarily prohibit the use of, restrict the use of, authorise the use of, alter or divert any street or public right of way and may for any reasonable time—

(a) divert the traffic or a class of traffic from the street or public right of way;

(b) authorise the use of motor vehicles on classes of public rights of way where, notwithstanding the provisions of this article, there is otherwise no public right to use motor vehicles; and

(c) subject to paragraph ‎(2) , prevent all persons from passing along the street or public right of way.

(2) The undertaker must provide reasonable access for pedestrians going to or from premises abutting a street or public right of way affected by the temporary prohibition, restriction, alteration or diversion of a street or public right of way under this article if there would otherwise be no such access.

(3) Without prejudice to the generality of paragraph ‎(1) , the undertaker may temporarily prohibit the use of, authorise the use of, restrict the use of, alter or divert—

(a) the streets specified in column 2 of the table in Part 1 (temporary prohibition or restriction of the use of streets) of Schedule 6 (streets and public rights of way) to the extent specified in column 3 of that table;

(b) the public rights of way specified in column 2 of the table in Part 2 (temporary prohibition or restriction of public rights of way with diversion) of Schedule 6 (streets and public rights of way) to the extent specified in column 3 of that table; and

(c) the public rights of way specified in column 2 of the table in Part 3 (temporary prohibition or restriction of public rights of way) of Schedule 6 (streets and public rights of way) to the extent specified in column 3 of that table; and

(4) The undertaker must not temporarily prohibit the use of, authorise the use of, restrict the use of, alter or divert—

(a) any street or public right of way specified in paragraph ‎(3) without first consulting the street authority; and

(b) any other street or public right of way without the consent of the street authority, and the street authority may attach reasonable conditions to any such consent.

(5) Any person who suffers loss by the suspension of any street or private right of way under this article is entitled to compensation to be determined, in case of dispute, under Part 1 (determination of questions of disputed compensation) of the 1961 Act.

(6) Without prejudice to the scope of paragraph ‎(1) , the undertaker may use any street or public right of way the use of which has been temporarily prohibited, restricted, altered or diverted under the powers conferred by this article and within the Order limits as a temporary working site.

(7) In this article expressions used both in this article and in the 1984 Act have the same meaning as in that Act.

Section 12Use of private roads

(1) The undertaker may use any private road within the Order limits for the passage of persons or vehicles (with or without materials, plant and machinery) for the purposes of, or in connection with, the construction or maintenance of the authorised development.

(2) The undertaker must compensate the person liable for the repair of a road to which paragraph ‎(1) applies for any loss or damage which that person may suffer by reason of the exercise of the power conferred by paragraph ‎(1) .

(3) Any dispute as to a person’s entitlement to compensation under paragraph ‎(2) , or as to the amount of such compensation, is to be determined under Part 1 (determination of questions of disputed compensation) of the 1961 Act.

Section 13Access to works

The undertaker may, for the purposes of the authorised development—

(a) form and lay out the permanent means of access, or improve existing means of access, in the locations specified in Part 1 (permanent means of access to works) of Schedule 7 (access to works);

(b) form and lay out the temporary means of access in the location specified in Part 2 (temporary means of access) of Schedule 7 (access to works); and

(c) with the approval of the relevant planning authority after consultation with the highway authority, form and lay out such other means of access or improve existing means of access, at such locations within the Order limits as the undertaker reasonably requires for the purposes of the authorised development.

Section 14Agreements with street authorities

(1) A street authority and the undertaker may enter into agreements with respect to—

(a) the strengthening, improvement, repair or reconstruction of any street under the powers conferred by this Order;

(b) any prohibition, restriction, alteration or diversion of a street authorised by this Order;

(c) the undertaking in the street of any of the works referred to in article ‎8 (street works) and article ‎10(1) (construction and maintenance of altered streets); or

(d) the adoption by a street authority which is the highway authority of works—

(i) undertaken on a street which is existing public maintainable highway; or

(ii) which the undertaker and highway authority agree to be adopted as public maintainable highway.

(2) If such agreement provides that the street authority must undertake works on behalf of the undertaker the agreement may, without prejudice to the generality of paragraph ‎(1) —

(a) make provision for the street authority to carry out any function under this Order which relates to the street in question;

(b) specify a reasonable time for the completion of the works; and

(c) contain such terms as to payment and otherwise as the parties consider appropriate.

Section 15Traffic regulation measures

(1) Subject to the provisions of this article the undertaker may at any time, in the interests of safety and for the purposes of, or in connection with, the construction of the authorised development, temporarily place traffic signs and signals in the extents of the road specified in column 2 of the table in Schedule 8 (traffic regulation measures) and the placing of those traffic signs and signals is deemed to have been permitted by the traffic authority for the purposes of section 65 of the 1984 Act and the Traffic Signs Regulations and General Directions 2016 .

(2) Subject to the provisions of this article and without limitation to the exercise of the powers conferred by paragraph ‎(1) , the undertaker may make temporary provision for the purposes of the construction of the authorised development—

(a) as to the speed at which vehicles may proceed along any road;

(b) permitting, prohibiting or restricting the stopping, waiting, loading or unloading of vehicles on any road;

(c) as to the prescribed routes for vehicular traffic or the direction or priority of vehicular traffic on any road;

(d) permitting, prohibiting or restricting the use by vehicular traffic or non-vehicular traffic of any road; and

(e) suspending or amending in whole or in part any order made, or having effect as if made, under the 1984 Act.

(3) No speed limit imposed by or under this Order applies to vehicles falling within regulation 3(4) of the Road Traffic Exemptions (Special Forces) (Variation and Amendment) Regulations 2011 when in accordance with regulation 3(5) of those regulations.

(4) Before exercising the power conferred by paragraph ‎(2) the undertaker must—

(a) consult with the chief officer of police in whose area the road is situated; and

(b) obtain the written consent of the traffic authority.

(5) The undertaker must not exercise the powers in paragraphs ‎(1) or ‎(2) unless it has—

(a) given not less than four weeks’ notice in writing of its intention so to do to the chief officer of police and to the traffic authority in whose area the road is situated; and

(b) not less than seven days before the provision is to take effect published the undertaker’s intention to make the provision in one or more newspapers circulating in the area in which any road to which the provision relates is situated; and

(c) displayed a site notice containing the same information at each end of the length of road affected.

(6) Any provision made under the powers conferred by paragraphs ‎(1) or ‎(2) of this article may be suspended, varied or revoked by the undertaker from time to time by subsequent exercise of the powers conferred by paragraph ‎(1) or ‎(2) .

(7) Any provision made by the undertaker under paragraphs ‎(1) or ‎(2) —

(a) must be made by written instrument in such form as the undertaker considers appropriate;

(b) has effect as if duly made by the traffic authority in whose area the road is situated as a traffic regulation order under the 1984 Act and the instrument by which it is effected may specify specific savings and exemptions to which the provision is subject; and

(c) is deemed to be a traffic order for the purposes of Schedule 7 to the Traffic Management Act 2004 (road traffic contraventions subject to civil enforcement).

Section 16Discharge of water

(1) Subject to paragraphs ‎(3) , ‎(4) and ‎(7) the undertaker may use any watercourse or any public sewer or drain for the drainage of water in connection with the construction or maintenance of the authorised development and for that purpose may lay down, take up and alter pipes and may, on any land within the Order limits, make openings into, and connections with, the watercourse, public sewer or drain.

(2) Any dispute arising from the making of connections to or the use of a public sewer or drain by the undertaker under paragraph ‎(1) is to be determined as if it were a dispute under section 106 (right to communicate with public sewers) of the Water Industry Act 1991 .

(3) The undertaker must not discharge any water into any watercourse, public sewer or drain except with the consent of the person to whom it belongs whose consent may be given subject to terms and conditions as that person may reasonably impose.

(4) The undertaker must not make any opening into any public sewer or drain except—

(a) in accordance with plans approved by the person to whom the sewer or drain belongs; and

(b) where that person has been given the opportunity to supervise the making of the opening.

(5) Where the undertaker discharges water into, or makes any opening into, a watercourse, public sewer or drain belonging to or under the control of a drainage authority, the provisions of Part 8 of Schedule 15 (protective provisions) apply in substitution for the provisions of paragraphs ‎(3) and ‎(4) .

(6) The undertaker must take such steps as are reasonably practicable to secure that any water discharged into a watercourse or public sewer or drain pursuant to this article is as free as may be practicable from gravel, soil or other solid substance, oil or matter in suspension.

(7) This article does not authorise the entry into controlled waters of any matter whose entry or discharge into controlled waters requires a licence pursuant to the Environmental Permitting (England and Wales) Regulations 2016 .

