This Order may be cited as the HyNet Carbon Dioxide Pipeline (Correction) Order 2024.
資料由法律人 LawPlayer整理提供·UK legislation / curated by LawPlayer from legislation.gov.uk
The HyNet Carbon Dioxide Pipeline (Correction) Order 2024
This Order comes into force on 16th October 2024.
(1) The HyNet Carbon Dioxide Pipeline Order 2024 is corrected as set out in the table in the Schedule to this Order, in which—
(a) column 1 sets out where the correction is to be made;
(b) column 2 sets out how the correction is to be made; and
(c) column 3 sets out the text which is to be submitted, inserted or omitted.
Cite this legislation
The HyNet Carbon Dioxide Pipeline (Correction) Order 2024 (legislation.gov.uk, OGL v3.0). Retrieved via LawPlayer, https://lawplayer.com/uk/act/uksi-2024-1031
Contains public sector information licensed under the Open Government Licence v3.0.
本頁資料來源:legislation.gov.uk (The National Archives)·整理提供:法律人 LawPlayer· lawplayer.com