法律人 LawPlayer logo

資料由法律人 LawPlayer整理提供·UK legislation / curated by LawPlayer from legislation.gov.uk

Statutory Instrument

The National Grid (Bramford to Twinstead Reinforcement) Order 2024

Citation
S.I. 2024/958
As at
Sections
159
Section 1Citation and commencement

This Order may be cited as the National Grid (Bramford to Twinstead Reinforcement) Order 2024 and comes into force on 4th October 2024.

Section 2Interpretation

(1) In this Order, unless where provided or the context requires otherwise—

“ 1961 Act ” means the Land Compensation Act 1961 ;

“ 1965 Act ” means the Compulsory Purchase Act 1965 ;

“ 1980 Act ” means the Highways Act 1980 ;

“ 1981 Act ” means the Compulsory Purchase (Vesting Declarations) Act 1981 ;

“ 1984 Act ” means the Road Traffic Regulation Act 1984 ;

“ 1990 Act ” means the Town and Country Planning Act 1990 ;

“ 1991 Act ” means the New Roads and Street Works Act 1991 ;

“ 2003 Act ” means the Communications Act 2003;

“ 2008 Act ” means the Planning Act 2008 ;

“ 2016 Regulations ” means the Environmental Permitting (England and Wales) Regulations 2016 ;

“ access, rights of way and public rights of navigation plans ” means the plans listed in Part 1 of Schedule 2 (plans) and certified under article 56 (certification of documents), and references to a particular access, rights of way and public rights of navigation plan are to be construed accordingly;

“ archaeological framework strategy ” means the document of that description (document 7.9), certified by the Secretary of State as the archaeological framework strategy for the purposes of this Order under article 56 (certification of documents), identifying steps to mitigate predicted effects on archaeology, geo-archaeology, palaeo-environmental and historic landscape heritage assets during construction of the authorised development;

“ authorised development ” means the development described in Schedule 1 (authorised development), and any other development authorised by this Order, which is development within the meaning of section 32 of the 2008 Act;

“bank holiday” means a bank holiday in England and Wales under section 1 of the Banking and Financial Dealings Act 1971 ;

“ book of reference ” means the book of reference (document 4.3 (F)) certified under article 56 (certification of documents) by the Secretary of State as the book of reference for the purposes of this Order;

“ building ” includes any structure or erection or any part of a building, structure or erection;

“ business day ” means Monday to Friday excluding bank holidays and other public holidays;

“ carriageway ” has the same meaning as in the 1980 Act;

“ commence ” means the carrying out of any material operation (as defined in section 155(2) (when development begins) of the 2008 Act) forming part of the authorised development other than the pre-commencement operations and “commencement” and “commenced” are to be construed accordingly;

“ electric line ” has the meaning set out in section 64(1) of the Electricity Act 1989 (interpretation etc. of Part 1) which includes but is not limited to new pylons, foundations and steelwork, conductors, insulators and fittings, fibre optic earthwire conductors, joint boxes, joint pits, joint bays, cables, cable ducts and link pillars;

“ electronic transmission ” means a communication transmitted—

by means of an electronic communications network; or

by other means but while in electronic form;

“ environmental statement ” means the environmental statement ( documents 6.1 to 6.4 (inclusive)) together with any supplemental or additional environmental information certified under article 56 (certification of documents), and any environmental statement submitted for the purposes of complying with and/or discharging the requirements, and any entries in the final version of the errata list ( document 8.4.3 (C) ) that relate to any of these documents;

“ highway ” and “ highway authority ” have the same meaning as in the 1980 Act;

“land plans” mean the relevant plans listed in Part 2 of Schedule 2 (plans) and certified under article 56 (certification of documents), and references to a particular land plan are to be construed accordingly;

“ limits of deviation ” means the limits of deviation referred to in article 5 (limits of deviation) and shown on the work plans;

“ maintain ” includes inspect, repair, adjust, alter, dismantle, remove, clear, refurbish, paint, surface treat, decommission, improve, reconstruct or replace any part, but not remove, reconstruct or replace the whole, of the authorised development including through the use of robots, helicopters, drones, gadgets or similar devices either remote controlled or autonomous, provided such works do not give rise to any materially new or materially different environmental effects to those identified in the environmental statement, and any derivative of “maintain” must be construed accordingly;

“ National Grid ” means National Grid Electricity Transmission plc (registered company number 2366977);

“operational use” occurs when part of the authorised development first transmits electricity at either 400kV or higher voltages;

“ Order land ” means the land shown on the land plans and described in the book of reference;

“ Order limits ” means the limits shown on the work plans within which the authorised development may be carried out;

“ outline construction environmental management plan ” means the document of that description (together with its appendices) ( documents 7.5 (E), 7.5.1 (D) and 7.5.2 (F) ) certified by the Secretary of State as the outline construction environmental management plan for the purposes of this Order under article 56 (certification of documents);

“ outline construction traffic management plan ” means the document of that description (together with its appendices) (document 7.6 (D)) certified by the Secretary of State as the outline construction traffic management plan for the purposes of this Order under article 56 (certification of documents);

“ outline landscape and ecological management plan ” means the document of that description (together with its appendices) (documents 7.8 (D), 7.8.1 (C), 7.8.2 (D) and 7.8.3 (C)) certified by the Secretary of State as the outline landscape and ecological management plan for the purposes of this Order under article 56 (certification of documents);

“ outline materials and waste management plan ” means the document of that description ( document 7.7 (B) ) certified by the Secretary of State as the outline materials and waste management plan for the purposes of this Order under article 56 (certification of documents);

“ outline public right of way management plan ” means the document of that description (together with its appendices) (document 8.5.8 (B)) certified by the Secretary of State as the outline public right of way management plan for the purposes of this Order under article 56 (certification of documents);

“ outline written scheme of investigation ” means the document of that description (document 7.10 (D)), certified by the Secretary of State as the outline written scheme of investigation for the purposes of this Order under article 56 (certification of documents), setting out the proposed approach to archaeological mitigation and investigations to be undertaken in association with the construction of the authorised development;

“ owner ”, in relation to land, has the same meaning as in section 7 of the Acquisition of Land Act 1981 ;

“ permit schemes ” means any scheme made under Part 3 of the Traffic Management Act 2004 as in force at the date on which this Order is made including the Traffic Management (Essex County Council) Permit Scheme Order 2015 as varied by The Essex County Council (Permit Scheme) (Variation) Order 2015;

“ pre-commencement operations ” means operations consisting of engineering investigations and surveys, environmental (including archaeological) investigations and monitoring, surveys and monitoring investigations for the purpose of assessing ground conditions, diversion and laying of services, demolition of existing buildings, site clearance, environmental mitigation measures, remediation in respect of any contamination or other adverse ground conditions, set up works associated with the establishment of construction compounds, temporary accesses, erection of any temporary means of enclosure or temporary demarcation fencing marking out site boundaries and the temporary display of site notices or advertisements;

“ provisional advance authorisation ” has the same meaning as in regulation 2 of the Traffic Management Permit Scheme Regulations 2007 ;

“ relevant highway authority ” means, in any given provision of this Order, the local highway authority for the area to which the provision relates;

“ relevant planning authority ” means, in any given provision of this Order, the local planning authority for the area to which the provision relates;

“ relevant street authority ” means, in any given provision of this Order, the local highway authority for the area to which the provision relates;

“ requirements ” means the requirements listed in Schedule 3 (requirements), and any reference to a numbered requirement is to be construed accordingly;

“ special category land plans ” means the plans listed in Part 3 of Schedule 2 (plans) and certified under article 56 (certification of documents) and references to a particular special category land plan are to be construed accordingly;

“ statutory undertaker ” means any person falling within section 127(8) of the 2008 Act;

“ street ” means a street within the meaning of section 48 of the 1991 Act, together with land on the verge of a street or between two carriageways, and includes part of a street;

“ street authority ”, in relation to a street, has the same meaning as in Part 3 (street works in England and Wales) of the 1991 Act;

“ temporary construction works ” means the temporary construction works described in Schedule 1 (authorised development) to the Order;

“ the table of parameters ” means the information shown on the sheet labelled as Table of Parameters within the work plans ;

“ traffic ” has the same meaning as in section 329(1) (further provision as to interpretation) of the 1980 Act;

“ traffic authority ” has the same meaning as in the 1984 Act;

“traffic regulation order plans” mean the plans listed in Part 4 of Schedule 2 (plans) and certified under article 56 (certification of documents), and references to a particular traffic regulation order plan are to be construed accordingly;

“ trees and hedgerows to be removed or managed plans ” means the plans listed in Part 5 of Schedule 2 (plans) and certified under article 56 (certification of documents), and references to a particular trees and hedgerows to be removed or managed plan are to be construed accordingly;

“ the tribunal ” means the Lands Chamber of the Upper Tribunal;

“ UKPN ” means UK Power Networks Holdings Limited (registered company number 07290590) and/or its affiliate Eastern Power Networks plc (registered company number 02366906);

“ the UKPN Works ” means those works to UKPN assets or equipment forming part of the authorised development, including Work Nos. 8 and 11;

“undertaker”—

in relation to the authorised development, means National Grid; and

in relation to the UKPN Works and subject to paragraph (5) of article 6 (benefit of Order), includes UKPN;

“ watercourse ” includes all rivers, streams, ditches, drains, canals, cuts, culverts, dykes, sluices, rhynes, sewers and passages through which water flows except a public sewer or drain; and

“ work plans ” means the plans listed in Part 6 of Schedule 2 (plans) and certified under article 56 (certification of documents), and references to a particular work plan are to be construed accordingly.

(2) References in this Order to rights over land include references to rights to do, or to place and maintain, anything in, on or under land or in the airspace above its surface and references in this Order to the imposition of restrictions in respect of land are references to restrictions over land which interfere with the interests or rights of another and are for the benefit of land which is acquired, or rights over which are acquired, under this Order.

(3) All distances, directions, levels and lengths referred to in this Order, are approximate. Distances between points on a work comprised in the authorised development are taken to be measured along that work. All distances for scheduled linear works referred to in this Order are measured along the centre line of the limits of deviation for that work. All pylon identification numbers set out in this Order are identified by reference to the work plans, and are subject to the limits of deviation for that work, such that the tower numbering and location of towers may adjust in accordance with the limits of deviation identified in article 5 (limits of deviation). Unless otherwise specified in Schedule 1 (authorised development), heights and depths in this Order or on the work plans are measured from the proposed final ground level.

(4) All areas described in square metres in the book of reference are approximate.

(5) References in this Order to numbered Works are references to the Works as numbered in Schedule 1 (authorised development).

(6) References in this Order to “document” followed by a number or numbers are references to documents submitted by National Grid in support of the application for development consent that resulted in the making of this Order.

(7) References in this Order to any statutory body includes that body’s successor in respect of functions which are relevant to this Order.

(8) References in this Order to any statute, order, regulation or similar instrument are to be construed as a reference to the statute, order, regulation or instrument as amended by any subsequent statute, order, regulation or instrument or as contained in any subsequent re-enactment.

Section 3Development consent etc. granted by the Order

(1) Subject to the provisions of this Order (including the requirements)—

(a) National Grid is granted development consent for the authorised development set out in Schedule 1 (authorised development) to be carried out within the Order limits; and

(b) subject to article 6(5) (benefit of Order), UKPN is granted development consent for the UKPN Works to be carried out within the Order limits.

(2) National Grid may—

(a) install and keep installed the authorised development; and

(b) remove or replace any electric line including pylons that may require removal as part of the authorised development.

(3) UKPN may—

(a) subject to paragraphs (3) and (5) of article 6 (benefit of Order), carry out the UKPN Works; and

(b) remove or replace any electric line including pylons or poles that may require removal in relation to the UKPN Works.

(4) National Grid may operate and use the electric lines and any other elements of the authorised development (excluding the UKPN Works) as part of the high-voltage electricity transmission system in England and Wales.

(5) UKPN may operate and use the electric line and any other elements of the UKPN Works as part of the electricity distribution network.

(6) The authorised development must be constructed and installed in the lines and situations shown on the work plans ..., subject to article 5 (limits of deviation) and to the requirements.

(7) Schedule 3 (requirements) has effect.

Section 4Maintenance of authorised development

(1) National Grid may at any time maintain the authorised development (excluding the UKPN Works), except to the extent that this Order, or an agreement made under this Order, provides otherwise.

(2) UKPN may at any time maintain the UKPN Works, except to the extent that this Order, or an agreement made under this Order, provides otherwise.

