(1) This Order may be cited as the Offshore Installations (Safety Zones) Order 2024.
(2) This Order comes into force 21 days after the day on which it is made.
資料由法律人 LawPlayer整理提供·UK legislation / curated by LawPlayer from legislation.gov.uk
(1) This Order may be cited as the Offshore Installations (Safety Zones) Order 2024.
(2) This Order comes into force 21 days after the day on which it is made.
A safety zone is established around the installation specified in column 1 of the table in the Schedule (being an installation stationed in waters to which subsection (7) of section 21 of the Petroleum Act 1987 applies) having a radius of 500 metres, as respects that installation, from the point which has the co-ordinates of latitude and longitude according to the World Geodetic System 1984 specified in columns 2 and 3 of the table in the Schedule.
(1) The Offshore Installations (Safety Zones) (No. 2) Order 2001 is amended as follows.
(2) In the Schedule (safety zones), omit the entries relating to—
(a) “North Leadon Cluster “A””;
(b) “FPSO at Mid-Line Structure”; and
(c) “South Leadon Cluster “B””.
The Offshore Installations (Safety Zones) Order 2024 (legislation.gov.uk, OGL v3.0). Retrieved via LawPlayer, https://lawplayer.com/uk/act/uksi-2024-162
Contains public sector information licensed under the Open Government Licence v3.0.
本頁資料來源:legislation.gov.uk (The National Archives)·整理提供:法律人 LawPlayer· lawplayer.com