(8) In this article—

(a) “ drainage authority ” means the drainage board concerned within the meaning of section 23 of the Land Drainage Act 1991 ;

(b) “ public sewer or drain ” means a sewer or drain which belongs to Homes England, the Environment Agency, an internal drainage board, a joint planning board, a local authority, a National Park Authority, a sewerage undertaker or an urban development corporation; and

(c) other expressions, excluding watercourse, used both in this article and in the Water Resources Act 1991 have the same meaning as in that Act.

Section 17Protective works to buildings

(1) Subject to the following provisions of this article, the undertaker may at its own expense carry out such protective works to any building lying within the Order land as the undertaker considers necessary or expedient.

(2) Protective works may be carried out—

(a) at any time before or during the construction of any part of the authorised development in the vicinity of the building; or

(b) after the completion of that part of the authorised development in the vicinity of the building at any time up to the end of the period of five years beginning with the date of final commissioning of that part of the authorised development.

(3) For the purpose of determining how the powers under this article are to be exercised, the undertaker may enter and survey any building falling within paragraph ‎(1) and any land within its curtilage.

(4) For the purpose of carrying out protective works under this article to a building, the undertaker may (subject to paragraphs ‎(5) and ‎(6) )—

(a) enter the building and any land within its curtilage; and

(b) where the works cannot be carried out reasonably conveniently without entering land which is adjacent to the building but outside its curtilage, enter the adjacent land (but not any building erected on it).

(5) Before exercising—

(a) a right under paragraph ‎(1) to carry out protective works to a building;

(b) a right under paragraph ‎(3) to enter a building and land within its curtilage;

(c) a right under paragraph ‎(4)(a) to enter a building and land within its curtilage;

(d) a right under paragraph ‎(4)(b) to enter land,

the undertaker must, except in the case of emergency, serve on the owners and occupiers of the building or land not less than 14 days’ notice of its intention to exercise that right and, in a case falling within sub-paragraph ‎(a) , ‎(c) or ‎(d) , specifying the protective works proposed to be carried out.

(6) Where a notice is served under paragraph ‎(5)(a) , ‎(5)(c) or ‎(5)(d) , the owner or occupier of the building or land concerned may, by serving a counter-notice within the period of 10 days beginning with the day on which the notice was served, require the question whether it is necessary or expedient to carry out the protective works or to enter the building or land to be referred to arbitration under article ‎42 (arbitration).

(7) The undertaker must compensate the owners and occupiers of any building or land in relation to which rights under this article have been exercised for any loss or damage arising to them by reason of the exercise of those rights.

(8) Where—

(a) protective works are carried out under this article to a building; and

(b) within the period of five years beginning with the date of final commissioning of the relevant part of the authorised development it appears protective works are inadequate to protect the building against damage caused by the construction or use of that part of the authorised development,

the undertaker must compensate the owners and occupiers of the building for any loss or damage sustained by them.

(9) Nothing in this article relieves the undertaker from any liability to pay compensation under section 10(2) (compensation for injurious affection) of the 1965 Act.

(10) Any compensation payable under paragraph ‎(7) or ‎(8) must be determined, in case of dispute, under Part 1 (determination of questions of disputed compensation) of the 1961 Act.

(11) Section 13 (refusal to give possession to acquiring authority) of the 1965 Act applies to the entry onto, or possession of, land under this article to the same extent as it applies to the compulsory acquisition of land under this Order by virtue of section 125 (application of compulsory acquisition provisions) of the 2008 Act.

(12) In this article “ protective works ” in relation to a building means—

(a) underpinning, strengthening and any other works the purpose of which is to prevent damage which may be caused to the building by the construction, maintenance or use of the authorised development; and

(b) any works the purpose of which is to remedy any damage which has been caused to the building by the construction, maintenance or use of the authorised development.

Section 18Authority to survey and investigate the land

(1) The undertaker may for the purposes of this Order enter on any land shown within the Order limits or enter on any land which may be affected by the authorised development or enter on any land upon which entry is required in order to carry out monitoring or surveys in respect of the authorised development and—

(a) survey or investigate the land;

(b) without prejudice to the generality of sub-paragraph ‎(a) , make trial holes or bore holes in such positions on the land as the undertaker thinks fit to investigate the nature of the surface layer and subsoil and groundwater and remove soil and groundwater samples;

(c) without prejudice to the generality of sub-paragraph ‎(a) , carry out ecological or archaeological investigations on such land, including the digging of trenches; and

(d) place on, leave on and remove from the land apparatus for use in connection with the survey and investigation of land and making of trial holes, bore holes or trenches.

(2) No land may be entered or equipment placed or left on or removed from the land under paragraph ‎(1) unless at least 14 days’ notice has been served on every owner and occupier of the land.

(3) Any person entering land under this article on behalf of the undertaker—

(a) must, if so required before entering the land, produce written evidence of their authority to do so; and

(b) may take with them such vehicles and equipment as are necessary to carry out the survey or investigation or to make the trial holes.

(4) No trial holes are to be made under this article—

(a) in land located within the highway boundary without the consent of the highway authority; or

(b) in a private street without the consent of the street authority.

(5) The undertaker must compensate the owners and occupiers of the land for any loss or damage arising by reason of the exercise of the authority conferred by this article, such compensation to be determined, in case of dispute, under Part 1 (determination of questions of disputed compensation) of the 1961 Act.

(6) Section 13 (refusal to give possession to acquiring authority) of the 1965 Act applies to the entry onto, or possession of, land under this article to the same extent as it applies to the compulsory acquisition of land under this Order by virtue of section 125 (application of compulsory acquisition provisions) of the 2008 Act.

Section 19Compulsory acquisition of land

(1) The undertaker may acquire compulsorily so much of the Order land as is required for the authorised development or to facilitate, or as is incidental, to it.

(2) This article is subject to article 20 (time limit for exercise of authority to acquire land compulsorily), paragraph ‎(2) of article ‎22 (compulsory acquisition of rights), article 25 (acquisition of subsoil only), article 28 (rights under or over streets), article ‎29 (temporary use of land for constructing the authorised development), article ‎31 (statutory undertakers) and article 47 (Crown rights).

Section 20Time limit for exercise of authority to acquire land compulsorily

(1) After the end of the period of five years beginning on the day on which this Order is made—

(a) no notice to treat is to be served under Part 1 (compulsory purchase under Acquisition of Land Act 1981) of the 1965 Act; and

(b) no declaration is to be executed under section 4 (execution of declaration) of the 1981 Act as applied by article ‎24 (application of the 1981 Act).

(2) The authority conferred by article ‎29 (temporary use of land for constructing the authorised development) ceases at the end of the period referred to in paragraph ‎(1) , except that nothing in this paragraph prevents the undertaker remaining in possession of land after the end of that period, if the land was entered and possession was taken before the end of that period.

(3) The applicable period for the purposes of section 4 of the 1965 Act (time limit for giving notice to treat) and section 5A of the 1981 Act (time limit for general vesting declaration) (as modified by this Order) is the period of five years beginning on the day on which this Order is made.

Section 21Compulsory acquisition of land – incorporation of the mineral code

Parts 2 and 3 of Schedule 2 (minerals) to the Acquisition of Land Act 1981 are incorporated into this Order subject to the modifications that—

(a) for “the acquiring authority” substitute “the undertaker” ;

(b) for the “undertaking” substitute “authorised development” ; and

(c) paragraph 8(3) is not incorporated.

Section 22Compulsory acquisition of rights

(1) Subject to paragraph ‎(2) and article ‎29 (temporary use of land for constructing the authorised development), the undertaker may acquire compulsorily such rights over the Order land or impose such restrictive covenants over the Order land as may be required for any purpose for which that land may be acquired under article 19 (compulsory acquisition of land), by creating them as well as by acquiring rights already in existence.

(2) Subject to the provisions of this paragraph, article ‎23 (private rights) and article ‎31 (statutory undertakers), in the case of the Order land specified in column 1 of the table in Schedule 9 (land in which only new rights etc. may be acquired) the undertaker’s powers of compulsory acquisition are limited to the acquisition of existing rights and the benefit of restrictive covenants over that land and the creation and acquisition of such new rights and the imposition of restrictive covenants for the purpose specified in relation to that land in column 2 of the table in that Schedule.

(3) Subject to section 8 (other provisions as to divided land) and Schedule 2A (counter-notice requiring purchase of land) of the 1965 Act (as substituted by paragraph ‎ 5(8) of Schedule 10 (modification of compensation and compulsory purchase enactments for the creation of new rights and imposition of new restrictive covenants)), where the undertaker creates or acquires an existing right over land or the benefit of a restrictive covenant under paragraph ‎(1) or ‎(2) , the undertaker is not required to acquire a greater interest in that land.

