This Order may be cited as the Immingham Open Cycle Gas Turbine (Amendment) Order 2023 and comes into force on 1st February 2023.
資料由法律人 LawPlayer整理提供·UK legislation / curated by LawPlayer from legislation.gov.uk
The Immingham Open Cycle Gas Turbine (Amendment) Order 2023
The Immingham Open Cycle Gas Turbine Order 2020 is amended in accordance with this Order.
In article 2 (interpretation) of Part 1 (preliminary) in the definition of “commissioning”, after the words “the undertaker’s operational and safety requirements”, insert “and the words “commission” and “commissioned” and cognate expressions are to be construed accordingly;” .
In Schedule 1 (authorised development), in the description of Work No. 1—
(a) at the end of sub-paragraph (u) delete “and”; and
(b) at the end of sub-paragraph (v) insert—
and
(w) synchronous condenser.
In Schedule 2 (requirements), in paragraph 11 sub-paragraph (3) after the words “No part of the authorised development may commence” insert “save for the permitted preliminary works” .
Cite this legislation
The Immingham Open Cycle Gas Turbine (Amendment) Order 2023 (legislation.gov.uk, OGL v3.0). Retrieved via LawPlayer, https://lawplayer.com/uk/act/uksi-2023-119
Contains public sector information licensed under the Open Government Licence v3.0.
本頁資料來源:legislation.gov.uk (The National Archives)·整理提供:法律人 LawPlayer· lawplayer.com