Section 1Citation, commencement and extent

(1) This Order may be cited as the Electricity (Exemption from the Requirement for a Generation Licence) (Scotland) Order 2005 and shall come into force on 30th November 2005.

(2) This Order does not extend to England and Wales.

Section 2Interpretation

In this Order—

“ the Act ” means the Electricity Act 1989;

“Farr generating station” means the onshore wind farm known as Farr Wind Farm situated approximately 15 kilometres south of Inverness;

“ FWL ” means Farr Windfarm Limited, registered in Scotland with number SC166005;

“licensed generator” means the holder of a licence under section 6(1)(a) of the Act;

“ MHWL ” means Mid Hill Wind Limited, registered in Scotland with number SC257734;

“Mid Hill generating station” means the onshore wind farm known as Mid Hill Wind Farm, situated at Mid Hill, Goosecruives, near Stonehaven; and

“total system in Great Britain” means all transmission systems and distribution systems, located in Great Britain, of holders of licences under sections 6(1)(b) and 6(1)(c) of the Act.

Section 3Exemption from section 4(1)(a) of the Act

(1) Exemption is granted from section 4(1)(a) of the Act to FWL in respect of the Farr generating station.

(2) Exemption is granted from section 4(1)(a) of the Act to MHWL in respect of the Mid Hill generating station.

Section 4Conditions on exemption

The exemption granted by article 3(1) to FWL is subject to compliance with the conditions specified in sub-paragraphs (a) and (b)—

(a) FWL is not a licensed generator;

(b) the Farr generating station is connected to the total system in Great Britain and is not normally capable of exporting more electrical power than 100 megawatts to that system, disregarding power temporarily provided in excess of 100 megawatts due to technical circumstances outside the reasonable control of FWL.

Section 5Conditions on exemption

The exemption granted by article 3(2) to MHWL is subject to compliance with the conditions specified in sub-paragraphs (a) and (b)—

(a) MHWL is not a licensed generator;

(b) the Mid Hill generating station is connected to the total system in Great Britain and is not normally capable of exporting more electrical power than 100 megawatts to that system, disregarding power temporarily provided in excess of 100 megawatts due to technical circumstances outside the reasonable control of MHWL.

5 sections

Cite this legislation

The Electricity (Exemption from the Requirement for a Generation Licence) (Scotland) Order 2005 (legislation.gov.uk, OGL v3.0). Retrieved via LawPlayer, https://lawplayer.com/uk/act/uksi-2005-3041

Contains public sector information licensed under the Open Government Licence v3.0.

OGL-3

本頁資料來源:legislation.gov.uk (The National Archives)·整理提供:法律人 LawPlayer· lawplayer.com