Section 5Limits of deviation

(1) Subject to paragraph (4) , in respect of the permanent overhead electric line and underground electric line works forming part of Work Nos. 1, 2, 3, 4, 5, 6, 10 and 11 (inclusive) of the authorised development for which it is granted development consent by paragraph (1) of article 3 (development consent etc. granted by the Order), the undertaker may—

(a) deviate laterally from the centreline for the linear works of the authorised development shown on the work plans within the limits of deviation relating to a Work shown on those plans and carry out construction activities for the purpose of the authorised development within the Order limits; and

(b) in respect of the pylons deviate vertically from the levels of the authorised development shown on the table of parameters—

(i) to any extent upwards not exceeding 4 metres;

(ii) to such extent downwards as the undertaker considers necessary or convenient;

(c) in respect of the overhead conductors and fibre-optic earth wires deviate vertically to such extent as the undertaker considers necessary or convenient;

(d) in respect of the underground electric line, deviate vertically—

(i) upwards such that the minimum distance that will be kept between the top of the protective tiles or (where there are no protective tiles) the top of the cable ducts and the top of the finished ground level is 0.9 metres; and

(ii) downwards to such extent as the undertaker considers necessary or convenient.

(2) Without prejudice to article 3 (6) (development consent etc. granted by the Order) the removal, clearance, decommissioning and demolition of any existing electric line may take place within the Order limits.

(3) Subject to paragraph (4) , in respect of other permanent above ground structures, erections and apparatus, including the Grid Supply Point Substation, Bramford Substation and cable sealing end compounds forming part of the authorised development—

(a) the authorised development is to be carried out within any applicable non-linear limits of deviation shown on the work plans; and

(b) the undertaker may deviate to any extent upwards not exceeding 10% above the maximum height shown on the table of parameters and to such extent downwards as the undertaker considers necessary or convenient.

(4) The maximum limits of vertical deviation specified in paragraphs (1)(b) , (1)(d) and (3)(b) do not apply where it is demonstrated by the undertaker to the Secretary of State’s satisfaction and the Secretary of State, following consultation with the relevant planning authority and any other person the Secretary of State considers appropriate having regard to the proposed deviation in question and the statutory roles and responsibilities of such person, certifies accordingly that a deviation in excess of these limits would not give rise to any materially new or materially different environmental effects to those identified in the Environmental Statement.

Section 6Benefit of Order

(1) Subject to article 7 (consent to transfer benefit of Order), the provisions of this Order have effect for the benefit of—

(a) National Grid in respect of the authorised development; and

(b) subject to paragraph (5), UKPN in respect of the UKPN Works.

(2) Paragraph (1) does not apply to the benefit of the consent granted by this Order for works carried out by the undertaker for the benefit or protection of land or persons (including statutory undertakers) affected by the authorised development.

(3) UKPN may not carry out the UKPN Works under article 3(3)(a) (development consent etc. granted by the Order) except in accordance with the written consent of National Grid, which may be granted subject to reasonable conditions.

(4) If UKPN fails to carry out any of the UKPN Works in accordance with National Grid’s consent, National Grid may give UKPN and the Secretary of State notice that National Grid intends to carry out those UKPN Works under article 3(3)(a) (development consent etc. granted by the Order) from a date specified in the notice.

(5) On the date specified in any notice under paragraph (4) of this article—

(a) UKPN is to cease to have the benefit of article 3(1)(b) (development consent etc. granted by the Order) and sub-paragraph (1)(b) of this article;

(b) UKPN is to cease to be an undertaker for the installation of the UKPN Works but remains an undertaker for the purposes of keeping installed and maintaining the electric lines included in the UKPN Works; and

(c) references to UKPN in article 26 (temporary use of land by UKPN) are to be read as including National Grid.

Section 7Consent to transfer benefit of Order

(1) National Grid in relation to the authorised development (not including the UKPN Works), and UKPN in relation to the UKPN Works, may, with the consent of the Secretary of State—

(a) transfer to another person (“ the transferee ”) any or all of the benefit of the provisions of this Order and such related statutory rights as may be agreed between National Grid or UKPN and the transferee;

(b) grant to another person (“ the lessee ”) for a period agreed between National Grid or UKPN and the lessee any or all of the benefit of the provisions of this Order and such related statutory rights as may be so agreed.

(2) Where a transfer or grant has been made in accordance with paragraph (1) references in this Order to National Grid or UKPN (as the case may be), except in paragraphs (3) and (4) , are to include references to the transferee or the lessee.

(3) The exercise by a person of any benefits or rights transferred or granted in accordance with any transfer or grant under paragraph (1) is subject to the same restrictions, liabilities and obligations as would apply under this Order if those benefits or rights were exercised by National Grid or UKPN.

(4) Any rights or benefits in relation to the UKPN Works that are transferred or granted by UKPN under paragraph (1) are subject to paragraphs (3) to (5) of article 6 (benefit of Order) as if they had remained exercisable by UKPN.

(5) Where a transfer or grant has been made in accordance with paragraph (1) , the undertaker must notify the relevant planning authority of the same.

Section 8Application of the 1990 Act

(1) In respect of the temporary construction works, section 57(2) of the 1990 Act (planning permission required for development) applies as if the development consent granted by this Order were planning permission granted for a limited period.

(2) Development consent granted by this Order is to be treated as specific planning permission for the purposes of section 264(3)(a) of the 1990 Act (cases in which land is to be treated as not being operational land).

(3) In the exercise of the power under paragraphs (1) and (2) of article 11 (street works) the undertaker is to be deemed to be the highway authority for the purposes of section 55(2)(b) of the 1990 Act.

Section 9Application of the Community Infrastructure Levy Regulations 2010

Notwithstanding the provisions of section 208 (liability) of the 2008 Act, for the purposes of regulation 6 of the Community Infrastructure Levy Regulations 2010 any building comprised in the authorised development is deemed to be—

(a) a building into which people do not normally go; or

(b) a building into which people go only intermittently for the purpose of inspecting or maintaining fixed plant or machinery.

Section 10Planning Permission

(1) If planning permission is issued pursuant to the 1990 Act for development any part of which is within the Order limits that is—

(a) not itself a nationally significant infrastructure project under the 2008 Act or part of such a project; and

(b) required to complete or enable the construction, use or operation of any part of the development authorised by this Order,

then the carrying out, use or operation of such development pursuant to the terms of the planning permission is not to constitute a breach of the terms of this Order.

(2) To the extent any development carried out or used pursuant to a planning permission granted under section 57 (planning permission required for development) of the 1990 Act or compliance with any conditions of that permission is inconsistent with the exercise of any power or right under this Order or the authorised development—

(a) that inconsistency is to be disregarded for the purposes of establishing whether any development which is the subject matter of that planning permission is capable of physical implementation; and

(b) in respect of that inconsistency, no enforcement action under the 1990 Act may be taken in relation to development carried out or used pursuant to that planning permission whether inside or outside the Order limits.

(3) Any development or any part of a development within the Order limits which is constructed or used under the authority of a planning permission granted under section 57 of the 1990 Act, including permissions falling under sub-paragraph (1) or (2) or otherwise, is deemed not to be a breach of, or inconsistent with, this Order and will not prevent the authorised development being carried out or used or any other power or right under this Order being exercised.

Section 11Street works

(1) The undertaker may, for the purposes of the authorised development, or for purposes ancillary to it, enter upon so much of any of the streets specified in column (2) of Schedule 5 (streets subject to street works) as is within the Order limits and may without the consent of the street authority—

(a) break up or open the street, or any sewer, drain or tunnel within or under it;

(b) tunnel, drill or bore under the street, or carry out any works to strengthen or repair the carriageway;

(c) remove or use all earth and materials in or under the street;

(d) place and keep apparatus in the street (including signage);

(e) maintain, renew or alter apparatus or furniture in or on the street or change its position;

(f) execute any works to provide or improve sight lines required by the highway authority;

(g) execute and maintain any works to provide hard and soft landscaping and any other works for the benefit or protection of the environment;

(h) carry out re-lining and placement of new temporary markings; and

(i) execute any works required for or incidental to any works referred to in sub-paragraphs (a) to (h) .

(2) Without limiting the scope of the powers conferred by paragraph (1) but subject to the consent of the street authority, the undertaker may, for the purposes of the authorised development, or for purposes ancillary to it, enter on so much of any other street whether or not within the Order limits, for the purposes set out at sub-paragraph (1) (a) to (i) and paragraph (3) of article 8 (application of the 1990 Act) applies.

(3) If a street authority that receives an application for consent under paragraph (2) fails to notify the undertaker of its decision within 35 days (or such other period as agreed by the street authority and the undertaker) beginning with the date on which the application was received, that authority will be deemed to have granted consent.

(4) Any application for consent under paragraph (2) must include a statement that the provisions of paragraph (3) apply to that application.

(5) If an application for consent under paragraph (2) does not include the statement required under paragraph (4) , then the provisions of paragraph (3) will not apply to that application.

(6) The authority given by paragraph (1) or (2) is a statutory right for the purposes of sections 48(3) (streets, street works and undertakers) and 51(1) (prohibition of unauthorised street works) of the 1991 Act.

(7) The powers conferred in paragraphs (1) or (2) are without limitation of the powers of the undertaker under the Electricity Act 1989 .

(8) In this article “ apparatus ” has the meaning given in Part 3 of the 1991 Act.

Section 12Application of the permit schemes

(1) The permit schemes apply to the construction of the authorised development and will have effect in connection with the exercise by the undertaker of any powers conferred by this Part.

(2) For the purposes of this Order—

(a) a permit may not be refused or granted subject to conditions which relate to the imposition of moratoria;

(b) a permit may not be granted subject to conditions where compliance with those conditions would constitute a breach of this Order or where the undertaker would be unable to comply with those conditions through the exercise of the powers conferred by this Order;

(c) a permit may not be refused where the proposed reason for refusal is the inability to impose a condition which will not comply with paragraph (b); and

(d) where a provisional advance authorisation has been granted to the undertaker in advance of the grant of a permit in relation to the construction of the authorised development, the relevant street authority may not grant a permit for any other works in the location during the time period to which that provisional advance authorisation relates save that nothing will restrict the ability of the local highway authority to grant a permit for immediate works.

(3) Irrespective of anything which is stated to the contrary within the permit schemes, where the undertaker submits an application for a permit in relation to the construction of the authorised development subject to proposed conditions and the relevant highway authority wishes for different conditions to be imposed on the permit, the relevant highway authority must seek to reach agreement with the undertaker on the conditions subject to which the permit is to be granted and provide alternative permit conditions, as appropriate, to the undertaker within ten working days following the date on which the application for the permit is made by the undertaker and must not refuse an application for a permit before the end of the period which is five working days following the date on which the alternative permit conditions are provided to the undertaker.

(4) Where the undertaker confirms its agreement to the alternative permit conditions provided by the relevant highway authority pursuant to paragraph (3) before the expiry of five working days following the date on which any such alternative permit conditions are provided to the undertaker, the relevant highway authority must grant the permit subject to those conditions.

(5) Any alternative permit conditions provided by a relevant highway authority in accordance with paragraph (3) must comply with paragraph (1)(b).

(6) References to moratoria in paragraph (1) mean restrictions imposed under section 58 ( restriction on works following substantial road works) or section 58A ( restriction on works following substantial street works) of the 1991 Act.

(7) Reference to immediate works in paragraph (1)(d) means emergency works as that term is defined in section 52 of the 1991 Act and urgent works as that term is defined in regulation 3(1) of the Street Works (Registers, Notices, Directions and Designations) (England) Regulations 2007 .

(8) Without restricting the undertaker’s recourse to any alternative appeal mechanism which may be available under the permit schemes or otherwise, the undertaker may appeal any decision to refuse to grant a permit or to grant a permit subject to conditions pursuant to the permit schemes in accordance with the mechanism set out in Schedule 4 (Discharge of Requirements) of this Order.

Section 13Application of the 1991 Act

(1) Works carried out under this Order in relation to a highway which consists of or includes a carriageway must be treated for the purposes of Part 3 of the 1991 Act (street works in England and Wales) as major highway works if—

(a) they are of a description mentioned in any of paragraphs (a), (c) to (e), (g) and (h) of section 86(3) of the 1991 Act (highway authorities, highways and related matters); or

(b) they are works which, had they been executed by the relevant highway authority, might have been carried out in exercise of the powers conferred by section 64 (dual carriageways and roundabouts) or section 184 (vehicle crossings over footways and verges) of the 1980 Act.

(2) In Part 3 of the 1991 Act, in relation to works which are major highway works by virtue of paragraph (1), references to the highway authority concerned are to be construed as references to the undertaker.

