法律人 LawPlayer logo

資料由法律人 LawPlayer整理提供·UK legislation / curated by LawPlayer from legislation.gov.uk

Statutory Instrument

The Highland Regional Council (Abhainn Mhungasdail) Water Order 1992

Citation
S.I. 1992/998
As at
Sections
7
Section 1Citation and commencement

This Order may be cited as the Highland Regional Council (Abhainn Mhungasdail) Water Order 1992 and shall come into force on 20th April 1992.

Section 2Interpretation

In this Order—

“ the Act ” means the Water (Scotland) Act 1980;

“approved” means approved by the Secretary of State;

“the Council” means the Highland Regional Council as water authority;

“day” means a period of 24 hours reckoned from midnight;

“deposited plans” means the two plans, each prepared in duplicate, docqueted and signed as relative to this Order and marked respectively “The Highland Regional Council (Abhainn Mhungasdail) Water Order 1992 Plan of Catchment Area” and “The Highland Regional Council (Abhainn Mhungasdail) Water Order 1992 Plans & Sections of Works”, one copy of each of which is deposited in the Scottish Office, New St Andrew’s House, Edinburgh, and the other in the office of the Chief Executive of the Council at Inverness;

“gauge” includes a gauge weir or other apparatus for measuring the flow of water;

“intake” includes any work by which water is taken by the Council for the purposes of the undertaking;

“undertaking” means the water undertaking for the time being of the Council;

“works” means the works described in Schedule 1 to this Order which the Council, in exercise of the powers conferred on them by section 21 of the Act, and in the lines and situations and according to the levels shown on the deposited plans, propose to construct and maintain for the purpose of providing a supply of water when they have acquired the necessary land or sufficient rights therein.

Section 3Incorporation and application of provisions of Schedule 4 to the Act

The provisions of sections 2 and 10(3) and (4) of Schedule 4 to the Act , modified and adapted to read as set out in Schedule 2 to this Order, shall apply to the undertaking in so far as affected by the provisions of this Order, and the terms used in those provisions, as so modified and adapted, which are defined in this Order, shall have the same meaning as in this Order.

Section 4Water rights

Subject to the provisions of this Order, the Council may, for the purposes of the undertaking and by means of an intake pipe (Work No.3), take water from the stream known as the Abhainn Mhungasdail in the Lochaber District of the Highland Region.

Section 5Water rights

(1) During the construction of the works the Council may take from the said Abhainn Mhungasdail such water as they may require for such construction.

(2) After the completion of the works the Council shall not—

(a) take any water from the said Abhainn Mhungasdail so as to reduce the rate of flow therein below 386 cubic metres per day as measured through or over an approved gauge (part of Work No.1);

(b) in any one day take from the said Abhainn Mhungasdail a quantity of water greater than 50 cubic metres as measured through or over an approved gauge (part of Work No.2).

Section 6Water rights

If the power to take water conferred by this Order has not been exercised within ten years from the date on which this Order comes into force the said power shall cease.

Section 7Miscellaneous

The Council shall at all times after the expiration of six months from the date on which this Order comes into force keep at the office of the Chief Executive of the Council a copy thereof and a copy of each of the deposited plans.

7 sections

Cite this legislation

The Highland Regional Council (Abhainn Mhungasdail) Water Order 1992 (legislation.gov.uk, OGL v3.0). Retrieved via LawPlayer, https://lawplayer.com/uk/act/uksi-1992-998

Contains public sector information licensed under the Open Government Licence v3.0.

OGL-3

本頁資料來源:legislation.gov.uk (The National Archives)·整理提供:法律人 LawPlayer· lawplayer.com