This Order may be cited as the Progress Power (Gas Fired Power Station) (Amendment) Order 2016 and comes into force on 12th November 2016.
資料由法律人 LawPlayer整理提供·UK legislation / curated by LawPlayer from legislation.gov.uk
The Progress Power (Gas Fired Power Station) (Amendment) Order 2016
The Progress Power (Gas Fired Power Station) Order 2015 (“the 2015 Order ”) is amended in accordance with this Order.
(1) Schedule 1 (authorised development) to the 2015 Order is amended as follows.
(2) In the description of numbered work 1B, for paragraph (e) substitute the following paragraph—
(e) three black start diesel generators where one gas turbine generator is constructed and one black start diesel generator where two, three, four or five gas turbine generators are constructed;
(3) In the description of numbered work 1B, insert the following paragraph after paragraph (g)—
(h) external fin fan cooler (where only one gas turbine generator is constructed).
In Schedule 2 (requirements) to the 2015 Order, Table 2 is replaced by Table 2 in the Schedule to this Order.
Cite this legislation
The Progress Power (Gas Fired Power Station) (Amendment) Order 2016 (legislation.gov.uk, OGL v3.0). Retrieved via LawPlayer, https://lawplayer.com/uk/act/uksi-2016-1086
Contains public sector information licensed under the Open Government Licence v3.0.
本頁資料來源:legislation.gov.uk (The National Archives)·整理提供:法律人 LawPlayer· lawplayer.com