(3) The following provisions of the 1991 Act do not apply in relation to any works executed under the powers of this Order—

(a) section 56 (power to give directions as to timing of street works);

(b) section 56A (power to give directions as to placing of apparatus);

(c) section 58 (restrictions on works following substantial road works);

(d) section 58A (restriction on works following substantial street works);

(e) section 73A (power to require undertaker to re-surface street);

(f) section 73B (power to specify timing etc. of re-surfacing);

(g) section 73C (materials, workmanship and standard of re-surfacing);

(h) section 78A (contributions to costs of re-surfacing by undertaker); and

(i) Schedule 3A (restriction on works following substantial street works).

(4) The following provisions of the 1991 Act do not apply in relation to any works executed under article 12 (application of the permit schemes ) of this Order—

(a) section 53 (the street works register);

(b) section 54 (advance notice of certain works);

(c) section 55 (notice of starting date of ... works);

(d) section 57 (notice of emergency works); and

(e) section 66 (avoidance of unnecessary delay or obstruction).

(5) The provisions of the 1991 Act mentioned in paragraph (6) (which, together with other provisions of that Act, apply in relation to the carrying out of street works) and any regulations made, or code of practice issued or approved under those provisions, apply (with necessary modifications) in relation to any closure, alteration or diversion of a street of a temporary nature by the undertaker under the powers conferred by article 15 (temporary closure of streets and public rights of way) whether or not the closure, alteration or diversion constitutes street works within the meaning of that Act.

(6) The provisions of the 1991 Act referred to in paragraph (5) are—

(a) section 54 (advance notice of certain works), subject to paragraph (7);

(b) section 55 (notice of starting date of works), subject to paragraph (7);

(c) section 57 (notice of emergency works);

(d) section 59 (general duty of street authority to co-ordinate works);

(e) section 60 (general duty of undertakers to co-operate);

(f) section 68 (facilities to be afforded to street authority);

(g) section 69 (works likely to affect other apparatus in the street);

(h) section 71 (materials, workmanship and standard of reinstatement);

(i) section 75 (inspection fees);

(j) section 76 (liability for cost of temporary traffic regulation);

(k) section 77 (liability for cost of use of alternative route); and

(l) all such other provisions as apply for the purposes of the provisions mentioned in sub-paragraphs (a) to (k).

(7) Sections 54 and 55 of the 1991 Act as applied by paragraph (5) have effect as if references in section 57 of that Act to emergency works were references to a closure, alteration or diversion (as the case may be) required in a case of emergency.

Section 14Power to alter layout, etc. of streets

(1) The undertaker may, without the consent of the street authority, and for the purposes of carrying out the authorised development, permanently or temporarily alter the layout of, or carry out any works in, a street specified in column (1) of Part 1 or 2 of Schedule 6 (streets subject to alteration of layout) in the manner specified in relation to that street in column (2).

(2) Without limitation on the specific powers conferred by paragraph (1), but subject to paragraph (4), the undertaker may, for the purposes of constructing and maintaining the authorised development, permanently or temporarily alter the layout of any street (and carry out works ancillary to such alterations) whether or not within the Order limits and the layout of any street having a junction with such a street and, without limiting the scope of this paragraph, the undertaker may—

(a) increase the width of the carriageway of the street by reducing the width of any kerb, footpath, footway, cycle track, central reservation or verge within the street;

(b) alter the level or increase the width of any such kerb, footpath, footway, cycle track, central reservation or verge;

(c) reduce the width of the carriageway of the street;

(d) execute any works to widen or alter the alignment of pavements;

(e) make and maintain crossovers, turning lanes and passing places;

(f) execute any works of surfacing or resurfacing of the highway;

(g) carry out works for the provision or alteration of parking places, loading bays and cycle tracks;

(h) execute any works necessary to alter or provide facilities for the management and protection of pedestrians; and

(i) execute any works to provide or improve sight lines required by the highway authority.

(3) The undertaker must restore to the reasonable satisfaction of the street authority any street that has been temporarily altered under this article.

(4) The powers conferred by paragraph (2) may not be exercised without the consent of the street authority.

(5) If a street authority which receives an application for consent under paragraph (4) fails to notify the undertaker of its decision before the end of the period of 35 days (or such other period as agreed by the street authority and the undertaker) beginning with the date on which the application was received, it is deemed to have granted consent.

(6) Any application for consent under paragraph (4) must include a statement that the provisions of paragraph (5) apply to that application.

(7) If an application for consent under paragraph (4) does not include the statement required under paragraph (6), then the provisions of paragraph (5) will not apply to that application.

Section 15Temporary closure of streets and public rights of way

(1) During and for the purposes of carrying out the authorised development, the undertaker may temporarily close, alter or divert any street or public right of way shown on the access, rights of way and public rights of navigation plans or within the Order limits and may for any reasonable time—

(a) divert the traffic from the street or public right of way; and

(b) subject to paragraph (3), prevent all persons from passing along the street or public right of way.

(2) Without limitation on the scope of paragraph (1), the undertaker may, with the consent of the street authority, use as a temporary working site any street or public right of way which has been temporarily closed, altered or diverted under the powers conferred by this article.

(3) The undertaker must provide reasonable access for pedestrians going to or from premises abutting a street or public right of way affected by the temporary closure, alteration or diversion under this article if there would otherwise be no reasonable access.

(4) Without limitation on the scope of paragraph (1), the undertaker may temporarily close, alter or divert the streets or public rights of way specified in columns (1) and (2) of Parts 1 and 2 of Schedule 7 (streets or public rights of way to be temporarily closed) to the extent specified, by reference to the letters and numbers shown on the access, rights of way and public rights of navigation plans, in column (3) of that Schedule, and, if it does so in respect of a street or public right of way specified in Part 1 of Schedule 7, must provide the temporary diversion as specified in column (4) of that Part.

(5) The undertaker must not temporarily close, alter or divert—

(a) any street or public right of way specified as mentioned in paragraph (4) without first consulting the street authority; or

(b) any other street or public right of way without the consent of the street authority which may attach reasonable conditions to any consent.

(6) Where the undertaker provides a temporary diversion under paragraph (4), the temporary alternative route is not required to be of a higher standard than the temporarily closed street or public right of way in columns (1) and (2) of Part 1 of Schedule 7 (streets or public rights of way to be temporarily closed).

(7) Prior to the reopening of any street or public right of way temporarily closed, altered or diverted under paragraph (4), the undertaker must remove all temporary works and restore the street or public right of way to the reasonable satisfaction of the street authority.

(8) Any person who suffers loss by the suspension of any private right of way under this article is entitled to compensation to be determined, in case of dispute, under Part 1 of the 1961 Act.

(9) If a street authority which receives an application for consent under paragraph (2) or (5)(b) fails to notify the undertaker of its decision before the end of the period of 35 days (or such other period as agreed by the street authority and the undertaker) beginning with the date on which the application was received, it is deemed to have granted consent.

(10) Any application for consent under paragraph (2) or (5)(b) must include a statement that the provisions of paragraph (9) apply to that application.

(11) If an application for consent under paragraph (2) or (5)(b) does not include the statement required under paragraph (10), then the provisions of paragraph (9) will not apply to that application.

Section 16Access to works

(1) The undertaker may, for the purposes of the authorised development—

(a) form and lay out means of access, or improve existing means of access, in the location specified in column (2) of Schedule 8 (access to works); and

(b) with the consent of the relevant planning authority after consultation with the relevant highway authority, form and lay out such other means of access or improve existing means of access, at such locations within the Order limits as the undertaker reasonably requires for the purposes of the authorised development.

(2) If a relevant planning authority which receives an application for consent under sub-paragraph (1)(b) fails to notify the undertaker of its decision before the end of the period of 35 days (or such other period as agreed by the relevant planning authority and the undertaker) beginning with the date on which the application was received, it is deemed to have granted consent.

(3) Any application for consent under sub-paragraph (1)(b) must include a statement that the provisions of paragraph (2) apply to that application.

(4) If an application for consent under paragraph (1)(b) does not include the statement required under paragraph (3), then the provisions of paragraph (2) will not apply to that application.

Section 17Construction, alteration and maintenance of streets

(1) Any street (other than any private streets) to be constructed under this Order must be completed to the reasonable satisfaction of the street authority and must, unless otherwise agreed with the street authority, be maintained to the same condition (including any culverts or other structures laid under that part of the highway) by and at the expense of the undertaker for a period of 12 months from its completion and, at the expiry of that period, by and at the expense of the street authority.

(2) Where a street is altered or diverted under this Order, the altered or diverted part of the street must be completed to the reasonable satisfaction of the street authority and must, unless otherwise agreed with the street authority, be maintained to the same condition (including any culverts or other structures laid under that part of the highway) by and at the expense of the undertaker for a period of 12 months from its completion and, at the expiry of that period, by and at the expense of the street authority.

(3) Where new land not previously part of the public highway is to form part of the public highway further to the provisions of this Order it must, unless otherwise agreed with the street authority, be deemed as dedicated as part of the public highway on the expiry of the period of 12 months from its completion.

(4) In any action against the undertaker in respect of loss or damage resulting from any failure by it to maintain a street under this article, it is a defence (without prejudice to any other defence or the application of the law relating to contributory negligence) to prove that the undertaker had taken such care as in all the circumstances was reasonably required to secure that the part of the street to which the action relates was not dangerous to traffic.

(5) For the purposes of a defence under paragraph (4), the court must in particular have regard to the following matters—

(a) the character of the street and the traffic which was reasonably to be expected to use it;

(b) the standard of maintenance appropriate for a street of that character and used by such traffic;

(c) the state of repair in which a reasonable person would have expected to find the street;

(d) whether the undertaker knew, or could reasonably have been expected to know, that the condition of the part of the street to which the action relates was likely to cause danger to users of the street; and

(e) where the undertaker could not reasonably have been expected to repair that part of the street before the cause of action arose, what warning notices of its condition had been displayed,

but for the purposes of such a defence it is not relevant to prove that the undertaker had arranged for a competent person to carry out or supervise the maintenance of the part of the street to which the action relates unless it is also proved that the undertaker had given the competent person proper instructions with regard to the maintenance of the street and that the competent person had carried out those instructions.

(6) In determining who is the street authority in relation to a street for the purposes of Part 3 of the 1991 Act, any obligation of the undertaker to maintain the street under paragraph (1) or (2) should be disregarded.

Section 18Agreements with street authorities

(1) A street authority and the undertaker may enter into agreements with respect to—

(a) the construction of any new street including any structure carrying the street over or under an electric line authorised by this Order;

(b) the maintenance of the structure of any bridge or tunnel carrying a street over or under an electric line authorised by this Order;

(c) any temporary closure, alteration or diversion of a street authorised by this Order;

(d) the carrying out in the street of any of the works referred to in article 11 (street works) or article 14 (power to alter layout, etc. of streets); and

(e) such other matters as the parties may agree, including such matters as may be included in agreements made pursuant to section 38 or section 278 of the 1980 Act.

(2) Such an agreement may, without limitation on the scope of paragraph (1) —

(a) make provision for the street authority to carry out any function under this Order which relates to the street in question;

(b) include an agreement between the undertaker and the street authority specifying a reasonable time for the completion of the works;

(c) provide for the dedication of any new street as public highway;

(d) contain such terms as to payment as the parties consider appropriate; and

(e) contain such other terms as the parties may agree.

Section 19Discharge of water

(1) Subject to paragraphs (3) and (4), the undertaker may use any watercourse or any public sewer or drain for the drainage of water in connection with the carrying out or maintenance of the authorised development, and for that purpose may lay down, take up and alter pipes and may, on any land within the Order limits, make openings into, and connections with, the watercourse, public sewer or drain.

(2) Any dispute arising from the making of connections to or the use of a public sewer or drain by the undertaker pursuant to paragraph (1) must be determined as if it were a dispute under section 106 of the Water Industry Act 1991 (right to communicate with public sewers).

(3) The undertaker must not discharge any water into any watercourse, public sewer or drain except with the consent of the person to whom it belongs; and such consent may be given subject to such terms and conditions as that person may reasonably impose.

(4) The undertaker must not make any opening into any public sewer or drain except—

(a) in accordance with plans approved by the person to whom the sewer or drain belongs; and

(b) where that person has been given the opportunity to supervise the making of the opening.

(5) The undertaker must not, in carrying out or maintaining works pursuant to this article, damage or interfere with the bed or banks of any watercourse forming part of a main river.

