The title of this Order is the Glyn Rhonwy Pumped Storage Generating Station (Amendment) (Wales) Order 2021 and it comes into force on 19 November 2021.
資料由法律人 LawPlayer整理提供·UK legislation / curated by LawPlayer from legislation.gov.uk
Statutory Instrument
The Glyn Rhonwy Pumped Storage Generating Station (Amendment) (Wales) Order 2021
Section 1Citation and commencement
Section 2Amendment to the Glyn Rhonwy Pumped Storage Generating Station Order 2017
(1) The Glyn Rhonwy Pumped Storage Generating Station Order 2017 (“ the 2017 Order ”) is amended as follows.
(2) For paragraph 2 of Part 2 of Schedule 1 to the 2017 Order substitute “The authorised development must be commenced no later than 29 March 2024.” .
2 sections
Cite this legislation
The Glyn Rhonwy Pumped Storage Generating Station (Amendment) (Wales) Order 2021 (legislation.gov.uk, OGL v3.0). Retrieved via LawPlayer, https://lawplayer.com/uk/act/wsi-2021-1284 (accessed 2026-07-07)
Contains public sector information licensed under the Open Government Licence v3.0.
本頁資料來源:legislation.gov.uk (The National Archives)·整理提供:法律人 LawPlayer· lawplayer.com