(4) Schedule 10 (modification of compensation and compulsory purchase enactments for the creation of new rights and imposition of new restrictive covenants) has effect for the purpose of modifying the enactments relating to compensation and the provisions of the 1965 Act in their application in relation to the compulsory acquisition under this article of a right over land by the creation of a new right or the imposition of a restrictive covenant.

(5) In any case where the acquisition of new rights or imposition of a restrictive covenant under paragraph ‎(1) or ‎(2) is required for the purpose of diverting, replacing or protecting apparatus of a statutory undertaker, the undertaker may, with the consent of the Secretary of State, transfer the power to acquire such rights or impose restrictive covenants to the statutory undertaker in question.

(6) The exercise by a statutory undertaker of any power in accordance with a transfer under paragraph ‎(5) is subject to the same restrictions, liabilities and obligations as would apply under this Order if that power were exercised by the undertaker.

(7) This article is subject to article 47 (Crown rights).

Section 23Private rights

(1) Subject to the provisions of this article, all private rights and restrictive covenants over land subject to compulsory acquisition under this Order are extinguished—

(a) from the date of acquisition of the land, or of the right, or of the benefit of the restrictive covenant by the undertaker, whether compulsorily or by agreement or through the grant of a lease of the land by agreement ; or

(b) on the date of entry on the land by the undertaker under section 11(1) (power of entry) of the 1965 Act,

whichever is the earliest.

(2) Subject to the provisions of this article, all private rights or restrictive covenants over land subject to the compulsory acquisition of rights or the imposition of restrictive covenants under article ‎22 (compulsory acquisition of rights) cease to have effect in so far as their continuance would be inconsistent with the exercise of the right or compliance with the restrictive covenant—

(a) as from the date of the acquisition of the right or imposition of the restrictive covenant by the undertaker (whether the right is acquired compulsorily, by agreement or through the grant of a lease of the land by agreement); or

(b) on the date of entry on the land by the undertaker under section 11(1) (power of entry) of the 1965 Act in pursuance of the right,

whichever is the earliest.

(3) Subject to the provisions of this article, all private rights or restrictive covenants over land of which the undertaker takes temporary possession under this Order are suspended and unenforceable, in so far as their continuance would be inconsistent with the purpose for which temporary possession is taken, for as long as the undertaker remains in lawful possession of the land.

(4) Any person who suffers loss by the extinguishment or suspension of any private right or restrictive covenant under this article is entitled to compensation in accordance with the terms of section 152 (compensation in case where no right to claim in nuisance) of the 2008 Act to be determined, in case of dispute, under Part 1 of the 1961 Act.

(5) This article does not apply in relation to any right to which section 138 (extinguishment of rights, and removal of apparatus, of statutory undertakers etc.) of the 2008 Act or article ‎31 (statutory undertakers) applies.

(6) Paragraphs ‎(1) to ‎(3) have effect subject to—

(a) any notice given by the undertaker before—

(i) the completion of the acquisition of the land or the acquisition of rights or the imposition of restrictive covenants over or affecting the land;

(ii) the undertaker’s appropriation of the land;

(iii) the undertaker’s entry onto the land; or

(iv) the undertaker’s taking temporary possession of the land,

that any or all of those paragraphs do not apply to any right specified in the notice; or

(b) any agreement made at any time between the undertaker and the person in or to whom the right in question is vested or belongs.

(7) If an agreement referred to in paragraph ‎(6)(b)—

(a) is made with a person in or to whom the right is vested or belongs; and

(b) is expressed to have effect also for the benefit of those deriving title from or under that person,

(c) the agreement is effective in respect of the persons so deriving title, whether that title was derived before or after the making of the agreement.

(8) References in this article to private rights over land include any right of way, trust, incident, restrictive covenant, easement, liberty, privilege, right or advantage annexed to land and adversely affecting other land, including any natural right to support; and include restrictions as to the user of land arising by virtue of a contract, agreement or undertaking having that effect.

Section 24Application of the 1981 Act

(1) The 1981 Act applies as if this Order were a compulsory purchase order.

(2) The 1981 Act, as applied by paragraph ‎(1) , has effect with the following modifications.

(3) In section 1 (application of the Act), for subsection 2 substitute—

(2) This section applies to any Minister, any local or other public authority or any other body or person authorised to acquire land by means of a compulsory purchase order.

(4) In section 5(2) (earliest date for execution of declaration) omit the words from “and this subsection” to the end.

(5) In section 5B(1) (extension of time limit during challenge) for “section 23 of the Acquisition of Land Act 1981 (application to High Court in respect of compulsory purchase order)” substitute “section 118 (legal challenges relating to applications for orders granting development consent) of the 2008 Act” .

(6) In section 6 (notices after extension of declaration), in subsection (1)(b) for “section 15 of, or paragraph 6 of Schedule 1 to, the Acquisition of Land Act 1981” substitute “section 134 (notice of authorisation of compulsory acquisition) of the Planning Act 2008” .

(7) In section 7 (constructive notice to treat), in subsection (1)(a) omit the words “(as modified by section 4 of the Acquisition of Land Act 1981)”.

(8) In Schedule A1 (counter-notice requiring purchase of land not in general vesting declaration), for paragraph 1(2) substitute—

(2) But see article ‎25(3) (acquisition of subsoil only) of the West Burton Solar Project Order 2025, which excludes the acquisition of subsoil only from this Schedule.

(9) References to the 1965 Act in the 1981 Act must be construed as references to the 1965 Act as applied by section 125 (application of compulsory acquisition provisions) of the 2008 Act (and as modified by article ‎27 (modification of Part 1 of the Compulsory Purchase Act 1965)) to the compulsory acquisition of land under this Order.

Section 25Acquisition of subsoil only

(1) The undertaker may acquire compulsorily so much of, or such rights in, the subsoil of the land referred to in paragraph (1) of article 19 (compulsory acquisition of land) or article ‎22 (compulsory acquisition of rights) as may be required for any purpose for which that land may be acquired under that provision instead of acquiring the whole of the land.

(2) Where the undertaker acquires any part of, or rights in, the subsoil of land, the undertaker is not required to acquire an interest in any other part of the land.

(3) The following do not apply in connection with the exercise of the power under paragraph ‎(1) in relation to subsoil only—

(a) Schedule 2A (counter-notice requiring purchase of land not in notice to treat) to the 1965 Act (as substituted pursuant to paragraph ‎ 5(8) of Schedule 10 (modification of compensation and compulsory purchase enactments for the creation of new rights and imposition of new restrictive covenants));

(b) Schedule A1 (counter-notice requiring purchase of land not in general vesting declaration) to the 1981 Act; and

(c) section 153(4A) (blighted land: proposed acquisition of part interest; material detriment test) of the 1990 Act.

(4) Paragraphs ‎(2) and ‎(3) are to be disregarded where the undertaker acquires a cellar, vault, arch or other construction forming part of a house, building or manufactory.

Section 26Power to override easements and other rights

(1) Any authorised activity which takes place on land within the Order land (whether the activity is undertaken by the undertaker or by any person deriving title from the undertaker or by any contractors, servants or agents of the undertaker) is authorised by this Order if it is done in accordance with the terms of this Order, notwithstanding that it involves—

(a) an interference with an interest or right to which this article applies; or

(b) a breach of a restriction as to the user of land arising by virtue of a contract.

(2) In this article “ authorised activity ” means—

(a) the erection, construction or maintenance of any part of the authorised development;

(b) the exercise of any power authorised by the Order; or

(c) the use of any land within the Order land (including the temporary use of land).

(3) The interests and rights to which this article applies include any easement, liberty, privilege, right or advantage annexed to land and adversely affecting other land, including any natural right to support and include restrictions as to the user of land arising by virtue of a contract.

(4) Where an interest, right or restriction is overridden by paragraph ‎(1) , compensation—

(a) is payable under section 7 (measure of compensation in case of severance) or 10 (further provision as to compensation for injurious affection) of the 1965 Act; and

(b) is to be assessed in the same manner and subject to the same rules as in the case of other compensation under those sections where—

(i) the compensation is to be estimated in connection with a purchase under that Act; or

(ii) the injury arises from the execution of works on or use of land acquired under that Act.

(c) Where a person deriving title under the undertaker by whom the land in question was acquired—

(i) is liable to pay compensation by virtue of paragraph ‎(4) ; and

(ii) fails to discharge that liability,

the liability is enforceable against the undertaker.

(5) Nothing in this article is to be construed as authorising any act or omission on the part of any person which is actionable at the suit of any person on any grounds other than such an interference or breach as is mentioned in paragraph ‎(1) .