(6) The undertaker must, unless otherwise authorised under the provisions of this Order or any environmental permit relating to the discharge of water in connection with the authorised development, take such steps as are reasonably practicable to secure that any water discharged into a watercourse or public sewer or drain under the powers conferred by this article is as free as may be practicable from gravel, soil or other solid substance, oil or matter in suspension; but nothing in this Order requires the undertaker to maintain a watercourse or public sewer or drain or the drainage works.

(7) Nothing in this article overrides the requirement for an environmental permit under regulation 12(1)(b) of the 2016 Regulations.

(8) This article does not permit any activity listed in paragraph 3(1) of Schedule 21 to the 2016 Regulations.

(9) If a person who receives an application for consent under paragraph (3) or approval under sub-paragraph (4)(a) fails to notify the undertaker of a decision within 35 days (or such other period as agreed by the person receiving the application and the undertaker) of receiving an application, that person is deemed to have granted consent or given approval, as the case may be.

(10) Any application for consent under paragraph (3) or approval under sub-paragraph (4)(a) must include a statement that the provisions of paragraph (9) apply to that application.

(11) If an application for consent under paragraph (3) or approval under paragraph (4)(a) does not include the statement required under paragraph (10), then the provisions of paragraph (9) will not apply to that application.

(12) In this article—

(a) “ public sewer or drain ” means a sewer or drain which belongs to Homes England, the Environment Agency, a harbour authority within the meaning of section 57 of the Harbours Act 1964 , an internal drainage board, a joint planning board, a local authority, a National Park Authority, a sewerage undertaker or an urban development corporation;

(b) “ main river ” has the same meaning as in the Water Resources Act 1991 ; and

(c) other expressions, excluding watercourse, used both in this article and in the 2016 Regulations have the same meaning as in those Regulations.

Section 20Protective works

(1) Subject to the following provisions of this article, the undertaker may at its own expense carry out such protective works to any land, building, structure, apparatus or equipment, lying within the Order limits or which may be affected by the authorised development, as the undertaker considers necessary or expedient.

(2) Protective works may be carried out—

(a) at any time before or during the carrying out in the vicinity of the land, building, structure, apparatus or equipment, of any part of the authorised development or works ancillary to it; or

(b) after the completion of any part of the authorised development in the vicinity of the land, building, structure, apparatus or equipment, at any time up to the end of the period of five years beginning with the day on which that part of the authorised development is first brought into operational use.

(3) For the purpose of determining how the functions under this article are to be exercised, the undertaker may enter and ... survey—

(a) any land, building, structure, apparatus or equipment, falling within paragraph (1) and any land within its curtilage; and

(b) where reasonably necessary, any land which is adjacent to the land, building, structure, apparatus or equipment, whether or not within the Order limits,

and place on, leave on and remove from the building, structure, apparatus or equipment any apparatus and equipment for use in connection with the survey.

(4) For the purpose of carrying out protective works under this article to any land, building, structure, apparatus or equipment, the undertaker may (subject to paragraphs (5) and (6))—

(a) enter the land, building or structure and any land within its curtilage; and

(b) where the works cannot be carried out reasonably conveniently without entering land which is adjacent to the land, building or structure but outside its curtilage, enter the adjacent land (but not any building erected on it).

(5) Before exercising—

(a) a right under paragraph (1) to carry out protective works to any land, building, structure, apparatus or equipment;

(b) a right under paragraph (3) to enter and/or survey any land, building, structure, apparatus or equipment, and land within its curtilage or any adjacent land;

(c) a right under sub-paragraph (4)(a) to enter the land, building or structure and land within its curtilage; or

(d) a right under sub-paragraph (4)(b) to enter land,

the undertaker must, except in the case of emergency, serve on the owners and occupiers of the building or land not less than 14 days’ notice of its intention to exercise that right and, in a case falling within sub-paragraph (a) or (c), specify the protective works proposed to be carried out.

(6) Where a notice is served under sub-paragraph (5)(a), (c) or (d), the owner or occupier of the land, building, structure, apparatus or equipment concerned may, by serving a counter-notice within the period of ten days beginning with the day on which the notice was served, require the question whether it is necessary or expedient to carry out the protective works or to enter the building or land to be referred to arbitration under article 58 (arbitration).

(7) The undertaker must compensate the owners and occupiers of any land, building, structure, apparatus or equipment, in relation to which rights under this article have been exercised, for any loss or damage arising to them by reason of the exercise of those rights.

(8) Where—

(a) protective works are carried out under this article to any land, building, structure, apparatus or equipment; and

(b) within the period of five years beginning with the day on which the part of the authorised development carried out in the vicinity of the land, building, structure, apparatus or equipment is first brought into operational use it appears that the protective works are inadequate to protect the land, building, structure, apparatus or equipment against damage caused by the carrying out or use of that part of the authorised development,

the undertaker must compensate the owners and occupiers of the land, building, structure, apparatus or equipment for any loss or damage sustained by them.

(9) Subject to article 53 (no double recovery), nothing in this article relieves the undertaker from any liability to pay compensation under section 152 of the 2008 Act (compensation in case where no right to claim in nuisance).

(10) Section 13 (refusal to give possession to acquiring authority) of the 1965 Act applies to the entry onto, or possession of, land under this article to the same extent as it applies to the compulsory acquisition of land under this Order by virtue of section 125 (application of compulsory acquisition provisions) of the 2008 Act.

(11) Any compensation payable under paragraph (7) or (8) must be determined, in case of dispute, under Part 1 of the 1961 Act (determination of questions of disputed compensation).

(12) In this article “ protective works ” in relation to any land, building, structure, apparatus, equipment or the authorised development means—

(a) underpinning, strengthening, ground strengthening, earthing and any other works the purpose of which is to prevent damage which may be caused to the land, building, structure, apparatus, equipment or the authorised development by the carrying out, maintenance or use of the authorised development; and

(b) any works the purpose of which is to remedy any damage which has been caused to the land, building, structure, apparatus or equipment by the carrying out, maintenance or use of the authorised development.

Section 21Authority to survey and investigate the land

(1) The undertaker may for the purposes of this Order enter on any land either shown within the Order limits or land which may be affected by the authorised development and—

(a) survey, monitor or investigate the land (including any watercourses, groundwater, static water bodies or vegetation on the land);

(b) without prejudice to the generality of sub-paragraph (a), survey, monitor or investigate the land and any buildings on that land for the purpose of investigating the potential effects of the authorised development on that land or buildings on that land or for enabling the construction, use and maintenance of the authorised development;

(c) without limitation on the scope of sub-paragraph (a), make trial holes, boreholes, excavations or take horizontal cores in such positions on the land as the undertaker thinks fit to investigate the nature of the surface layer, subsoil, groundwater and other materials below ground level and/or remove soil, rock, water and/or other material samples and discharge water from sampling operations on to the land;

(d) without limitation on the scope of sub-paragraph (a), carry out ecological or archaeological investigations and monitoring on the land, including making any excavations or trial holes on the land for such purposes; and

(e) place on, leave on and remove from the land apparatus (including but not limited to welfare facilities and apparatus attached to buoys) for use in connection with the survey, monitoring or investigation of land, making of trial holes, boreholes, excavations, cores, and/or the carrying out of ecological or archaeological investigations or monitoring.

(2) The power conferred by paragraph (1) includes without prejudice to the generality of that paragraph the power to take, and process, samples of or from any of the following found on, in or over the land—

(a) water;

(b) air;

(c) soil or rock;

(d) flora;

(e) bodily excretions, or dead bodies, of non-human creatures; or

(f) any non-living thing present as a result of human action.

(3) No land may be entered or equipment placed or left on or removed from the land under paragraph (1), unless at least 14 days’ notice has been served on every owner and occupier of the land.

(4) Any person entering land under this article on behalf of the undertaker—

(a) must, if so required, before or after entering the land, produce written evidence of their authority to do so;

(b) must, before entering the land, provide in the notice details of the purpose specified in paragraph (1) to survey and investigate the land; and

(c) may take onto the land such vehicles and equipment as are necessary to carry out the survey, monitoring or investigation or to make the trial holes.

(5) No trial holes, boreholes, excavations or horizontal cores may be made under this article—

(a) on land located within the highway boundary without the consent of the relevant highway authority; or

(b) in a private street without the consent of the street authority.

(6) As soon as reasonably practicable following the completion of any activities or programme of activities carried out under paragraph (1), the undertaker must remove any apparatus and restore the land to the reasonable satisfaction of the owners of the land.

(7) The undertaker must compensate the owners and occupiers of the land for any loss or damage arising by reason of the exercise of the powers conferred by this article, such compensation to be determined, in case of dispute, under Part 1 of the 1961 Act (determination of questions of disputed compensation).

(8) If a highway authority or street authority which receives an application for consent fails to notify the undertaker of its decision within 35 days (or such other period as agreed by the highway authority or the street authority and the undertaker) of receiving the application for consent—

(a) under sub-paragraph (5)(a) in the case of a highway authority; or

(b) under sub-paragraph (5)(b) in the case of a street authority,

that authority is deemed to have granted consent.

(9) Any application for consent under either sub-paragraph (5)(a) or sub-paragraph (5)(b) must include a statement that the provisions of paragraph (8) apply to that application.

(10) If an application for consent under either paragraph (5)(a) or paragraph (5)(b) does not include the statement required under paragraph (9), then the provisions of paragraph (8) will not apply to that application.

(11) Section 13 of the 1965 Act (refusal to give possession to acquiring authority) applies to the temporary use of land pursuant to this article to the same extent as it applies to the compulsory acquisition of land under this Order by virtue of section 125 of the 2008 Act (application of compulsory acquisition provisions).

Section 22Compulsory acquisition of land

(1) National Grid may acquire compulsorily so much of the Order land described in the book of reference as is required for the construction, operation and maintenance of the authorised development (including the UKPN Works) or is incidental to it or required to facilitate it.

(2) UKPN may acquire compulsorily so much of the Order land described in the book of reference as is required for the construction, operation and maintenance of that part of the UKPN Works forming part of Work No. 9 only.

(3) This article is subject to article 23 (compulsory acquisition of rights), article 24 (acquisition of subsoil or airspace only), article 25 (temporary use of land by National Grid), article 26 (temporary use of land by UKPN), article 27 (temporary use of land for maintaining the authorised development), article 31 (compulsory acquisition of land – incorporation of the mineral code), article 33 (acquisition of part of certain properties), article 40 (crown rights) and Schedule 14 (protective provisions).

Section 23Compulsory acquisition of rights

(1) Subject to the provisions of this article, the undertaker may acquire compulsorily the rights, and impose the restrictions, over the Order land, described in the book of reference, by creating them as well as by acquiring rights and the benefits of restrictions already in existence.

(2) This article is subject to article 22 (compulsory acquisition of land), article 25 (temporary use of land by National Grid) and article 26 (temporary use of land by UKPN).

(3) Subject to section 8 of the 1965 Act (other provisions as to divided land) as substituted by Schedule 9 to this Order (modification of compensation and compulsory purchase enactments for creation of new rights), where the undertaker acquires a right over land or imposes a restriction under paragraph (1) , the undertaker is not required to acquire a greater interest in that land.

(4) Schedule 9 to this Order has effect for the purpose of modifying the enactments relating to compensation and the provisions of the 1965 Act in their application in relation to the compulsory acquisition under this article of a right over land by the creation of a new right or the imposition of a restriction.

(5) In any case where the acquisition of rights or the imposition of a restriction under paragraph (1) is required for the purpose of diverting, replacing or protecting apparatus of a statutory undertaker, the undertaker may, with the consent of the Secretary of State, transfer the power to acquire such rights or impose such restrictions to the relevant statutory undertaker.

(6) The exercise by a statutory undertaker of any power in accordance with a transfer under paragraph (5) is subject to the same restrictions, liabilities and obligations as would apply under this Order if that power were exercised by the undertaker.

(7) Nothing in this article authorises the acquisition of rights over, or the imposition of restrictions affecting, an interest which is for the time being held by or on behalf of the Crown.

Section 24Acquisition of subsoil or airspace only

(1) The undertaker may compulsorily acquire so much of, or such rights in, the subsoil of, or the airspace of, the land referred to in article 22 (compulsory acquisition of land) and article 23 (compulsory acquisition of rights) as may be required for any purpose for which that land may be acquired or for which rights over or under the land may be acquired under those provisions instead of acquiring the whole of the land.

(2) Where the undertaker acquires any part of, or rights in, the subsoil of or the airspace over land under paragraph (1) , the undertaker is not required to acquire an interest in any other part of the land.

