This Order may be cited as the Electricity (Exemption from the Requirement for a Generation Licence) (Frodsham) (England and Wales) Order 2015 and comes into force on 25th July 2015.
資料由法律人 LawPlayer整理提供·UK legislation / curated by LawPlayer from legislation.gov.uk
The Electricity (Exemption from the Requirement for a Generation Licence) (Frodsham) (England and Wales) Order 2015
In this Order—
“ the Act ” means the Electricity Act 1989;
“the company” means Frodsham Wind Farm Limited, a company registered in England and Wales with company number 07075301;
“the generating station” means the Frodsham onshore wind farm, an electricity generating station located at Ordnance Survey map reference SJ489780, near Frodsham, Cheshire;
“the total system in England and Wales” means—
the transmission system of the holder of a licence under section 6(1)(b) of the Act; and
all distribution systems,
in each case, to the extent located in England and Wales.
(1) Subject to paragraph (2), the company is granted exemption from section 4(1)(a) of the Act (prohibition of unlicensed generation of electricity for supply) in respect of the generating station.
(2) The exemption granted in paragraph (1) is subject to compliance with the following conditions—
(a) that the generating station is connected to the total system in England and Wales;
(b) that, except in circumstances outside the reasonable control of the company, the generating station does not export more than 100 megawatts of electrical power to the total system in England and Wales; and
(c) that the company does not hold a licence under section 6(1)(a) of the Act.
Cite this legislation
The Electricity (Exemption from the Requirement for a Generation Licence) (Frodsham) (England and Wales) Order 2015 (legislation.gov.uk, OGL v3.0). Retrieved via LawPlayer, https://lawplayer.com/uk/act/uksi-2015-1409
Contains public sector information licensed under the Open Government Licence v3.0.
本頁資料來源:legislation.gov.uk (The National Archives)·整理提供:法律人 LawPlayer· lawplayer.com