Section 27Modification of Part 1 of the Compulsory Purchase Act 1965

(1) Part 1 of the 1965 Act (compulsory acquisition under Acquisition of Land Act 1981), as applied to this Order by section 125 (application of compulsory acquisition provisions) of the 2008 Act, is modified as follows.

(2) In section 4A(1) (extension of time limit during challenge) for “section 23 of the Acquisition of Land Act 1981 (application to High Court in respect of compulsory purchase order)” substitute “section 118 (legal challenges relating to applications for orders granting development consent) of the Planning Act 2008” .

(3) In section 11A (powers of entry: further notice of entry)—

(a) in subsection (1)(a), after “land” insert “under that provision” ; and

(b) in subsection (2), after “land” insert “under that provision” .

(4) In Schedule 2A (counter-notice requiring purchase of land not in notice to treat)—

(a) for paragraphs 1(2) and 14(2) substitute—

(2) But see article ‎25(3) (acquisition of subsoil only) of the West Burton Solar Project Order 2025, which excludes the acquisition of subsoil only from this Schedule.

(b) after paragraph 29 insert—

INTERPRETATION

(30) In this Schedule, references to entering on and taking possession of land do not include doing so under article 17 (protective works to buildings), article ‎29 (temporary use of land for constructing the authorised development) or article ‎30 (temporary use of land for maintaining the authorised development) of the West Burton Solar Project Order 2025.

Section 28Rights under or over streets

(1) The undertaker may enter on, appropriate and use so much of the subsoil of or airspace over any street within the Order limits as may be required for the purposes of the authorised development and may use the subsoil or airspace for those purposes or any other purpose ancillary to the authorised development.

(2) Subject to paragraph ‎(3) , the undertaker may exercise any power conferred by paragraph ‎(1) in relation to a street without being required to acquire any part of the street or any easement or right in the street.

(3) Paragraph ‎(2) does not apply in relation to—

(a) any subway or underground building; or

(b) any cellar, vault, arch or other construction in, on or under a street which forms part of a building fronting onto the street.

(4) Subject to paragraph ‎(5) , any person who is an owner or occupier of land appropriated under paragraph ‎(1) without the undertaker acquiring any part of that person’s interest in the land, and who suffers loss as a result, is entitled to compensation to be determined, in case of dispute, under Part 1 (determination of questions of disputed compensation) of the 1961 Act.

(5) Compensation is not payable under paragraph ‎(4) to any person who is an undertaker to whom section 85 (sharing cost of necessary measures) of the 1991 Act applies in respect of measures of which the allowable costs are to be borne in accordance with that section.

Section 29Temporary use of land for constructing the authorised development

(1) The undertaker may, in connection with the construction of the authorised development—

(a) enter on and take temporary possession of—

(i) so much of the land specified in column (1) of the table in Schedule 11 (land of which temporary possession may be taken) for the purpose specified in relation to the land in column (2) of that table; and

(ii) any other Order land in respect of which no notice of entry has been served under section 11 (powers of entry) of the 1965 Act and no declaration has been made under section 4 (execution of declaration) of the 1981 Act;

(b) remove any buildings, agricultural plant and apparatus, drainage, fences, debris and vegetation from that land;

(c) construct temporary works (including means of access), haul roads, security fencing, bridges, structures and buildings on that land;

(d) use the land for the purposes of a temporary working site with access to the working site in connection with the authorised development;

(e) construct any works on that land as are mentioned in Schedule 1 (authorised development); and

(f) carry out mitigation works required under the requirements in Schedule 2 (requirements).

(2) Paragraph ‎(1) does not authorise the undertaker to take temporary possession of—

(a) any house or garden belonging to a house; or

(b) any building (other than a house) if it is for the time being occupied.

(3) Not less than 14 days before entering on and taking temporary possession of land under this article the undertaker must serve notice of the intended entry on the owners and occupiers of the land.

(4) The undertaker must not, without the agreement of the owners of the land, remain in possession of any land under this article—

(a) in the case of the land referred to in paragraph ‎(1)(a)(i) after the end of the period of one year beginning with the date of final commissioning of the part of the authorised development for which temporary possession of the land was taken; or

(b) in the case of land referred to in paragraph ‎(1)(a)(ii) after the end of the period of one year beginning with the date of final commissioning of the part of the authorised development for which temporary possession of the land was taken unless the undertaker has, before the end of that period, served a notice of entry under section 11 of the 1965 Act or made a declaration under section 4 of the 1981 Act in relation to that land.

(5) Unless the undertaker has served notice of entry under section 11 of the 1965 Act or made a declaration under section 4 of the 1981 Act or otherwise acquired the land or rights over land subject to temporary possession, the undertaker must before giving up possession of land of which temporary possession has been taken under this article, remove all works and restore the land to the reasonable satisfaction of the owners of the land; but the undertaker is not required to—

(a) replace any building, structure, debris, drain or electric line removed under this article;

(b) remove any drainage works installed by the undertaker under this article;

(c) remove any new road surface or other improvements carried out under this article to any street specified in Schedule 4 (streets subject to street works), Schedule 5 (alteration of streets) or Schedule 7 (access to works);

(d) remove any fencing or boundary treatments installed by the undertaker under this article to replace or enhance existing fencing or boundary treatments; or

(e) restore the land on which any works have been carried out under paragraph ‎(1)(f) insofar as the works relate to mitigation works identified in the environmental statement or required pursuant to the requirements in Schedule 2 (requirements).

(6) The undertaker must pay compensation to the owners and occupiers of land of which temporary possession is taken under this article for any loss or damage arising from the exercise in relation to the land of the provisions of any power conferred by this article.

(7) Any dispute as to a person’s entitlement to compensation under paragraph ‎(6) , or as to the amount of the compensation, must be determined under Part 1 (determination of questions of disputed compensation) of the 1961 Act.

(8) Nothing in this article affects any liability to pay compensation under section 152 (compensation in case where no right to claim in nuisance) of the 2008 Act or under any other enactment in respect of loss or damage arising from the carrying out of the authorised development, other than loss or damage for which compensation is payable under paragraph ‎(6) .

(9) Where the undertaker takes possession of land under this article, the undertaker is not required to acquire the land or any interest in it.

(10) The undertaker must not compulsorily acquire, acquire new rights over or impose restrictive covenants over, the land referred to in paragraph ‎(1)(a)(i) under this Order.

(11) Nothing in this article precludes the undertaker from—

(a) creating and acquiring new rights or imposing restrictions over any part of the Order land identified in Schedule 9 (land in which only new rights etc. may be acquired); or

(b) acquiring any part of the subsoil of (or rights in the subsoil of) that land under article ‎25 (acquisition of subsoil only) or any part of the subsoil of or airspace over that land under article ‎28 (rights under or over streets).

(12) Section 13 (refusal to give possession to acquiring authority) of the 1965 Act applies to the temporary use of land under this article to the same extent as it applies to the compulsory acquisition of land under this Order by virtue of section 125 (application of compulsory acquisition provisions) of the 2008 Act.

(13) Nothing in this article prevents the taking of temporary possession more than once in relation to any land that the undertaker takes temporary possession of under this article.

Section 30Temporary use of land for maintaining the authorised development

(1) Subject to paragraph ‎(2) , at any time during the maintenance period relating to any part of the authorised development, the undertaker may—

(a) enter on and take temporary possession of any land within the Order land if such possession is reasonably required for the purpose of maintaining the authorised development;

(b) enter on any land within the Order land for the purpose of gaining such access as is reasonably required for the purpose of maintaining the authorised development; and

(c) construct such temporary works (including the provision of means of access) and buildings on the land as may be reasonably necessary for that purpose.

(2) Paragraph ‎(1) does not authorise the undertaker to take temporary possession of—

(a) any house or garden belonging to a house; or

(b) any building (other than a house) if it is for the time being occupied.

(3) Not less than 28 days before entering on and taking temporary possession of land under this article the undertaker must serve notice of the intended entry on the owners and occupiers of the land.

(4) The undertaker may only remain in possession of land under this article for so long as may be reasonably necessary to carry out the maintenance of the part of the authorised development for which possession of the land was taken.

(5) Before giving up possession of land of which temporary possession has been taken under this article, the undertaker must remove all temporary works and restore the land to the reasonable satisfaction of the owners of the land.

(6) The undertaker must pay compensation to the owners and occupiers of land of which temporary possession is taken under this article for any loss or damage arising from the exercise in relation to the land of the provisions of this article.

(7) Any dispute as to a person’s entitlement to compensation under paragraph ‎(6) , or as to the amount of compensation, must be determined under Part 1 (determination of questions of disputed compensation) of the 1961 Act.