(3) The following do not apply in connection with the exercise of the power under paragraph (1) in relation to subsoil or airspace only—

(a) Schedule 2A (counter-notice requiring purchase of land not in notice to treat) to the 1965 Act (as modified by article 35 (application of Part 1 of the 1965 Act));

(b) Schedule A1 (counter-notice requiring purchase of land not in general vesting declaration) to the 1981 Act; and

(c) section 153(4A) (blighted land: proposed acquisition of part interest; material detriment test) of the 1990 Act.

(4) Paragraph (2) does not prevent article 33 (acquisition of part of certain properties) from applying where the undertaker acquires a cellar, vault, arch or other construction forming part of a house, building or manufactory.

(5) Subject to paragraph (6), any person who is an owner or occupier of land appropriated under paragraph (1) without the undertaker acquiring any part of that person’s interest in the land, and who suffers loss as a result, is entitled to compensation to be determined, in case of dispute, under Part 1 of the 1961 Act.

(6) Compensation is not payable under paragraph (5) to any person who is a statutory undertaker to whom section 85 (sharing of cost of necessary measures) of the 1991 Act applies in respect of measures of which the allowable costs are to be borne in accordance with that section.

Section 25Temporary use of land by National Grid

(1) National Grid may, in connection with the carrying out of the authorised development—

(a) enter on and take temporary possession of—

(i) so much of the land specified in column (1) of Schedule 10 (land of which only temporary possession may be taken) to exercise the powers described in the Book of Reference for the purpose specified in relation to that land in column (2) of that Schedule relating to the part of the authorised development specified in column (3) of that Schedule; and

(ii) any other Order land in respect of which no notice of entry has been served under section 11 of the 1965 Act (other than in connection with the acquisition of rights only) and no declaration has been made under section 4 of the 1981 Act;

(b) remove any electric line, electrical plant, buildings, structures, pylons, apparatus, equipment, vegetation or any other thing from that land;

(c) construct temporary or permanent works (including the provision of means of access and buildings or structures on that land); and

(d) construct any works specified in relation to that land in column (2) of Schedule 10 or any other mitigation works.

(2) Not less than 14 days before entering on and taking temporary possession of land under this article, National Grid must serve notice of the intended entry on the owners and occupiers of the land.

(3) National Grid may not, without the agreement of the owners of the land, remain in possession of any land under this article—

(a) in the case of land referred to in sub-paragraph (1) (a) (i) , after the end of the period of one year beginning with the date of completion of the part of the authorised development specified in relation to that land in column (3) of Schedule 10, or

(b) in the case of land referred to in sub-paragraph (1) (a) (ii) , after the end of the period of one year beginning with the date of completion of the work for which temporary possession of the land was taken unless National Grid has, by the end of that period, served a notice of entry under section 11 of the 1965 Act or made a declaration under section 4 of the 1981 Act in relation to that land.

(4) National Grid must provide the owners of any land of which temporary possession has been taken under this article with written notice of the date of completion of the works for which temporary possession was taken within 28 days of the completion of those works.

(5) Before giving up possession of land of which temporary possession has been taken under sub-paragraph (1) (a) (i) , unless otherwise agreed with the owners of the land, National Grid must remove all temporary works and restore the land to the reasonable satisfaction of the owners of the land, but National Grid is not required to—

(a) replace a building, structure, apparatus, equipment, electric line, electrical plant or pylon removed under this article;

(b) restore the land on which any works or mitigation have been carried out under sub-paragraph (1) (d) including insofar as the element of works shown in column (4) of Schedule 10 is concerned;

(c) remove any foundations below 1.5 metres which had been placed in that land to support pylons and electric lines constructed upon those foundations;

(d) remove any permanent work including pylons, electric lines, underground cables, or other permanent services, constructed or installed on, over, under or in that land as part of the authorised development;

(e) remove any ground-strengthening works (being either works listed in Schedule 10 of this Order or other works to provide safe and stable ground conditions) which have been placed in that land to facilitate construction of the authorised development;

(f) remove or reposition any apparatus belonging to statutory undertakers;

(g) remove any drainage works; or

(h) restore ground levels adjusted as part of the authorised development.

(6) Before giving up possession of land of which temporary possession has been taken under sub-paragraph (1) (a) (ii) , unless otherwise agreed by the owners of the land, National Grid must either acquire the land or the interest on, over, or in the land in accordance with the provisions of sub-paragraph (3) (b) or remove all temporary works and restore the land to the reasonable satisfaction of the owners of the land; but National Grid is not required to—

(a) replace a building, structure, apparatus, equipment, electric line, electrical plant or pylon removed under this article;

(b) restore the land on which any mitigation works have been carried out under sub-paragraph (1) (d) ;

(c) remove any foundations below 1.5 metres which had been placed in that land to support pylons and electric lines constructed upon those foundations;

(d) remove any permanent work including pylons, electric lines, underground cables, or other permanent services, constructed or installed on, over, under or in that land as part of the authorised development;

(e) remove any ground-strengthening works (being works to provide safe and stable ground conditions) which have been placed in that land to facilitate construction of the authorised development;

(f) remove or reposition any apparatus belonging to statutory undertakers;

(g) remove any drainage works; or

(h) restore ground levels adjusted as part of the authorised development.

(7) National Grid must pay compensation to the owners and occupiers of land of which temporary possession is taken under this article for any loss or damage arising from the exercise in relation to the land of the provisions of this article.

(8) Any dispute as to a person’s entitlement to compensation under paragraph (7) , or as to the amount of the compensation, must be determined under Part 1 of the 1961 Act.

(9) Nothing in this article affects any liability to pay compensation under section 152 of the 2008 Act (compensation in case where no right to claim in nuisance) or under any other enactment in respect of loss or damage arising from the carrying out of the authorised development, other than loss or damage for which compensation is payable under paragraph (7) .

(10) Where National Grid takes possession of land under this article, National Grid is not required to acquire the land or any interest in it.

(11) Section 13 of the 1965 Act (refusal to give possession to acquiring authority) applies to the temporary use of land pursuant to this article to the same extent as it applies to the compulsory acquisition of land under this Order by virtue of section 125 of the 2008 Act (application of compulsory acquisition provisions).

(12) Nothing in this article prevents National Grid from taking temporary possession more than once in relation to any land specified in sub-paragraph (1) (a) .

Section 26Temporary use of land by UKPN

(1) UKPN may, in connection with the carrying out of the UKPN Works—

(a) enter on and take temporary possession of—

(i) so much of the land specified in column (1) of Schedule 10 (Land of which only temporary possession may be taken) to exercise the powers described in the Book of Reference for the purpose specified in relation to that land in column (2) of that Schedule relating to the part of the authorised development specified in column (3) of that Schedule; and

(ii) any other Order land in respect of the UKPN Works in respect of which no notice of entry has been served under section 11 of the 1965 Act (other than in connection with the acquisition of rights only) and no declaration has been made under section 4 of the 1981 Act;

(b) remove any electric line, electrical plant, buildings, structures, pylons, apparatus, equipment, vegetation or any other thing from that land;

(c) construct temporary or permanent works (including the provision of means of access and buildings or structures on that land); and

(d) construct any works specified in relation to that land in column (2) ... of Schedule 10 or any other mitigation works.

(2) Not less than 14 days before entering on and taking temporary possession of land under this article, UKPN must serve notice of the intended entry on the owners and occupiers of the land.

(3) UKPN may not, without the agreement of the owners of the land, remain in possession of any land under this article—

(a) in the case of land referred to in sub-paragraph (1)(a)(i), after the end of the period of one year beginning with the date of completion of the part of the authorised development specified in relation to that land in column (3) of Schedule 10, or

(b) in the case of land referred to in sub-paragraph (1)(a)(ii), after the end of the period of one year beginning with the date of completion of the work for which temporary possession of the land was taken unless UKPN has, by the end of that period, served a notice of entry under section 11 of the 1965 Act or made a declaration under section 4 of the 1981 Act in relation to that land.

(4) UKPN must provide the owner(s) of any land of which temporary possession has been taken under this article with written notice of the date of completion of the works for which temporary possession was taken within 28 days of the completion of those works.

(5) Before giving up possession of land of which temporary possession has been taken under sub-paragraph (1)(a)(i), unless otherwise agreed with the owners of the land UKPN must remove all temporary works and restore the land to the reasonable satisfaction of the owners of the land, but UKPN is not required to—

(a) replace a building, structure, electric line, electrical plant or pylon removed under this article;

(b) restore the land on which any works have been carried out under sub-paragraph (1)(d) insofar as the element of works shown in column (4) of Schedule 10 is concerned;

(c) remove any foundations below 1.5 metres which had been placed in that land to support pylons and electric lines constructed upon those foundations; or

(d) remove any pylons or electric lines or underground cables constructed or installed on, over, under or in that land as part of the UKPN Works.

(6) Before giving up possession of land of which temporary possession has been taken under sub-paragraph (1)(a)(ii), unless otherwise agreed by the owners of the land, UKPN must either acquire the land or the interest on, over, or in the land in accordance with the provisions of paragraph (3)(b) or remove all temporary works and restore the land to the reasonable satisfaction of the owners of the land; but UKPN is not required to—

(a) replace a building, structure, electric line, electrical plant or pylon removed under this article;

(b) restore the land on which any works have been carried out under sub-paragraph (1)(d) insofar as the element of works shown in column (4) of Schedule 10 is concerned;

(c) remove any foundations below 1.5 metres which had been placed in that land to support pylons and electric lines constructed upon those foundations; or

(d) remove any pylons or electric lines or underground cables constructed or installed on, over, under or in that land as part of the UKPN Works.

(7) UKPN must pay compensation to the owners and occupiers of land of which temporary possession is taken under this article for any loss or damage arising from the exercise in relation to the land of the provisions of this article.

(8) Any dispute as to a person’s entitlement to compensation under paragraph (7), or as to the amount of the compensation, must be determined under Part 1 of the 1961 Act.

(9) Nothing in this article affects any liability to pay compensation under section 152 of the 2008 Act (compensation in case where no right to claim in nuisance) or under any other enactment in respect of loss or damage arising from the carrying out of the authorised development, other than loss or damage for which compensation is payable under paragraph (7).

(10) Where UKPN takes possession of land under this article, UKPN is not required to acquire the land or any interest in it.

(11) Section 13 of the 1965 Act (refusal to give possession to acquiring authority) applies to the temporary use of land pursuant to this article to the same extent as it applies to the compulsory acquisition of land under this Order by virtue of section 125 of the 2008 Act (application of compulsory acquisition provisions).

(12) Nothing in this article prevents—

(a) UKPN from taking temporary possession more than once in relation to any land specified in sub-paragraph (1)(a); or

(b) National Grid from taking temporary possession more than once in relation to any land specified in sub-paragraph (1)(a) of article 25.

Section 27Temporary use of land for maintaining the authorised development

(1) Subject to paragraph (2) , at any time during the maintenance period relating to any part of the authorised development, the undertaker may—

(a) enter upon and take temporary possession of any land within the Order limits if such possession is reasonably required for the purpose of maintaining the authorised development;

(b) construct such temporary works (including the provision of means of access) and buildings on the land as may be reasonably necessary for that purpose; and

(c) enter on any land within the Order limits for the purpose of gaining such access as is reasonably required for the purpose of maintaining the authorised development.

(2) Paragraph (1) does not authorise the undertaker to take temporary possession of—

(a) any house or garden belonging to a house; or

(b) any building (other than a house) if it is for the time being occupied.

(3) Not less than 28 days before entering upon and taking temporary possession of land under this article the undertaker must serve notice of the intended entry on the owners and occupiers of the land and that notice must explain the purpose for which entry is taken, except as provided in paragraph (11) .

(4) The undertaker may remain in possession of land under this article only for so long as may be reasonably necessary to carry out the maintenance of the part of the authorised development for which possession of the land was taken.

(5) Before giving up possession of land of which temporary possession has been taken under this article, the undertaker must remove all temporary works and restore the land to the reasonable satisfaction of the owners of the land.

(6) The undertaker must pay compensation to the owners and occupiers of land of which temporary possession is taken under this article for any loss or damage arising from the exercise in relation to the land of the powers conferred by this article.

(7) Any dispute as to a person’s entitlement to compensation under paragraph (6) , or as to the amount of the compensation, must be determined under Part 1 of the 1961 Act.

(8) Nothing in this article affects any liability to pay compensation under section 152 of the 2008 Act (compensation in case where no right to claim in nuisance) or under any other enactment in respect of loss or damage arising from the maintenance of the authorised development, other than loss or damage for which compensation is payable under paragraph (6) .

