Statutory Instrument

The Utilities Act 2000 (Commencement No. 3 and Transitional Provisions) Order 2000

Citation
S.I. 2000/2974
As at
Sections
12
Section 1Citation and interpretation

(1) This Order may be cited as the Utilities Act 2000 (Commencement No. 3 and Transitional Provisions) Order 2000.

(2) In this Order—

“ the Act ” means the Utilities Act 2000;

“the Electricity Act ” means the Electricity Act 1989 ; and

“the Gas Act ” means the Gas Act 1986 .

(3) In this Order (save where the context otherwise requires) references to sections and Schedules are references to sections of and Schedules to the Act.

Section 2Provisions of the Act commenced by this Order

Subject to articles 3 to 12, 7th November 2000 is the appointed day for the coming into force of the provisions of the Act listed in the first column of the Schedule to this Order for the purposes set out in the second column.

Section 3Transitional provisions

(1) Where at any time before the appointed day any individual or body consulted by the Council pursuant to section 19(4)(a) objects to the disclosure of any information relating to it the Council shall until the appointed day refrain from disclosing that information.

(2) On and after the appointed day the entirety of section 19(4) shall apply to any information which, pursuant to paragraph (1), the Council has refrained from disclosing.

(3) For the purposes of paragraphs (1) and (2), the “appointed day” means the day appointed for the coming into force of section 19(4)(b).

(4) Until the appointed day for the coming into force of section 3(1), in section 19(5) for “Authority” there is substituted “Director General of Gas Supply, the Director General of Electrical Supply”.

Section 4Transitional provisions

In section 33DA of the Gas Act (which section 20(5) inserts into that Act)—

(a) until the appointed day for the coming into force of paragraph 2(1) of Schedule 6 for “gas transporters” or “transporters” in all places where the words occur there is substituted “public gas transporters”; and

(b) until the appointed day for the coming into force of section 3(1) for “Authority” there is substituted “Director”.

Section 5Transitional provisions

In section 42AA of the Electricity Act (which section 20(6) inserts into that Act)—

(a) until the appointed day for the coming into force of paragraph 38(4) of Schedule 6, the duty of the Council to publish information relating to complaints shall relate to complaints made by consumers about any matter relating to the activities of public electricity suppliers (as defined in section 6(9) of the Electricity Act) and the holders of a licence granted under section 6(2)(a) of the Electricity Act and “complaints” in section 42AA(2) of the Electricity Act shall be construed accordingly; and

(b) until the appointed day for the coming into force of section 3(1) for “Authority” there is substituted “Director”.

Section 6Transitional provisions

(1) Where at any time before the appointed day any individual or body consulted by the Council pursuant to section 21(4)(a) objects to the publication of any information relating to it the Council shall until the appointed day refrain from publishing that information.

(2) On and after the appointed day the entirety of section 21(4) shall apply to any information which, pursuant to paragraph (1), the Council has refrained from publishing.

(3) For the purposes of paragaphs (1) and (2), the “appointed day” means the day appointed for the coming into force of section 21(4)(b).

Section 7Transitional provisions

In section 32 of the Gas Act (which section 22(1) substitutes for the original section 32 of that Act)—

(a) until the appointed day for the coming into force of section 95 for any purpose which includes the exercise by the Authority of its powers under section 30A(1) of the Gas Act (which section 95 inserts into that Act), there is omitted from the definition of “enforcement function” in subsection (10) “or 30A”; and

(b) until the appointed day for the coming into force of section 3(1) for “Authority” in each place where it appears there is substituted “Director”.

Section 8Transitional provisions

In section 46 of the Electricity Act (which section 22(2) substitutes for the original section 46 of that Act)—

(a) until the appointed day for the coming into force of section 59 for any purpose which includes the exercise by the Authority of its powers under section 27A(1) of the Electricity Act (which section 59 inserts into that Act), there is omitted from the definition of “enforcement function” in subsection (10) “or 27A”; and

(b) until the appointed day for the coming into force of section 3(1) for “Authority” in each place where it appears there is substituted “Director”.

Section 9Transitional provisions

Until the appointed day for the coming into force of section 3(1), in section 33 of the Gas Act (which section 23(1) substitutes for the original section 33 of that Act) and in section 46A of the Electricity Act (which section 23(2) inserts into that Act) for “Authority” in all places where it occurs there is substituted “Director”.

Section 10Transitional provisions

(1) Until the appointed day for the coming into force of section 3(1), in sections 105(3)(a) and 105(8)(c) for “Authority” there is substituted “Director General of Gas Supply, the Director General of Electricity Supply” and in section 105(11) for “Authority” there is substituted “Director General of Gas Supply or the Director General of Electricity Supply”.

(2) Until the appointed day for the coming into force of paragraph 29(2) of Schedule 6, in section 105(3)(b) there is omitted “or section 28(2A) of the 1989 Act”.

(3) Until the appointed day for the coming into force of paragraph 2(1) of Schedule 6, in relation to section 48 of the Gas Act, in section 105(10) in the definition of “relevant activities” for “gas transporter” there is substituted “public gas transporter”.

Section 11Transitional provisions

Until the appointed day for the coming into force of section 3(1), in paragraph 31 of Schedule 7—

(a) in sub-paragraphs (3) and (4) for “Authority” there is substituted “Director General of Gas Supply”; and

(b) in sub-paragraph (5) there is omitted “the Authority and”, for “them” there is substituted “it” and for “their” there is substituted “its”.

Section 12Transitional provisions

Until the appointed day for the coming into force of section 3(1), in paragraph 32 of Schedule 7—

(a) in sub-paragraphs (3) and (4) for “Authority” there is substituted “Director General of Electricity Supply”; and

(b) in sub-paragraph (5) there is omitted “the Authority and”, for “them” there is substituted “it” and for “their” there is substituted “its”.

12 sections

Cite this legislation

The Utilities Act 2000 (Commencement No. 3 and Transitional Provisions) Order 2000 (legislation.gov.uk, OGL v3.0). Retrieved via LawPlayer, https://lawplayer.com/uk/act/uksi-2000-2974

Contains public sector information licensed under the Open Government Licence v3.0.

OGL-3

本頁資料來源:legislation.gov.uk (The National Archives)·整理提供:法律人 LawPlayer· lawplayer.com