(8) Nothing in this article affects any liability to pay compensation under section 152 (compensation in case where no right to claim in nuisance) of the 2008 Act or under any other enactment in respect of loss or damage arising from the maintenance of the authorised development, other than loss or damage for which compensation is payable under paragraph ‎(6) .

(9) Where the undertaker takes possession of land under this article, the undertaker is not required to acquire the land or any interest in it.

(10) Section 13 (refusal to give possession to acquiring authority) of the 1965 Act applies to the temporary use of land under this article to the same extent as it applies to the compulsory acquisition of land under this Order by virtue of section 125 (application of compulsory acquisition provisions) of the 2008 Act.

(11) In this article “ the maintenance period ” means the period of five years beginning with the date of final commissioning of the part of the authorised development for which temporary possession is required under this article except where maintenance relates to landscaping in which case “ the maintenance period ” means such period as is set out in the landscape and ecological management plan which is approved by the relevant planning authority pursuant to requirement ‎7 , beginning with the date on which that part of the landscaping is completed.

Section 31Statutory undertakers

Subject to the provisions of Schedule 15 (protective provisions) the undertaker may—

(a) acquire compulsorily, or acquire new rights or impose restrictive covenants over, the land belonging to statutory undertakers shown on the land plan within the Order land; and

(b) extinguish the rights of, remove , relocate the rights of or reposition the apparatus belonging to statutory undertakers over or within the Order land.

Section 32Apparatus and rights of statutory undertakers in stopped up streets

Where a street is altered or diverted or its use is temporarily prohibited or restricted under article ‎8 (street works), article ‎9 (power to alter layout, etc., of streets), article ‎10 (construction and maintenance of altered streets) or article ‎11 (temporary prohibition or restriction of use of streets and public rights of way) any statutory undertaker whose apparatus is under, in, on, along or across the street has the same powers and rights in respect of that apparatus, subject to Schedule 15 (protective provisions), as if this Order had not been made.

Section 33Recovery of costs of new connections

(1) Where any apparatus of a public utility undertaker or of a public communications provider is removed under article ‎31 (statutory undertakers) any person who is the owner or occupier of premises to which a supply was given from that apparatus is entitled to recover from the undertaker compensation in respect of expenditure reasonably incurred by that person, in consequence of the removal, for the purpose of effecting a connection between the premises and any other apparatus from which a supply is given.

(2) Paragraph ‎(1) does not apply in the case of the removal of a public sewer but where such a sewer is removed under article ‎31 (statutory undertakers), any person who is—

(a) the owner or occupier of premises the drains of which communicated with that sewer; or

(b) the owner of a private sewer which communicated with that sewer,

is entitled to recover from the undertaker compensation in respect of expenditure reasonably incurred by that person, in consequence of the removal, for the purpose of making the drain or sewer belonging to that person communicate with any other public sewer or with a private sewerage disposal plant.

(3) This article does not have effect in relation to apparatus to which Part 3 (street works in England and Wales) of the 1991 Act applies.

(4) In this article—

“ public communications provider ” has the same meaning as in section 151(1) (interpretation of Chapter 1) of the Communications Act 2003 ; and

“ public utility undertaker ” has the same meaning as in the 1980 Act.

Section 34Benefit of the Order

(1) Subject to paragraph ‎(2) and article ‎35 (consent to transfer the benefit of the Order), the provisions of this Order have effect solely for the benefit of the undertaker.

(2) Paragraph ‎(1) does not apply to Work No. 4 in respect of which the provisions of this Order are for the benefit of the undertaker and National Grid.

Section 35Consent to transfer the benefit of the Order

(1) Subject to the powers of this Order, the undertaker may—

(a) transfer to another person (“ the transferee ”) any or all of the benefit of the provisions of this Order and such related statutory rights as may be agreed between the undertaker and the transferee; and

(b) grant to another person (“ the lessee ”) for a period agreed between the undertaker and the lessee any or all of the benefit of the provisions of this Order and such related statutory rights as may be so agreed.

(2) Where a transfer or grant has been made references in this Order to the undertaker, except in paragraph ‎(8) , are to include references to the transferee or lessee.

(3) The consent of the Secretary of State is required for the exercise of the powers of paragraph ‎(1) except where—

(a) the transferee or lessee is the holder of a licence under section 6 (licences authorising supply etc.) of the 1989 Act;

(b) in respect of Work No. 5B, the transferee or lessee is the undertaker as defined in the Cottam Solar Project Order, the Gate Burton Energy Park Order, or the Tillbridge Solar Order; or

(c) the time limits for claims for compensation in respect of the acquisition of land or effects upon land under this Order have elapsed and—

(i) no such claims have been made;

(ii) any such claim has been made and has been compromised or withdrawn;

(iii) compensation has been paid in full and final settlement of any such claim;

(iv) payment of compensation into court has taken place in lieu of settlement of any such claim; or

(v) it has been determined by a tribunal or court of competent jurisdiction in respect of any such claim that no compensation is payable.

(4) Where the consent of the Secretary of State is not required, the undertaker must notify the Secretary of State and the relevant planning authorities in writing before transferring or granting a benefit referred to in paragraph ‎(1) .

(5) The notification referred to in paragraph ‎(4) must state—

(a) the name and contact details of the person to whom the benefit of the powers will be transferred or granted;

(b) subject to paragraph ‎(6) , the date on which the transfer will take effect;

(c) the powers to be transferred or granted;

(d) pursuant to paragraph ‎(8) , the restrictions, liabilities and obligations that will apply to the person exercising the powers transferred or granted; and

(e) where relevant, a plan showing the works or areas to which the transfer or grant relates.

(6) The date specified under paragraph ‎(5)(b) must not be earlier than the expiry of ten working days from the date of the receipt of the notification.

(7) The notification given must be signed by the undertaker and the person to whom the benefit of the powers will be transferred or granted as specified in that notification.

(8) Where the undertaker has transferred any benefit, or for the duration of any period during which the undertaker has granted any benefit—

(a) the benefit transferred or granted (“the transferred benefit”) must include any rights that are conferred, and any obligations that are imposed, by virtue of the provisions to which the benefit relates;

(b) the transferred benefit will reside exclusively with the transferee or, as the case may be, the lessee and the transferred benefit will not be enforceable against the undertaker; and

(c) the exercise by a person of any benefits or rights conferred in accordance with any transfer or grant is subject to the same restrictions, liabilities and obligations as would apply under this Order if those benefits or rights were exercised by the undertaker.

Section 36Application of landlord and tenant law

(1) This article applies to—

(a) any agreement for leasing to any person the whole or any part of the authorised development or the right to operate the same; and

(b) any agreement entered into by the undertaker with any person for the construction, maintenance, use or operation of the authorised development, or any part of it,

so far as any such agreement relates to the terms on which any land which is the subject of a lease granted by or under that agreement is to be provided for that person’s use.

(2) No enactment or rule of law regulating the rights and obligations of landlords and tenants prejudices the operation of any agreement to which this article applies.

(3) Accordingly, no such enactment or rule of law applies in relation to the rights and obligations of the parties to any lease granted by or under any such agreement, so as to—

(a) exclude or in any respect modify any of the rights and obligations of those parties under the terms of the lease, whether with respect to the termination of the tenancy or any other matter;

(b) confer or impose on any such party any right or obligation arising out of or connected with anything done or omitted on or in relation to land which is the subject of the lease, in addition to any such right or obligation provided for by the terms of the lease; or

(c) restrict the enforcement (whether by action for damages or otherwise) by any party to the lease of any obligation of any other party under the lease.

Section 37Operational land for the purposes of the 1990 Act

Development consent granted by this Order is to be treated as specific planning permission for the purposes of section 264(3) (cases in which land is to be treated as operational land) of the 1990 Act.

Section 38Felling or lopping of trees and removal of hedgerows

(1) Subject to paragraph (3) and article 39 (trees subject to tree preservation order), the undertaker may fell or lop any tree or shrub near any part of the authorised development or cut back its roots, if it reasonably believes it to be necessary to do so to prevent the tree or shrub from—

(a) obstructing or interfering with the construction, maintenance or operation of the authorised development or any apparatus used in connection with the authorised development;

(a) constituting a danger to persons using the authorised development;

(b) obstructing or interfering with the passage of construction vehicles to the extent necessary for the purposes of construction of the authorised development.

(2) The undertaker may, for the purposes of the authorised development or in connection with the authorised development and subject to paragraph (3) remove part of the hedgerows specified in column 2 of the table in Part 1, column 2 of the table in Part 2 and column 2 of the table in Part 3 of Schedule 12 (hedgerows to be removed) to the extent set out in the landscape and ecological management plan approved pursuant to requirement ‎7 in Schedule 2 (requirements).