(9) Where the undertaker takes possession of land under this article, the undertaker is not required to acquire the land or any interest in it.

(10) Section 13 of the 1965 Act (refusal to give possession to the acquiring authority) applies to the temporary use of land pursuant to this article to the same extent as it applies to the compulsory acquisition of land under this Order by virtue of section 125 of the 2008 Act (application of compulsory acquisition provisions).

(11) Where the undertaker has identified a potential risk to the safety of—

(a) the authorised development or any part of it; or

(b) the public; or

(c) the surrounding environment,

the requirement to serve not less than 28 days’ notice under paragraph (3) does not apply and the undertaker may enter the land pursuant to paragraph (1) subject to giving such period of notice (if any) as is reasonably practicable in all the circumstances.

(12) In this article “ the maintenance period ” in relation to any part of the authorised development means the period of five years beginning with the date on which that part of the authorised development is brought into operational use, except where the authorised development is replacement or landscape planting where “ the maintenance period ” means the period of five years beginning with the date on which that part of the replacement or landscape planting is completed.

Section 28Use of subsoil under or airspace over streets

(1) The undertaker may enter on and use so much of the subsoil of, or airspace over, any street within the Order limits as may be required for the purposes of the authorised development or for any other purpose ancillary to the authorised development and may use the subsoil or airspace for those purposes.

(2) Subject to paragraph (3) , the undertaker may exercise any power conferred by paragraph (1) in relation to a street without being required to acquire any part of the street or any easement or right in the street.

(3) Paragraph (2) does not apply in relation to—

(a) any subway or underground building; or

(b) any cellar, vault, arch or other construction in, on or under a street which forms part of a building fronting onto the street.

(4) Subject to paragraph (5) , any person who is an owner or occupier of land appropriated under paragraph (1) without the undertaker acquiring any part of that person’s interest in the land, and who suffers loss as a result, is entitled to compensation to be determined, in case of dispute, under Part 1 of the 1961 Act.

(5) Compensation is not payable under paragraph (4) to any person who is an undertaker to whom section 85 of the 1991 Act (sharing cost of necessary measures) applies in respect of measures of which the allowable costs are to be borne in accordance with that section.

Section 29Disregard of certain interests and improvements

(1) In assessing the compensation payable to any person on the acquisition from that person of any land or right over any land under this Order, the Tribunal must not take into account—

(a) any interest in land; or

(b) any enhancement of the value of any interest in land by reason of any building erected, works executed or improvement or alteration made on relevant land,

if the Tribunal is satisfied that the creation of the interest, the erection of the building, the execution of the works or the making of the improvement or alteration as part of the authorised development was not reasonably necessary and was undertaken with a view to obtaining compensation or increased compensation.

(2) In paragraph (1) “ relevant land ” means the land acquired from the person concerned or any other land with which that person is, or was at the time when the building was erected, the works executed or the improvement or alteration made as part of the authorised development, directly or indirectly concerned.

Section 30Set-off for enhancement in value of retained land

(1) In assessing the compensation payable to any person in respect of the acquisition from that person under this Order of any land (including any subsoil) the tribunal must set off against the value of the land so acquired any increase in value of any contiguous or adjacent land belonging to that person in the same capacity which will accrue to that person by reason of the construction of the authorised development.

(2) In assessing the compensation payable to any person in respect of the acquisition from that person of any new rights over land (including the subsoil), under article 23 (compulsory acquisition of rights), the Tribunal must set off against the value of the rights so acquired—

(a) any increase in the value of the land over which the new rights are required; and

(b) any increase in value of any contiguous or adjacent land belonging to that person in the same capacity,

which will accrue to that person by reason of the construction of the authorised development.

(3) The 1961 Act has effect, subject to paragraphs (1) and (2), as if this Order were a local enactment for the purposes of that Act.

Section 31Compulsory acquisition of land – incorporation of the mineral code

Parts 2 and 3 of Schedule 2 to the Acquisition of Land Act 1981 (minerals) are incorporated into this Order subject to the modifications that—

(a) paragraph 8(3) is not incorporated;

(b) for “the acquiring authority” substitute “the undertaker” ;

(c) for “undertaking” substitute “authorised development” ; and

(d) for “compulsory purchase order” substitute “this Order” .

Section 32Time limit for exercise of authority to acquire land and rights compulsorily

(1) After the end of the period of five years beginning with the day on which this Order comes into force—

(a) no notice to treat may be served under Part 1 of the 1965 Act; and

(b) no declaration may be executed under section 4 of the 1981 Act as applied by article 34 (application of the 1981 Act) .

(2) The authority conferred by article 25 (temporary use of land by National Grid) and article 26 (temporary use of land by UKPN) ceases at the end of the period referred to in paragraph (1) , save that nothing in this paragraph prevents the undertaker remaining in possession of land after the end of that period, if the land was entered and possession was taken before the end of that period.

(3) If any proceedings are begun to challenge the validity of this Order, the period specified in paragraph (1) is extended for the period specified in paragraph (4).

(4) Under paragraph (3) the period is taken to be extended by—

(a) a period equivalent to the period beginning with the day the proceedings are filed and ending on the day they are withdrawn or finally determined, or

(b) if shorter, one year.

(5) Proceedings are not finally determined for the purposes of sub-paragraph (4)(a) if any appeal—

(a) could be brought (ignoring any possibility of an appeal out of time with permission), or

(b) has been made and not withdrawn or finally determined.

Section 33Acquisition of part of certain properties

(1) This article applies where—

(a) a notice to treat is served on a person (“ the owner ”) under the 1965 Act (as so applied) in respect of land forming only part of a house, building or factory or of land consisting of a house with a park or garden (“ the land subject to the notice to treat ”); and

(b) a copy of this article is served on the owner with the notice to treat.

(2) In such a case, the owner may, within the period of 28 days beginning with the day on which the notice was served, serve on the undertaker a counter-notice objecting to the sale of the land subject to the notice to treat and stating that the owner is willing and able to sell the whole (“ the land subject to the counter-notice ”).

(3) If no such counter-notice is served within that period, the owner is required to sell the land subject to the notice to treat.

(4) If such a counter-notice is served within that period, the question whether the owner is required to sell only the land subject to the notice to treat must, unless the undertaker agrees to take the land subject to the counter-notice, be referred to the tribunal.

(5) If on such a reference the tribunal determines that the land subject to the notice to treat can be taken—

(a) without material detriment to the remainder of the land subject to the counter-notice; or

(b) where the land subject to the notice to treat consists of a house with a park or garden, without material detriment to the remainder of the land subject to the counter-notice and without seriously affecting the amenity and convenience of the house,

the owner is required to sell the land subject to the notice to treat.

(6) If on such a reference the tribunal determines that only part of the land subject to the notice to treat can be taken—

(a) without material detriment to the remainder of the land subject to the counter-notice; or

(b) where the land subject to the notice to treat consists of a house with a park or garden, without material detriment to the remainder of the land subject to the counter-notice and without seriously affecting the amenity and convenience of the house,

the notice to treat is deemed to be a notice to treat for that part.

(7) If on such a reference the tribunal determines that—

(a) the land subject to the notice to treat cannot be taken without material detriment to the remainder of the land subject to the counter-notice; but

(b) the material detriment is confined to a part of the land subject to the counter-notice,

the notice to treat is deemed to be a notice to treat for the land to which the material detriment is confined in addition to the land already subject to the notice, whether or not the additional land is land which the undertaker is authorised to acquire compulsorily under this Order.

(8) If the undertaker agrees to take the land subject to the counter-notice, or if the tribunal determines that—

(a) none of the land subject to the notice to treat can be taken without material detriment to the remainder of the land subject to the counter-notice or, as the case may be, without material detriment to the remainder of the land subject to the counter-notice and without seriously affecting the amenity and convenience of the house; and

(b) the material detriment is not confined to a part of the land subject to the counter-notice,

the notice to treat is deemed to be a notice to treat for the land subject to the counter-notice whether or not the whole of that land is land which the undertaker is authorised to acquire compulsorily under this Order.

(9) Where by reason of a determination by the tribunal under this article a notice to treat is deemed to be a notice to treat for less land or more land than that specified in the notice, the undertaker may, within the period of six weeks beginning with the day on which the determination is made, withdraw the notice to treat; and, in that event, must pay the owner compensation for any loss or expense occasioned to the owner by the giving and withdrawal of the notice, to be determined in case of dispute by the tribunal.

(10) Where the owner is required under this article to sell only part of a house, building or manufactory or of land consisting of a house with a park or garden, the undertaker must pay the owner compensation for any loss sustained by the owner due to the severance of that part in addition to the value of the interest acquired.

Section 34Application of the 1981 Act

(1) The 1981 Act applies as if this Order were a compulsory purchase order.

(2) The 1981 Act, as so applied, has effect with the following modifications.

(3) In section 1 (application of Act) for subsection (2) there is substituted—

(2) This section applies to any Minister, any local or other public authority or any other body or person authorised to acquire land by means of a compulsory purchase order.

(4) In section 5(2) (earliest date for execution of declaration), omit the words from “, and this subsection” to the end.

(5) Section 5A (time limit for general vesting declaration) is omitted.

(6) In section 5B (extension of time limit during challenge)—

(a) for “section 23 of the Acquisition of Land Act 1981 (application to High Court in respect of compulsory purchase order)” substitute “section 118 of the Planning Act 2008 (legal challenges relating to applications for orders granting development consent)” ; and

(b) for “the three year period mentioned in section 5A” substitute “the five year period mentioned in article 32 of the National Grid (Bramford to Twinstead Reinforcement) Order 2024” .

(7) For section 6(1)(b) (notices after execution of declaration) substitute—

(b) on every other person who has given information to the acquiring authority with respect to any of that land further to the invitation published and served under section 134 (notice of authorisation of compulsory acquisition) of the Planning Act 2008.

(8) In section 7(1)(a) (constructive notice to treat), omit “(as modified by section 4 of the Acquisition of Land Act 1981)”.

(9) In Schedule A1 (counter-notice requiring purchase of land not in general vesting declaration), for paragraph 1(2) substitute—

(2) But see article 24(3) (acquisition of subsoil or airspace only) of the National Grid (Bramford to Twinstead Reinforcement) Order 2024, which excludes the acquisition of subsoil or airspace only from this Schedule.

(10) References to the 1965 Act in the 1981 Act must be construed as references to the 1965 Act as applied by section 125 of the 2008 Act (application of compulsory acquisition provisions) and as modified by article 36 to the compulsory acquisition of land under this Order.

Section 35Application of Part 1 of the 1965 Act

(1) Part 1 of the 1965 Act as applied by section 125 (application of compulsory acquisition provisions) of the 2008 Act is modified as follows.

(2) In section 4 (time limit for giving notice to treat) for “after the end of the period of 3 years beginning with the day on which the compulsory purchase order becomes operative” substitute “after the end of the period stated in article 32 (time limit for exercise of authority to acquire land and rights compulsorily) of the National Grid (Bramford to Twinstead Reinforcement) Order 2024” .

(3) In section 4A(1) (extension of time limit during challenge)—

(a) for “section 23 of the Acquisition of Land Act 1981 (application to the High Court in respect of compulsory purchase order)” substitute “section 118 of the Planning Act 2008 (legal challenges relating to applications for orders granting development consent)” ; and

(b) for “the three year period mentioned in section 4” substitute “the five year period mentioned in article 32 (time limit for exercise of authority to acquire land and rights compulsorily) of the National Grid (Bramford to Twinstead Reinforcement) Order 2024” .

(4) In section 11A (powers of entry: further notices of entry)—

(a) in subsection (1)(a), after “land” insert “under that provision” ; and

(b) in subsection (2), after “land” insert “under that provision” .

(5) In section 22(2) (expiry of time limit for exercise of compulsory purchase power not to affect acquisition of interests omitted from purchase), for “section 4 of this Act” substitute “article 32 (time limit for exercise of authority to acquire land and rights compulsorily) of the National Grid (Bramford to Twinstead Reinforcement) Order 2024” .

(6) In Schedule 2A (counter-notice requiring purchase of land not in notice to treat)—

(a) for paragraphs 1(2) and 14(2) substitute—

(2) But see article 24(3) (acquisition of subsoil or airspace only) of the National Grid (Bramford to Twinstead Reinforcement) Order 2024, which excludes the acquisition of subsoil or airspace only from this Schedule

(b) and after paragraph 29, insert—

INTERPRETATION

(30) In this Schedule, references to entering on and taking possession of land do not include doing so under article 20 (protective works), 25 (temporary use of land by National Grid), 26 (temporary use of land by UKPN) or 27 (temporary use of land for maintaining the authorised development) of the National Grid (Bramford to Twinstead Reinforcement) Order 2024.

