3
Section 1Citation and commencement

This Order may be cited as the Thurrock Flexible Generation Plant Consent (Amendment No. 2) Order 2024 and comes into force on 13th September 2024.

Section 2Amendment to the Thurrock Flexible Generation Plant Development Consent Order 2022

The Thurrock Flexible Generation Plant Development Consent Order 2022 (“ the 2022 Order ”) is amended in accordance with this Order.

Section 3Amendment to Schedule 1 (Authorised Development)

In Schedule 1 to the 2022 Order (Authorised Development), in the description of Work no. 1 in 1A replace at 1A(b) “up to 48 gas reciprocating engines” with “up to 96 gas reciprocating engines” .

3 sections

Cite this legislation

The Thurrock Flexible Generation Plant Consent (Amendment No. 2) Order 2024 (legislation.gov.uk, OGL v3.0). Retrieved via LawPlayer, https://lawplayer.com/uk/act/uksi-2024-955

Contains public sector information licensed under the Open Government Licence v3.0.

OGL-3

本頁資料來源:legislation.gov.uk (The National Archives)·整理提供:法律人 LawPlayer· lawplayer.com