This Order may be cited as the Electricity (Exemption from the Requirement for a Generation Licence) (Berry Burn) Order 2014 and comes into force on 19th February 2014.
資料由法律人 LawPlayer整理提供·UK legislation / curated by LawPlayer from legislation.gov.uk
The Electricity (Exemption from the Requirement for a Generation Licence) (Berry Burn) Order 2014
In this Order—
“ the Act ” means the Electricity Act 1989;
“the company” means Berry Burn Wind Farm Limited, a company registered in England and Wales with company number 4511914;
“the generating station” means the Berry Burn onshore wind farm, an electricity generating station whose entrance is located at Ordnance Survey map reference NJ 06169 45610, near Inverness, Scotland;
“the total system” means all transmission systems and distribution systems, located in Great Britain, of holders of licences under section 6(1)(b) and (c) of the Act (transmission and distribution licences).
(1) Subject to paragraph (2), the company is granted exemption from section 4(1)(a) of the Act (prohibition of unlicensed generation of electricity for supply) in respect of the generating station.
(2) The exemption granted in paragraph (1) is subject to compliance with the following conditions—
(a) that the generating station is connected to the total system;
(b) that, except in circumstances outside the reasonable control of the company, the generating station does not export more than 100 megawatts of electrical power to the total system; and
(c) that the company does not hold a licence under section 6(1)(a) of the Act.
Cite this legislation
The Electricity (Exemption from the Requirement for a Generation Licence) (Berry Burn) Order 2014 (legislation.gov.uk, OGL v3.0). Retrieved via LawPlayer, https://lawplayer.com/uk/act/uksi-2014-94
Contains public sector information licensed under the Open Government Licence v3.0.
本頁資料來源:legislation.gov.uk (The National Archives)·整理提供:法律人 LawPlayer· lawplayer.com