Section 36Extinguishment and suspension of private rights

(1) Subject to the provisions of this article, all private rights and restrictive covenants over land subject to compulsory acquisition under this Order are extinguished or suspended—

(a) as from the date of acquisition of the land by the undertaker, whether compulsorily or by agreement; or

(b) on the date of entry on the land by the undertaker under section 11(1) of the 1965 Act (powers of entry) ,

whichever is the earlier.

(2) Subject to the provisions of this article, all private rights and restrictive covenants over land owned by the undertaker which, being within the Order limits, is required for the purposes of this Order, are extinguished on the start of any activity authorised by this Order which interferes with or breaches such rights or such restrictive covenants.

(3) Subject to the provisions of this article, all private rights and restrictive covenants over land subject to the compulsory acquisition of rights or the imposition of restrictions under this Order are extinguished in so far as their continuance would be inconsistent with the exercise of the right acquired or the burden of the restriction imposed—

(a) as from the date of the acquisition of the right or the benefit of the restriction by the undertaker, whether compulsorily or by agreement; or

(b) on the date of entry on the land by the undertaker under section 11(1) of the 1965 Act in pursuance of the right,

whichever is the earlier.

(4) Subject to the provisions of this article and article 39 (extinguishment of private rights and restrictive covenants relating to apparatus belonging to National Grid or UKPN removed from land subject to temporary possession), all private rights or restrictive covenants over land of which the undertaker takes temporary possession under this Order are suspended and unenforceable for as long as the undertaker remains in lawful possession of the land and in so far as their continuation would be inconsistent with the exercise of the powers under this Order or a breach of a restriction as to the user of land arising by virtue of a contract.

(5) Any person who suffers loss by the extinguishment or suspension of any private right or restrictive covenant under this article is entitled to compensation in accordance with the terms of section 152 of the 2008 Act (compensation in case where no right to claim in nuisance) to be determined, in case of dispute, under Part 1 of the 1961 Act.

(6) This article does not apply in relation to any right to which section 138 of the 2008 Act (extinguishment of rights, and removal of apparatus, of statutory undertakers etc.) or article 42 (statutory undertakers) applies.

(7) Paragraphs (1) to (4) have effect subject to—

(a) any notice given by the undertaker before—

(i) the completion of the acquisition of the land or rights or the imposition of restrictive covenants over or affecting the land;

(ii) the undertaker’s appropriation of it;

(iii) the undertaker’s entry onto it; or

(iv) the undertaker’s taking temporary possession of it,

that any or all of those paragraphs do not apply to any right specified in the notice; and

(b) any agreement made, in so far as it relates to the authorised development, at any time between the undertaker and the person in or to whom the right or restrictive covenant in question is vested, belongs or benefits.

(8) If any such agreement as is referred to in sub-paragraph (7)(b)—

(a) is made with a person in or to whom the right is vested or belongs; and

(b) is expressed to have effect also for the benefit of those deriving title from or under that person,

it is effective in respect of the persons so deriving title, whether the title was derived before or after the making of the agreement.

(9) A reference in this article to private rights and restrictive covenants over land includes any trust, incident, easement, wayleave, liberty, privilege, right or advantage annexed to land (including any land forming part of a common, open space or fuel or field garden allotment) and adversely affecting other land, including any natural right to support, and including restrictions as to the user of land arising by virtue of a contract.

Section 37Power to override easements and other rights

(1) Any authorised activity which takes place on land within the Order limits (whether the activity is undertaken by the undertaker or by any person deriving title from the undertaker or by any servants or agents of the undertaker) is authorised by this Order if it is done in accordance with the terms of this Order, notwithstanding that it involves—

(a) an interference with an interest or right to which this article applies; or

(b) a breach of a restriction as to the user of land arising by virtue of a contract.

(2) In this article “ authorised activity ” means—

(a) the erection, construction or maintenance of any part of the authorised development;

(b) the exercise of any power authorised by this Order; or

(c) the use of any land (including the temporary use of land).

(3) The interests and rights to which this article applies include any trust, incident, easement, wayleave, liberty, privilege, right or advantage annexed to land (including any land forming part of a common, open space or fuel or field garden allotment) and adversely affecting other land, including any natural right to support, and including restrictions as to the user of land arising by virtue of a contract.

(4) Where an interest, right or restriction is overridden by paragraph (1) , compensation—

(a) is payable under section 7 (measure of compensation in case of severance) or 10 (further provision as to compensation for injurious affection) of the 1965 Act; and

(b) is to be assessed in the same manner and subject to the same rules as in the case of other compensation under those sections where—

(i) the compensation is to be estimated in connection with a purchase under that Act; or

(ii) the injury arises from the execution of works on or use of land acquired under that Act.

(5) Where a person deriving title under the undertaker by whom the land in question was acquired—

(a) is liable to pay compensation by virtue of paragraph (4) , and

(b) fails to discharge that liability,

the liability is to be enforceable against that undertaker in accordance with section 204(3) of the Housing and Planning Act 2016 .

(6) Nothing in this article is to be construed as authorising any act or omission on the part of any person which is actionable at the suit of any person on any grounds other than such an interference or breach as is mentioned in paragraph (1) of this article.

Section 38Statutory authority to override easements and other rights

(1) The carrying out or use of development authorised by this Order and the doing of anything else authorised by this Order is authorised by virtue of section 158 (nuisance: statutory authority) of the 2008 Act, notwithstanding that it involves—

(a) an interference with an interest or right to which this article applies; or

(b) a breach of a restriction as to user of land arising by virtue of contract.

(2) The undertaker must pay compensation to any person whose land is injuriously affected by—

(a) an interference with an interest or right to which this article applies; or

(b) a breach of a restriction as to user of land arising by virtue of contract,

authorised by virtue of this Order and the operation of section 158 of the 2008 Act.

(3) The interests and rights to which this article applies include any trust, incident, easement, wayleave, liberty, privilege, right or advantage annexed to land (including any land forming part of a common, open space or fuel or field garden allotment) and adversely affecting other land, including any natural right to support, and including restrictions as to the user of land arising by virtue of a contract.

(4) Subsection (2) of section 10 (further provision as to compensation for injurious affection) of the 1965 Act applies to paragraph (2) by virtue of section 152(5) of the 2008 Act.

(5) Any rule or principle applied to the construction of section 10 of the 1965 Act will be applied to the construction of paragraph (2) (with any necessary modifications).

Section 39Extinguishment of private rights and restrictive covenants relating to apparatus belonging to National Grid or UKPN removed from land subject to temporary possession

(1) This article applies to any Order land specified in Schedule 11 (extinguishment of private rights and restrictive covenants relating to apparatus belonging to National Grid or UKPN removed from land subject to temporary possession) and any other Order land of which National Grid takes temporary possession under article 25 (temporary use of land by National Grid) or UKPN takes temporary possession under article 26 (temporary use of land by UKPN).

(2) All private rights or restrictive covenants in relation to apparatus belonging to National Grid or UKPN removed from any land to which this article applies are extinguished from the date on which National Grid or UKPN gives up temporary possession of that land under article 25 (temporary use of land by National Grid) or 26 (temporary use of land by UKPN), as the case may be.

(3) The extinguishment of rights by paragraph (2) does not give rise to any cause of action relating to the presence on or in the land of any foundations (save for those which lie less than 1.5 metres underground) referred to in sub-paragraph (5)(c) and (6)(c) of article 25 or sub-paragraph (5)(c) and (6)(c) of article 26 (National Grid and UKPN not required to remove foundations when giving up temporary possession).

(4) Schedule 11 (extinguishment of private rights and restrictive covenants relating to apparatus belonging to National Grid or UKPN removed from land subject to temporary possession) has effect.

Section 40Crown rights

(1) Nothing in this Order affects prejudicially any estate, right, power, privilege, authority or exemption of the Crown and, in particular, nothing in this Order authorises the undertaker or any licensee to take, use, enter on or in any manner interfere with any land or rights of any description (including any part of the shore or bed of the sea or any river, channel, creek, bay or estuary)—

(a) belonging to His Majesty in right of the Crown and forming part of the Crown Estate, without the consent in writing of the Crown Estate Commissioners;

(b) belonging to His Majesty in right of the Crown and not forming part of the Crown Estate, without the consent in writing of the government department having the management of that land; or

(c) belonging to a government department or held in trust for His Majesty for the purposes of a government department, without the consent in writing of that government department.

(2) Paragraph (1) does not apply to the exercise of any right under this Order for the compulsory acquisition of an interest in any Crown land (as defined in section 227 of the 2008 Act) that is for the time being held otherwise than by or on behalf of the Crown.

(3) A consent under paragraph (1) —

(a) may be given unconditionally or subject to terms and conditions; and

(b) is deemed to have been given in writing where it is sent electronically.

Section 41Special category land

(1) So much of the special category land that is required for the purposes of the exercising by the undertaker of the Order rights will be discharged from all rights, trusts and incidents to which it was previously subject so far as their continuance would be inconsistent with the exercise of the Order rights.

(2) In this article—

“ Order rights ” means the rights exercisable over the special category land by the undertaker under article 23 (compulsory acquisition of rights); and

“ special category land ” means the land as forming part of a common, open space, or fuel or field allotment and which is identified in the book of reference and marked as such on the plan entitled “special category land plans”.

Section 42Statutory undertakers

(1) Subject to the provisions of Schedule 14 (protective provisions) the undertaker may—

(a) further to the power in article 22 (compulsory acquisition of land), acquire compulsorily the Order land belonging to statutory undertakers, and described in the book of reference;

(b) extinguish or suspend the rights of, remove or reposition apparatus belonging to statutory undertakers where such apparatus is anywhere over or within the Order limits notwithstanding that repositioning may be outside of the Order limits;

(c) further to the power in article 23 (compulsory acquisition of rights), acquire compulsorily existing rights, create and acquire the new rights and impose restrictive covenants over land belonging to statutory undertakers described in the book of reference and indicated on the land plans;

(d) construct the authorised development in such a way as to cross underneath or over apparatus belonging to statutory undertakers and other like bodies within the Order limits; and

(e) construct over existing apparatus belonging to statutory undertakers any necessary track or roadway (whether temporary or permanent) together with the right to maintain or remove the same and install such service media under or over the existing apparatus needed in connection with the authorised development.

(2) Paragraph (1)(b) has no effect in relation to apparatus in respect of which Part 3 (street works in England and Wales) of the 1991 Act applies.

Section 43Recovery of costs of new connections

(1) Where any apparatus of a public utility undertaker or of a public communications provider is removed under article 42 (statutory undertakers), any person who is the owner or occupier of premises to which a supply was given from that apparatus is entitled to recover from the undertaker compensation in respect of expenditure reasonably incurred by that person, in consequence of the removal, for the purpose of effecting a connection between the premises and any other apparatus from which a supply is given.

(2) Paragraph (1) does not apply in the case of the removal of a public sewer, but where such a sewer is removed under article 42 (statutory undertakers) any person who is—

(a) the owner or occupier of premises the drains of which communicated with that sewer; or

(b) the owner of a private sewer which communicated with that sewer,

is entitled to recover from the undertaker compensation in respect of expenditure reasonably incurred by that person, in consequence of the removal, for the purpose of making the drain or sewer belonging to that person communicate with any other public sewer or with a private sewerage disposal plant.

(3) In this article—

“ public communications provider ” has the same meaning as in section 151(1) of the 2003 Act; and

“ public utility undertaker ” means a gas, water, electricity or sewerage undertaker.

Section 44Application of landlord and tenant law

(1) This article applies to—

(a) any agreement for leasing to any person the whole or any part of the authorised development or the right to operate the same; and

(b) any agreement entered into by the undertaker with any person for the construction, maintenance, use or operation of the authorised development, or any part of it,

so far as any such agreement relates to the terms on which any land which is the subject of a lease granted by or under that agreement is to be provided for that person’s use.

(2) No enactment or rule of law regulating the rights and obligations of landlords and tenants prejudices the operation of any agreement to which this article applies.

(3) Accordingly, no such enactment or rule of law applies in relation to the rights and obligations of the parties to any lease granted by or under any such agreement so as to—

(a) exclude or in any respect modify any of the rights and obligations of those parties under the terms of the lease, whether with respect to the termination of the tenancy or any other matter;

(b) confer or impose on any such party any right or obligation arising out of or connected with anything done or omitted on or in relation to land which is the subject of the lease, in addition to any such right or obligation provided for by the terms of the lease; or

(c) restrict the enforcement (whether by action for damages or otherwise) by any party to the lease of any obligation of any other party under the lease.

