Statutory Instrument

The Highways (SSSI Diversion Orders) (England) Regulations 2007

Citation
S.I. 2007/1494
As at
Sections
8
Section 1Citation, commencement and extent

(1) These Regulations may be cited as the Highways (SSSI Diversion Orders) (England) Regulations 2007 and shall come into force on 1st July 2007.

(2) These Regulations apply in relation to England only .

Section 2Interpretation

In these Regulations—

“ the Act ” means the Highways Act 1980;

“order” means an SSSI diversion order or an order varying or revoking such an order.

Section 3Notice of intention to apply for an order

A notice of intention to apply for an order shall be in the form set out in Schedule 1 or in a form substantially to the same effect.

Section 4Application for an order

(1) An application for an order, and the assessment to accompany it, shall be in the form set out in Schedule 2 or in a form substantially to the same effect.

(2) The map required to accompany an application for an order shall be on a scale of not less than 1/2,500, or, if no such map is available, on the largest scale available.

(3) Other information to accompany an application is stated in the form set out in Schedule 2.

Section 5Orders

(1) An order shall be in the form set out in Schedule 3 or in a form substantially to the same effect.

(2) The map contained in an order shall be on a scale of not less than 1/2,500, or, if no such map is available, on the largest scale available.

Section 6Notices of making or confirmation

(1) A notice required to be given under paragraph 1(1) of Schedule 6 to the Act in respect of the making of an order and its intended submission for confirmation or confirmation as an unopposed order shall be in the form set out in Form 1 in Schedule 4 or in a form substantially to the same effect.

(2) A notice required to be published under paragraph 4(1) of Schedule 6 to the Act in respect of the confirmation of an order shall be in the form set out in Form 2 in Schedule 4 or in a form substantially to the same effect.

(3) A notice required to be published under paragraph 4(1) of Schedule 6 to the Act in respect of the making of an order by the Secretary of State shall be in the form set out in Form 3 in Schedule 4 or in a form substantially to the same effect.

(4) A notice required to be served under paragraph 1(3)(b)(iv) or 4(1)(a) of Schedule 6 to the Act shall, in relation to the areas specified in column 1 of the table in Schedule 4 to these Regulations, be served on the persons prescribed in column 2 of that table.

Section 7Procedure for orders

(1) An order shall be made in duplicate.

(2) Where an order is submitted to the Secretary of State for confirmation, the order and duplicate shall be sent to him accompanied by—

(a) two further copies of the order;

(b) a copy of the notice given before submission as required by paragraph 1(1) of Schedule 6 to the Act;

(c) any representations or objections duly made with respect to the order and not withdrawn, together with any observations on them made by the council ; and

(d) a statement of the grounds on which the council consider that the order should be confirmed.

(3) Any proceedings preliminary to the confirmation of an SSSI diversion order may be taken concurrently with any proceedings preliminary to the confirmation of a public path extinguishment order , a rail crossing extinguishment order or a special extinguishment order .

(4) After being notified of a decision not to confirm an order, the council shall, as soon as the requirements of paragraph 4(3) of Schedule 6 to the Act have been complied with, certify in writing to the Secretary of State that those requirements have been complied with.

(5) After an order has been confirmed by the Secretary of State, the council shall, as soon as the requirements of paragraph 4(1) of Schedule 6 to the Act have been complied with, certify in writing to the Secretary of State that those requirements have been complied with.

(6) After an order has been confirmed, the council shall send a copy of the order as confirmed to the Ordnance Survey.

Section 8Claims for compensation in respect of orders

(1) A claim made in accordance with section 28 of the Act (compensation for loss caused by public path creation order), as applied by section 121(2) of the Act , in consequence of the coming into operation of an order shall be made in writing and shall be served on the council, or, in the case of an order made by the Secretary of State, on the authority nominated by the Secretary of State as provided by section 28(3) of the Act (as it applies by virtue of section 121(2)(a) of the Act), by delivering it to the offices of the council or the authority (as the case may be), addressed to its Chief Executive, or by sending it by prepaid post so addressed.

(2) The time within which any such claim shall be served shall be six months from the date on which the order in respect of which the claim is made has come fully into force.

8 sections

Cite this legislation

The Highways (SSSI Diversion Orders) (England) Regulations 2007 (legislation.gov.uk, OGL v3.0). Retrieved via LawPlayer, https://lawplayer.com/uk/act/uksi-2007-1494

Contains public sector information licensed under the Open Government Licence v3.0.