Statutory Instrument

The M3 Motorway (Compton—Bassett Section) Scheme 1987

Citation
S.I. 1987/1367
As at
Sections
5
Section 1

The Secretary of State is authorised to provide along the route described in the Schedule to this Scheme a special road for the use of traffic of Classes I and II of the classes of traffic set out in Schedule 4 to the Highways Act 1980.

Section 2

The centre line of the special road is indicated by a heavy black line on the deposited plan.

Section 3

The special road, except insofar as its route follows the route of any existing trunk road, shall become a trunk road on the date when this Scheme comes into force.

Section 4

In this Scheme—

(1) all measurements of distance are measured along the route of the relevant highway;

(2)

(i) “the deposited plan”

(ii) “the special road”

Section 5

This Scheme shall come into force on 21st August 1987 and may be cited as the M3 Motorway (Compton—Bassett Section) Scheme 1987.

5 sections

Cite this legislation

The M3 Motorway (Compton—Bassett Section) Scheme 1987 (legislation.gov.uk, OGL v3.0). Retrieved via LawPlayer, https://lawplayer.com/uk/act/uksi-1987-1367