Statutory Instrument

The Electricity (Prepayment Meter) Regulations 2006

Citation
S.I. 2006/2010
As at
Sections
6
Section 1Citation and commencement

These Regulations may be cited as the Electricity (Prepayment Meter) Regulations 2006 and shall come into force on 1 st September 2006.

Section 2Interpretation

In these Regulations—

“gas supplier” means the holder of a licence under section 7A(1)(a) of the Gas Act 1986 except where the holder is acting otherwise than for purposes connected with the carrying on of activities authorised by the licence;

“ongoing gas consumption” means gas consumed after the date an agreement under regulation 4 is sent to the customer;

“prepayment meter” means an electricity prepayment meter installed by an authorised supplier through which the customer takes his supply of electricity;

“repayment amount” means the amount of each instalment to be paid towards the repayment of the sum owed;

“repayment rate” means the frequency with which instalments are to be paid towards the repayment of the sum owed; and

“sum owed” means the aggregate of sums specified under regulation 3 owed at the time an agreement under regulation 4 is sent to the customer.

Section 3Recovery of sums owed for electricity and gas

(1) A prepayment meter may be used to recover a sum that is owed to a gas supplier or an electricity supplier by a customer in respect of any one or more of the following—

(a) at any premises previously owned or occupied by the customer—

(i) the supply of gas;

(ii) the supply of electricity;

(iii) the provision of a gas meter; and

(iv) the provision of an electricity meter;

(b) the provision of a gas meter at the premises on which the prepayment meter is installed; and

(c) the supply of gas to the premises on which the prepayment meter is installed.

(2) Any sum recoverable through a prepayment meter under paragraph 12(2)(a) of Schedule 7 to the Electricity Act 1989 may be consolidated with a sum specified in regulation 3(1) and recovered under these Regulations.

Section 4The agreement

(1) An electricity supplier may not recover sums specified in regulation 3(1) by means of a prepayment meter unless it has previously entered into an agreement with the customer which complies with paragraphs (2) and (4), and, where applicable, regulations 5 and 6.

(2) The agreement must state in writing—

(a) the name of the customer;

(b) any charges that the customer will be required to pay in addition to those recovered under regulation 3; and

(c) that the electricity supplier warrants that he has, orally, provided the customer with details as required under paragraph (3).

(3) The details required by this paragraph are—

(a) other means of payment available to the customer;

(b) the operation of the prepayment meter, particularly as regards the recovery of debt and charging for ongoing consumption; and

(c) the implications of failing to make any payments in full or in part when they fall due under the agreement.

(4) The agreement must include written terms to the following effect—

(a) that the customer can give a notice of cancellation to the electricity supplier;

(b) where notice of cancellation is given, the agreement shall be treated as if it had not been made;

(c) notice of cancellation can be given orally or in writing and must be given within seven working days beginning with the day on which the customer receives written terms of the agreement; and

(d) either party can terminate the agreement on provision of 30 days' oral or written notice.

Section 5Collection of the sum owed

Where the prepayment meter is being used to recover a sum owed the agreement must include in writing—

(a) the amount of each element of the sum owed and to what it relates;

(b) the repayment rate and repayment amount;

(c) the date at which the sum owed will be fully repaid if the repayment amount is paid at the repayment rate;

(d) a term that the repayment rate and repayment amount have been calculated by the supplier to take into account the customer’s ability to pay the total of all charges to be recovered through the prepayment meter;

(e) a term that the customer has agreed to the repayment rate and repayment amount; and

(f) a term that the repayment rate and repayment amount can only be varied—

(i) at the customer’s request and if agreed by the electricity supplier; or

(ii) by the supplier in accordance with sub-paragraph (d) and with prior notice given to the customer.

Section 6Collection for ongoing gas consumption

Where the prepayment meter is being used to recover a sum that is owed under regulation 3(1)(c) for ongoing gas consumption the agreement must include in writing—

(a) the amount and frequency of payments required for ongoing gas consumption;

(b) a term that the supplier will make reasonable endeavours to obtain gas meter readings at least every six months;

(c) a term that the supplier will adjust the amount and frequency of payments required for ongoing gas consumption to reflect the gas meter readings obtained; and

(d) a term that when adjusting the amount and frequency of payments under sub-paragraph (c) the supplier shall first give notice of the adjustments to the customer.

6 sections

Cite this legislation

The Electricity (Prepayment Meter) Regulations 2006 (legislation.gov.uk, OGL v3.0). Retrieved via LawPlayer, https://lawplayer.com/uk/act/uksi-2006-2010

Contains public sector information licensed under the Open Government Licence v3.0.

OGL-3

本頁資料來源:legislation.gov.uk (The National Archives)·整理提供:法律人 LawPlayer· lawplayer.com