(3) In carrying out any activity authorised by paragraphs ‎(1) or (2) the undertaker must do no unnecessary damage to any tree or shrub or hedgerow and must pay compensation to any person for any loss or damage arising from such activity.

(4) Any dispute as to a person’s entitlement to compensation under paragraph (3) , or as to the amount of compensation, is to be determined under Part 1 (determination of questions of disputed compensation) of the 1961 Act.

(5) The undertaker may not pursuant to paragraphs ‎(1) and ‎(2) fell or lop a tree or remove hedgerows within the extent of the publicly maintainable highway without the prior consent of the highway authority.

(6) In this article “ hedgerow ” has the same meaning as in the Hedgerows Regulations 1997 .

Section 39Trees subject to tree preservation orders

(1) The undertaker may, if it reasonably believes it to be necessary to do so in order to prevent the tree from obstructing or interfering with the construction, maintenance or operation of the authorised development or any apparatus used in connection with the authorised development, fell or lop or cut back the roots of any tree that is subject to a tree preservation order and is—

(a) described in the outline landscape and ecological management plan;

(b) described in the landscape and ecological management plan approved pursuant to Requirement ‎ 7; or

(c) located within or overhanging land within the Order limits provided the tree preservation order is made after the date the landscape and ecological management plan is approved pursuant to Requirement ‎ 7.

(2) In carrying out any activity authorised by paragraph ‎(1) —

(a) the undertaker must do no unnecessary damage to any tree and must pay compensation to any person for any loss or damage arising from such activity; and

(b) the duty contained in section 206(1) (replacement of trees) of the 1990 Act does not apply.

(3) The authority given by paragraph ‎(1) constitutes a deemed consent under the relevant tree preservation order.

(4) Any dispute as to a person’s entitlement to compensation under paragraph ‎(2) , or as to the amount of compensation, is to be determined under Part 1 (determination of questions of disputed compensation) of the 1961 Act.

Section 40Certification of plans and documents, etc.

(1) The undertaker must, as soon as practicable after the making of this Order, submit to the Secretary of State copies of all documents and plans listed in the table at Part 1 of Schedule 13 (documents and plans to be certified) for certification that they are true copies of the documents referred to in this Order.

(2) Before submitting the documents and plans in accordance with paragraph ‎(1) , the undertaker must substitute or supplement, as the case may be, the documents listed in column 1 of the table at Part 2 of Schedule 13 (documents and plans to be certified) with the documents listed in column 2 of that table.

(3) A plan or document so certified is admissible in any proceedings as evidence of the contents of the document of which it is a copy.

Section 41No double recovery

Compensation is not payable in respect of the same matter both under this Order and under any enactment, any contract or any rule of law.

Section 42Arbitration

(1) Any difference under any provision of this Order, unless otherwise provided for, is to be referred to and settled in arbitration in accordance with the rules set out in Schedule 14 (arbitration rules) of this Order, by a single arbitrator to be agreed upon by the parties within 14 days of receipt of the notice of arbitration, or if the parties fail to agree within the time period stipulated, to be appointed on application of either party (after giving written notice to the other) by the Secretary of State.

(2) Any matter for which the consent or approval of the Secretary of State is required under any provision of this Order is not subject to arbitration.

Section 43Protective provisions

Schedule 15 (protective provisions) has effect.

Section 44Service of notices

(1) A notice or other document required or authorised to be served for the purposes of this Order may be served—

(a) by post;

(b) by delivering it to the person on whom it is to be served or to whom it is to be given or supplied; or

(c) with the consent of the recipient and subject to paragraphs ‎(6) to ‎(8) , by electronic transmission.

(2) Where the person on whom a notice or other document to be served for the purposes of this Order is a body corporate, the notice or document is duly served if it is served on the secretary or clerk of that body.

(3) For the purposes of section 7 (references to service by post) of the Interpretation Act 1978 as it applies for the purposes of this article, the proper address of any person in relation to the service on that person of a notice or document under paragraph ‎(1) is, if that person has given an address for service, that address and otherwise—

(a) in the case of the secretary or clerk of a body corporate, the registered or principal office of that body; and

(b) in any other case, the last known address of that person at that time of service.

(4) Where for the purpose of this Order a notice or other document is required or authorised to be served on a person as having an interest in, or as the occupier of, land and the name or address of that person cannot be ascertained after reasonable enquiry, the notice may be served by—

(a) addressing it to that person by the description of “owner”, or as the case may be “occupier” of the land (describing it); and

(b) either leaving it in the hands of the person who is or appears to be resident or employed on the land or leaving it conspicuously affixed to some building or object on or near the land.

(5) Where a notice or other document required to be served or sent for the purposes of this Order is served or sent by electronic transmission the requirement is to be taken to be fulfilled only where—

(a) the recipient of the notice or other document to be transmitted has given consent to the use of electronic transmission in writing or by electronic transmission;

(b) the notice or document is capable of being accessed by the recipient;

(c) the notice or document is legible in all material respects; and

(d) the notice or document is in a form sufficiently permanent to be used for subsequent reference.

(6) Where the recipient of a notice or other document served or sent by electronic transmission notifies the sender within seven days of receipt that the recipient requires a paper copy of all or any part of that notice or other document the sender must provide such a copy as soon as reasonably practicable.

(7) Any consent to the use of an electronic transmission by a person may be revoked by that person in accordance with paragraph ‎(8) .

(8) Where a person is no longer willing to accept the use of electronic transmission for any of the purposes of this Order—

(a) that person must give notice in writing or by electronic transmission revoking any consent given by that person for that purpose; and

(b) such revocation is final and takes effect on a date specified by the person in the notice but that date must not be less than seven days after the date on which the notice is given.

(9) This article does not exclude the employment of any method of service not expressly provided for by it.

Section 45Procedure in relation to certain approvals etc.

(1) Where an application is made to or request is made of a consenting authority for any consent, agreement or approval required or contemplated by any of the provisions of the Order (not including the requirements), such consent, agreement or approval to be validly given, must be given in writing.

(2) Where paragraph ‎(1) applies to any consent, agreement or approval, such consent, agreement or approval must not be unreasonably withheld or delayed.

(3) Schedule 16 (procedure for discharge of requirements) has effect in relation to all consents, agreements or approvals required, granted, refused or withheld in relation to the requirements.

(4) Save for applications made pursuant to Schedule 16 (procedure for discharge of requirements) and where stated to the contrary if, within ten weeks (or such longer period as may be agreed between the undertaker and the relevant consenting authority in writing) after the application or request has been submitted to a consenting authority it has not notified the undertaker of its disapproval and the grounds of disapproval, it is deemed to have approved the application or request.

(5) Where any application is made as described in paragraph ‎(1) , the undertaker must include a statement in such application that refers to the timeframe for consideration of the application and the consequences of failure to meet that timeframe as prescribed by paragraph ‎(4) .

(6) Schedule 16 (procedure for discharge of requirements) does not apply in respect of any consents, agreements or approvals contemplated by the provisions of Schedule 15 (protective provisions) or any dispute under article ‎17(6) (protective works to buildings) to which paragraph ‎(4) applies.

(7) In this article “ consenting authority ” means the relevant planning authority, highway authority, traffic authority, street authority, the owner of a watercourse, sewer or drain or the beneficiary of any of the protective provisions contained in Schedule 15 (protective provisions).

Section 46Guarantees in respect of payment of compensation

(1) The undertaker must not exercise the powers conferred by the provisions referred to in paragraph ‎(2) in relation to any part of the Order land unless it has first put in place either—

(a) a guarantee, the form and amount of which has been approved by the Secretary of State in respect of the liabilities of the undertaker to pay compensation pursuant to the provisions referred to in paragraph ‎(2) in respect of the exercise of the relevant provision in relation to that part of the Order land; or

(b) an alternative form of security, the form and amount of which has been approved by the Secretary of State in respect of the liabilities of the undertaker to pay compensation pursuant to the provisions referred to in paragraph ‎(2) in respect of the exercise of the relevant provision in relation to that part of the Order land.

(2) The provisions are—

(a) article 19 (compulsory acquisition of land);

(b) article ‎22 (compulsory acquisition of rights);

(c) article ‎23 (private rights);

(d) article ‎28 (rights under or over streets);

(e) article ‎29 (temporary use of land for constructing the authorised development);

(f) article ‎30 (temporary use of land for maintaining the authorised development); and

(g) article ‎31 (statutory undertakers).

(3) A guarantee or alternative form of security given in respect of any liability of the undertaker to pay compensation under this Order is to be treated as enforceable against the guarantor or person providing the alternative form of security by any person to whom such compensation is payable and must be in such a form as to be capable of enforcement by such a person.

(4) Nothing in this article requires a guarantee or alternative form of security to be in place for more than 15 years after the date on which the relevant power is exercised.

Section 47Crown rights

(1) Nothing in this Order affects prejudicially any estate, right, power, privilege, authority or exemption of the Crown and, in particular, nothing in this Order authorises the undertaker or any transferee, lessee or licensee to take, use, enter upon or in any manner interfere with any land or rights of any description (including any portion of the shore or bed of the sea or any river, channel, creek, bay or estuary)—

(a) belonging to His Majesty in right of the Crown and forming part of The Crown Estate without the consent in writing of the Crown Estate Commissioners;

(b) belonging to His Majesty in right of the Crown and not forming part of The Crown Estate without the consent in writing of the government department having the management of that land; or

(c) belonging to a government department or held in trust for His Majesty for the purposes of a government department without the consent in writing of that government department.

(2) Paragraph ‎(1) does not apply to the exercise of any right under this Order for the compulsory acquisition of an interest in land (as defined in the 2008 Act) which is for the time being held otherwise than by or on behalf of the Crown.

(3) A consent under paragraph ‎(1) may be given unconditionally or subject to terms and conditions and is deemed to have been given in writing where it is sent electronically.

Section 1Interpretation

In this Schedule—

“ energy storage ” means equipment used for the storage of electrical energy;

“ inverter ” means electrical equipment required to convert direct current power to alternating current;

“ mounting structure ” means a frame or rack made of galvanised steel, anodised aluminium or other material designed to support the solar modules;

“ National Grid West Burton substation ” means the existing 400kV substation at West Burton Power Station, owned and operated by National Grid;

“ solar module ” means a solar photovoltaic panel or module designed to convert solar irradiance to electrical energy;

“ substation ” means a substation containing electrical equipment required to switch, transform, convert electricity and provide reactive power consumption;

“ switchgear ” means a combination of electrical disconnect switches, fuses or circuit breakers used to control, protect and isolate electrical equipment; and

“ transformer ” means a structure serving to transform electricity to a different voltage.

Section 2Authorised Development

In the District of West Lindsey and in the County of Lincolnshire a nationally significant infrastructure project as defined in sections 14 and 15 of the 2008 Act and associated development under section 115(1)(b) of the 2008 Act.

The nationally significant infrastructure project comprises the following works—

Work No. 1 —

(a) Work No. 1A — a ground mounted solar photovoltaic generating station with a gross electrical output capacity of over 50 megawatts including—

(i) solar modules fitted to mounting structures;

(ii) DC electrical cabling and combiner DC boxes;

(iii) conversion units including inverters, transformers, switchgear, and monitoring and control systems; and

(iv) electrical and communications cabling connecting Work No. 1A(iii) to Work No. 3A.

(b) Work No. 1B — a ground mounted solar photovoltaic generating station with a gross electrical output capacity of over 50 megawatts including—

(i) solar modules fitted to mounting structures;

(ii) DC electrical cabling and combiner DC boxes;

(iii) conversion units including inverters, transformers, switchgear, and monitoring and control systems; and

(iv) electrical and communications cabling connecting Work No. 1B(iii) to Work No. 3B.

(c) Work No. 1C — a ground mounted solar photovoltaic generating station with a gross electrical output capacity of over 50 megawatts including—

(i) solar modules fitted to mounting structures;

(ii) DC electrical cabling and combiner DC boxes;

(iii) conversion units including inverters, transformers, switchgear, and monitoring and control systems; and

(iv) electrical and communications cabling connecting Work No. 1C(iii) to Work No. 3C.

and associated development within the meaning of section 115(1)(b) of the 2008 Act comprising—

Work No. 2 — an energy storage facility comprising—

(a) battery energy storage cells with automatic fire suppression system or dry pipe sprinkler system;

(b) a structure protecting the battery energy storage cells comprised in Work No. 2(a) and ancillary equipment, being either one container or multiple containers joined to each other, mounted on a reinforced concrete foundation slab or concrete piling;

(c) interconnection units including heating, ventilation and air conditioning or liquid cooling systems and temperature management either housed within the containers comprised in Work No. 2(b), attached to the side or top of each of the containers, or located separate from but near to each of the containers;

(d) conversion units including inverters, transformers, switchgear and energy management system;

(e) monitoring and control systems housed within a container with Work No. 2(c) or located separately in its own container or control room;

(f) electrical cabling including electrical cables connecting Work No. 2 to Work No. 3C;

(g) bunded impermeable surface to manage surface water drainage;

(h) water storage facility for the purposes of firefighting water supply; and

(i) bunded impermeable surface and associated infrastructure to contain used firewater.

Work No. 3 — works in connection with onsite substations including—

(a) Work No. 3A — a substation with works comprising—

(i) an up to 132kV substation, with associated transformer bays, feeder bays, transformers, switchgear buildings and ancillary equipment including reactive power units;

(ii) control building or container relay rooms with associated offices, storage and welfare facilities;

(iii) monitoring and control systems for Work Nos. 1A and 3A;

(iv) maintenance compound;

(v) electrical cabling; and

(vi) earthworks, including soil stripping and site levelling.

(b) Work No. 3B — a substation with works comprising—

(i) an up to 132kV substation, with associated transformer bays, feeder bays, transformers, switchgear buildings and ancillary equipment including reactive power units;

(ii) control building or container relay rooms with associated offices, storage and welfare facilities;

(iii) monitoring and control systems for Work Nos. 1B and 3B;

(iv) maintenance compound;

(v) electrical cabling; and

(vi) earthworks, including soil stripping and site levelling.

(c) Work No. 3C — a substation with works comprising—

(i) an up to 400kV substation, with associated transformer bays, feeder bays, transformers, switchgear buildings and ancillary equipment including reactive power units;

(ii) control building or container relay rooms with associated offices, storage and welfare facilities;

(iii) monitoring and control systems for Work Nos. 1C and 3C;

(iv) maintenance compound;

(v) electrical cabling; and

(vi) earthworks, including soil stripping and site levelling.

Section 3Authorised Development

In the Districts of West Lindsey and Bassetlaw and in the Counties of Lincolnshire and Nottinghamshire a nationally significant infrastructure project as defined in sections 14 and 15 of the 2008 Act and associated development under section 115(1)(b) of the 2008 Act, comprising the following works—

Work No. 4 — works to the National Grid substation to facilitate connection of the authorised development to the National Grid including extending main busbar 4 and reserve busbar 3/4 gas zones to allow for the connection of a new GIS substation bay comprising—

(a) a 400kV 3phase 4000A circuit breaker for control and protection of the outgoing circuit serving the authorised development;

(b) a 3phase set of current transformers for protection of the new outgoing 400kV feeder circuit and the overlap with the National Grid system;

(c) a 3phase high accuracy metering current and voltage transformer assembly for commercial metering of the connection;

(d) a 3phase 400kV line disconnector/earth switch for isolation and earthing of the outgoing 400kV feeder circuit;

(e) a 3phase set of 400kV high voltage cable sealing ends and cables connecting the National Grid substation with Work No. 5;

(f) a 3phase power quality ready capacitor voltage transformer; and

(g) provision of a stand-alone building to house duplicate feeder protection systems, commercial metering systems, protection and control equipment and user remote control and data acquisition apparatus.

Work No. 5 — works in connection with electrical cabling including—

(a) Work No. 5A — works to lay electrical cables, accesses, and temporary construction laydown areas for the electrical cables including—

(i) high voltage electrical cables connecting Work No. 3C to Work No. 4;

(ii) high voltage electrical cables connecting Work No. 3C to Work No. 3A;

(iii) high voltage electrical cables connecting Work No. 3C to Work No. 3B;

(iv) laying down of access tracks, ramps, footpaths, roads, including the laying and construction of drainage infrastructure, signage and information boards;

(v) joint bays, link boxes, cable ducts, cable protection, joint protection, manholes, marker posts, underground cable marker, tiles and tape, communications chambers, fibre optic cables and lighting and other works associated with cable laying;

(vi) tunnelling, boring and drilling works; and

(vii) temporary construction and decommissioning laydown areas comprising—

(aa) areas of hardstanding, compacted ground or track matting;

(bb) car parking;

(cc) area to store materials and equipment;

(dd) site and welfare offices and workshops;

(ee) security infrastructure, including cameras, perimeter fencing and lighting;

(ff) safety infrastructure to manage traffic when crossing roads or other obstacles;

(gg) site drainage and waste management infrastructure (including sewerage); and

(hh) electricity, water, waste water and telecommunications connections.

(b) Work No. 5B — works to lay electrical cables, accesses, and temporary construction laydown areas for the electrical cables including—

(i) high voltage electrical cables connecting Work No. 3C to Work No. 4;

(ii) laying down of access tracks, ramps, footpaths, roads, including the laying and construction of drainage infrastructure, signage and information boards;

(iii) joint bays, link boxes, cable ducts, cable protection, joint protection, manholes, marker posts, underground cable marker, tiles and tape, communication chambers, fibre optic cables and lighting and other works associated with cable laying.

(iv) tunnelling, boring and drilling works; and

(v) temporary construction and decommissioning laydown areas comprising—

(aa) areas of hardstanding, compacted ground or track matting;

(bb) car parking;

(cc) area to store materials and equipment;

(dd) site and welfare offices and workshops;

(ee) security infrastructure, including cameras, perimeter fencing and lighting;

(ff) safety infrastructure to manage traffic when crossing roads or other obstacles;

(gg) site drainage and waste management infrastructure (including sewerage); and

(hh) electricity, water, waste water and telecommunications connections.

Work No. 6 — works including—

(a) Work No. 6A — works including—

(i) fencing, gates, boundary treatment and other means of enclosure;

(ii) works for the provision of security and monitoring measures including CCTV columns, lighting columns and lighting, cameras, weather stations, communication infrastructure, and perimeter fencing;

(iii) landscaping and biodiversity mitigation and enhancement measures including planting;

(iv) improvement, maintenance and use of existing private tracks;

(v) laying down of internal access tracks, ramps, means of access and footpaths;

(vi) temporary footpath diversions;

(vii) earthworks;

(viii) sustainable drainage system ponds, runoff outfalls, general drainage and irrigation infrastructure and improvements or extensions to existing drainage and irrigation systems;

(ix) acoustic barriers;

(x) electricity and telecommunications connections; and

(xi) secondary temporary construction and decommissioning laydown areas.

(b) Work No. 6B — works including—

(i) fencing, gates, boundary treatment and other means of enclosure;

(ii) works for the provision of security and monitoring measures including CCTV columns, lighting columns and lighting, cameras, weather stations, communication infrastructure, and perimeter fencing;

(iii) landscaping and biodiversity mitigation and enhancement measures including planting;

(iv) improvement, maintenance and use of existing private tracks;

(v) laying down of internal access tracks, ramps, means of access and footpaths;

(vi) temporary footpath diversions;

(vii) earthworks;

(viii) sustainable drainage system ponds, runoff outfalls, general drainage and irrigation infrastructure and improvements or extensions to existing drainage and irrigation systems;

(ix) acoustic barriers;

(x) electricity and telecommunications connections; and

(xi) secondary temporary construction and decommissioning laydown areas.

(c) Work No. 6C — works including—

(i) fencing, gates, boundary treatment and other means of enclosure;

(ii) works for the provision of security and monitoring measures including CCTV columns, lighting columns and lighting, cameras, weather stations, communication infrastructure, and perimeter fencing;

(iii) landscaping and biodiversity mitigation and enhancement measures including planting;

(iv) improvement, maintenance and use of existing private tracks;

(v) laying down of internal access tracks, ramps, means of access and footpaths;

(vi) temporary footpath diversions;

(vii) earthworks;

(viii) sustainable drainage system ponds, runoff outfalls, general drainage and irrigation infrastructure and improvements or extensions to existing drainage and irrigation systems;

(ix) acoustic barriers;

(x) electricity and telecommunications connections; and

(xi) temporary construction and decommissioning laydown areas.

Work No. 7 — temporary construction and decommissioning laydown areas including—

(a) Work No. 7A — temporary construction and decommissioning laydown areas comprising—

(i) areas of hardstanding;

(ii) car parking;

(iii) site and welfare offices and workshops;

(iv) security infrastructure, including cameras, perimeter fencing and lighting;

(v) area to store materials and equipment;

(vi) site drainage and waste management infrastructure (including sewerage); and

(vii) electricity, water, waste water and telecommunications connections.

(b) Work No. 7B — temporary construction and decommissioning laydown area comprising—

(i) areas of hardstanding;

(ii) car parking;

(iii) site and welfare offices and workshops;

(iv) security infrastructure, including cameras, perimeter fencing and lighting;

(v) area to store materials and equipment;

(vi) site drainage and waste management infrastructure (including sewerage); and

(vii) electricity, water, waste water and telecommunications connections.

(c) Work No. 7C — temporary construction and decommissioning laydown area comprising—

(i) areas of hardstanding;

(ii) car parking;

(iii) site and welfare offices and workshops;

(iv) security infrastructure, including cameras, perimeter fencing and lighting;

(v) area to store materials and equipment;

(vi) site drainage and waste management infrastructure (including sewerage); and

(vii) electricity, water, waste water and telecommunications connections.

Work No. 8 — works to facilitate access to Work Nos. 1 to 7 and 9 to 11 including—

(a) Work No. 8A — works to facilitate temporary construction and decommissioning access to Work Nos. 1 to 7 and 9 to 11 including—

(i) creation of accesses from the public highway;

(ii) creation of visibility splays;

(iii) works to alter the layout of any street or highway temporarily; and

(iv) offsite works adjacent to highways land including those to structures, boundary features, drainage features on private land required for the facilitation of movement of abnormal indivisible loads associated with Work Nos. 3 and 5.

(b) Work No. 8B — works to facilitate permanent access to Work Nos. 1 to 6 and 9 to 11 including—

(i) creation of accesses from the public highway;

(ii) creation of visibility splays; and

(iii) works to alter the layout of any street or highway permanently.

Work No. 9 — works to create and maintain habitat management areas, including—

(a) fencing, gates, boundary treatment and other means of enclosure;

(b) earth works including bunds, embankments, ponds, trenching and swales;

(c) landscaping and biodiversity mitigation and enhancement measures including planting;

(d) means of access; and

(e) drainage.

Work No. 10 — works to create and maintain a habitat management area, comprising—

(a) fencing, gates, boundary treatment and other means of enclosure;

(b) landscaping and biodiversity mitigation and enhancement measures including planting;

(c) improvement, maintenance and use of existing private tracks;

(d) earthworks;

(e) drainage; and

(f) means of access.

Work No. 11 — creation of a permissive footpath comprising—

(a) creation of a permissive footpath from the track off Sykes Lane along the Codder Lane Belt and then south and west to re-join Sykes Lane opposite Hardwick Scrub;

(b) fencing, gates, boundary treatment and other means of enclosure; and

(c) landscaping and biodiversity mitigation and enhancement measures including planting.

In connection with and in addition to Work Nos. 1 to 11 further associated development within the Order limits including—

(a) fencing, gates, boundary treatment and other means of enclosure;

(b) bunds, embankments, trenching and swales;

(c) works to the existing irrigation system and works to alter the position and extent of such irrigation system;

(d) surface water drainage systems, storm water attenuation systems including storage basins, oil water separators, including channelling and culverting and works to existing drainage networks;

(e) electrical, gas, water, foul water drainage and telecommunications infrastructure connections, diversions and works to, and works to alter the position of, such services and utilities connections;

(f) works to alter the course of, or otherwise interfere with, non-navigable rivers, streams or watercourses;

(g) ramps, bridges and other means of access;

(h) works for the provision of security and monitoring measures such as CCTV columns, lighting columns and lighting, cameras, lightning protection masts, weather stations, storage containers, communication infrastructure, and perimeter fencing;

(i) improvement, maintenance and use of existing private tracks;

(j) temporary footpath diversions and footpath enhancement;

(k) landscaping and related works;

(l) habitat creation and enhancement;

(m) site establishments and preparation works including site clearance (including vegetation removal, demolition of existing buildings and structures); earthworks (including soil stripping and storage and site levelling) and excavations; the alteration of the position of services and utilities; and works for the protection of buildings and land;

(n) works to maintain and repair streets and access roads;

(o) tunnelling, boring and drilling works; and

(p) other works to mitigate any adverse effects of the construction, maintenance, operation or decommissioning of the authorised development,

and further associated development comprising such other works or operations as may be necessary or expedient for the purposes of or in connection with the construction, operation and maintenance of the authorised development which are within the Order limits and fall within the scope of work assessed in the environmental statement.

353 sections

Cite this legislation

The West Burton Solar Project Order 2025 (legislation.gov.uk, OGL v3.0). Retrieved via LawPlayer, https://lawplayer.com/uk/act/uksi-2025-116 (accessed 2026-07-07)

Contains public sector information licensed under the Open Government Licence v3.0.

OGL-3

本頁資料來源:legislation.gov.uk (The National Archives)·整理提供:法律人 LawPlayer· lawplayer.com