Section 45Defence to proceedings in respect of statutory nuisance

(1) Where proceedings are brought under section 82(1) of the Environmental Protection Act 1990 (summary proceedings by persons aggrieved by statutory nuisances) in relation to a nuisance falling within paragraphs (g) and (ga) of section 79(1) of that Act no order must be made, and no fine must be imposed, under section 82(2) of that Act if—

(a) the defendant shows that the nuisance—

(i) relates to premises used by the undertaker for the purposes of or in connection with the construction or maintenance of the authorised development and that the nuisance is attributable to the carrying out of the authorised development in accordance with a notice served under section 60 (control of noise on construction sites ) or a consent given under section 61 (prior consent for work on construction sites ) of the Control of Pollution Act 1974 ; or

(ii) relates to premises used by the undertaker for the purposes of or in connection with the construction of the authorised development and that the nuisance is attributable to the carrying out of the authorised development in accordance with the controls and measures relating to noise as described in the relevant construction environmental management plan approved pursuant to requirement 4; or

(iii) is a consequence of the construction or maintenance of the authorised development and that it cannot reasonably be avoided; or

(iv) is a consequence of complying with a requirement of this Order and that it cannot reasonably be avoided; or

(b) the defendant shows that the nuisance is a consequence of the use of the authorised development and that it cannot reasonably be avoided.

(2) For the purposes of paragraph (1) above in relation to the construction of the authorised development only, compliance with the controls and measures relating to noise described in the relevant construction environmental management plan approved pursuant to requirement 4 will be sufficient, but not necessary, to show that an alleged nuisance could not reasonably be avoided.

(3) Where a relevant planning authority is acting in accordance with section 60(4) and section 61(4) of the Control of Pollution Act 1974 in relation to the construction of the authorised development then the local authority must also have regard to the controls and measures relating to noise referred to in the relevant construction environmental management plan approved pursuant to requirement 4.

(4) Section 61(9) of the Control of Pollution Act 1974 does not apply where the consent relates to the use of premises by the undertaker for the purposes of or in connection with the construction or maintenance of the authorised development.

(5) In this article “ premises ” has the same meaning as in section 79 of the Environmental Protection Act 1990 .

Section 46Traffic regulation

(1) Subject to the provisions of this article, the undertaker may at any time for the purposes of construction of the authorised development or for purposes ancillary to the construction of the authorised development—

(a) prohibit waiting of vehicles and regulate vehicular speed by imposing a speed restriction on vehicles in the manner specified in Part 1 of Schedule 12 (traffic regulation orders) on a road specified in column (2) and along the lengths and between the points specified in column (3) in the manner specified in column (4) of that Part of that Schedule;

(b) prohibit use of roads by through traffic in the manner specified in Part 2 of Schedule 12 (traffic regulation orders) on the roads specified in column (2) and along the lengths and between the points specified in column (3) in the manner specified in column (4) of that Part of that Schedule;

(c) regulate the direction of vehicular movements in the manner specified in Part 3 of Schedule 12 (traffic regulation orders) on the roads specified in column (2) and along the lengths and between the points specified in column (3) in the manner specified in column (4) of that Part of that Schedule; and

(d) prohibit overtaking in the manner specified in Part 4 of Schedule 12 (traffic regulation orders) on the roads specified in column (2) and along the lengths and between the points specified in column (3) in the manner specified in column (4) of that Part of that Schedule.

(2) Without limiting the scope of the specific powers conferred by paragraph (1) but subject to the provisions of this article and the consent of the traffic authority in whose area the road concerned is situated, the undertaker may, in so far as may be expedient or necessary for the purposes of or in connection with construction of the authorised development, or for purposes ancillary to it, at any time—

(a) revoke, amend or suspend in whole or in part any order made, or having effect as if made, under the 1984 Act;

(b) permit, prohibit or restrict the stopping, parking, waiting, loading or unloading of vehicles on any road;

(c) authorise the use as a parking place of any road;

(d) make provision as to the maximum speed, direction or priority of vehicular traffic on any road; and

(e) permit, prohibit or restrict vehicular access to any road,

either at all times or at times, on days or during such periods as may be specified by the undertaker.

(3) The undertaker must not exercise the powers in paragraphs (1) and (2) unless it has—

(a) given not less than four weeks’ notice in writing of its intention so to do to the chief officer of police and to the traffic authority in whose area the road is situated; and

(b) advertised its intention in such manner as the traffic authority may specify in writing within seven days of its receipt of notice of the undertaker’s intention as provided for in sub-paragraph (a) .

(4) Any prohibition, restriction or other provision made by the undertaker under paragraph (1) or (2) —

(a) has effect as if duly made by—

(i) the traffic authority in whose area the road is situated as a traffic regulation order under the 1984 Act; or

(ii) the local authority in whose area the road is situated as an order under section 32 of the 1984 Act (power of local authorities to provide parking places),

and the instrument by which it is effected may specify savings and exemptions (in addition to those mentioned in Schedule 12 (traffic regulation orders)) to which the prohibition, restriction or other provision is subject; and

(b) is deemed to be a traffic order for the purposes of Schedule 7 to the Traffic Management Act 2004 (road traffic contraventions subject to civil enforcement).

(5) Any prohibition, restriction or other provision made under this article may at any time be suspended, varied or revoked by the undertaker from time to time by subsequent exercise of the powers conferred by paragraphs (1) and (2) .

(6) Any prohibition, restriction or other provision made by the undertaker under paragraph (1) or (2) will cease to have effect on the expiry of the period of five years beginning with the date on which the authorised development is first brought into operational use, except where the authorised development is replacement or landscape planting in which case the period of five years will begin with the date on which that part of the replacement or landscape planting is completed.

(7) If any prohibition, restriction or other provision has been made by the undertaker under paragraph (1) or (2), then before the expiration of the period referred to in paragraph (6) the undertaker must—

(a) give at least four weeks’ notice in writing to the chief officer of police and to the traffic authority in whose area the road is situated; and

(b) advertise the fact in such manner as the traffic authority may specify in writing within seven days of its receipt of notice of the undertaker’s notice as provided for in sub-paragraph (a).

(8) Before complying with the provisions of paragraphs (3) and (7) the undertaker must consult the chief officer of police and the traffic authority in whose area the road is situated.

(9) Expressions used in this article and in the 1984 Act have the same meaning in this article as in that Act.

(10) If the traffic authority fails to notify the undertaker of its decision within 35 days (or such other period as agreed by the traffic authority and the undertaker) of receiving an application for consent under paragraph (2) the traffic authority is deemed to have granted consent.

(11) Any application for consent under paragraph (2) must include a statement that the provisions of paragraph (10) apply to that application.

(12) If an application for consent under paragraph (2) does not include the statement required under paragraph (11) , then the provisions of paragraph (10) will not apply to that application.

Section 47Felling or lopping

(1) The undertaker may fell, lop, prune, cut, trim, coppice, pollard, or reduce in height or width, any tree, shrub, shrubbery, hedgerow, or important hedgerow under or within or overhanging or near any part of the authorised development, or cut back its roots, if it reasonably believes it to be necessary to do so to prevent the tree, shrub, shrubbery, hedgerow or important hedgerow—

(a) from obstructing or interfering with the construction, maintenance or operation of the authorised development or any apparatus used in connection with the authorised development; or

(b) from constituting a danger to persons constructing, maintaining, or operating the authorised development.

(2) In carrying out any activity authorised by paragraph (1), the undertaker must not cause any unnecessary damage to any tree, shrub, shrubbery or hedgerow, or important hedgerow and must pay compensation to any person for any loss or damage arising from such activity.

(3) Any dispute as to a person’s entitlement to compensation under paragraph (2), or as to the amount of compensation, must be determined under Part 1 of the 1961 Act.

(4) Subject at all times to paragraph (8), the undertaker must not pursuant to paragraph (1) fell, lop, prune, cut, trim, coppice, pollard, or reduce in height or width a tree within or overhanging the extent of the public highway without the consent of the relevant highway authority.

(5) If the relevant highway authority fails to notify the undertaker of its decision within 35 days (or such other period as agreed by the relevant highway authority and the undertaker) of receiving an application for consent under paragraph (4) the relevant highway authority is deemed to have granted consent.

(6) Any application for consent under paragraph (4) must include a statement that the provisions of paragraph (5) apply to that application.

(7) If an application for consent under paragraph (4) does not include the statement required under paragraph (6), then the provisions of paragraph (5) will not apply to that application.

(8) The consent of the relevant highway authority is not required under paragraph (4) where—

(a) the tree to be felled, lopped, pruned, cut, trimmed, coppiced, pollarded, or reduced in height or width is described or shown as ‘affected vegetation’ on the trees and hedgerows to be removed or managed plans ; and

(b) the undertaker has given 5 days notice to the relevant highway authority of its intention to carry out any of the operations described in sub-paragraph (a).

(9) The power conferred by paragraph (1) removes any obligation upon the undertaker to secure any consent to remove hedgerows under the Hedgerows Regulations 1997 .

(10) In this article “ hedgerow ” and “ important hedgerow ” have the same meaning as in the Hedgerow Regulations 1997.

Section 48Trees subject to Tree Preservation Orders

(1) The undertaker may fell, lop, prune, cut, trim, coppice, pollard, or reduce in height or width, any tree described in Schedule 13 (trees subject to tree preservation orders) and identified on the trees and hedgerows to be removed or managed plans, or cut back its roots, if it reasonably believes it to be necessary in order to do so to prevent the tree—

(a) from obstructing or interfering with the construction, maintenance or operation of the authorised development or any apparatus used in connection with the authorised development; or

(b) from constituting a danger to persons constructing, maintaining, or operating the authorised development.

(2) The undertaker may fell, lop, prune, cut, trim, coppice, pollard, or reduce in height or width, any tree within or overhanging land within the Order limits subject to a tree preservation order which was made after 31 January 2023, or cut back its roots, if it reasonably believes it to be necessary to do so in order to prevent the tree—

(a) from obstructing or interfering with the construction, maintenance or operation of the authorised development or any apparatus used in connection with the authorised development; or

(b) from constituting a danger to persons constructing, maintaining, or operating the authorised development.

(3) In carrying out any activity authorised by paragraph (1) or (2) —

(a) the undertaker must do no unnecessary damage to any tree and must pay compensation to any person for any damage arising from such activity; and

(b) the duty in section 206(1) of the 1990 Act (replacement of trees) does not apply.

(4) The authority given by paragraphs (1) and (2) constitutes a deemed consent under the relevant tree preservation order.

(5) Any dispute as to a person’s entitlement to compensation under paragraph (3) , or as to the amount of compensation, must be determined under Part 1 of the 1961 Act.

Section 49Temporary closure of, and works in, the River Stour

(1) The undertaker may, in connection with the construction of the authorised development, temporarily interfere with the relevant part of the river.

(2) Without limitation on the powers conferred by paragraph (1) but subject to paragraph (4) the undertaker may, in connection with the construction of the authorised development—

(a) temporarily moor or anchor barges or other vessels or craft in the relevant part of the river and may load or unload into and from such barges, other vessels or craft equipment, machinery, soil and any other materials in connection with the construction or maintenance of the authorised development; and

(b) on grounds of health and safety only, temporarily close to navigation the relevant part of the river.

(3) The power conferred by paragraphs (1) and (2) will be exercised in such a way which secures—

(a) that no more of the relevant part of the river is closed to navigation at any time than is necessary in the circumstances; and

(b) that, if complete closure to navigation of the relevant part of the river becomes necessary, all reasonable steps are taken to secure that the period of closure is kept to a minimum and that the minimum obstruction, delay or interference is caused to vessels or craft which may be using or intending to use the part so closed.

(4) Any person who suffers loss as a result of the suspension of any private right of navigation under this article is entitled to be paid compensation for such loss by the undertaker, to be determined, in case of dispute, under Part 1 of the 1961 Act.

(5) In this article, “ the relevant part of the river ” means so much of the River Stour as is shown shaded yellow on the access, rights of way and public rights of navigation plans.

Section 50Protection of interests

Schedule 14 (protective provisions) has effect.

159 sections

Cite this legislation

The National Grid (Bramford to Twinstead Reinforcement) Order 2024 (legislation.gov.uk, OGL v3.0). Retrieved via LawPlayer, https://lawplayer.com/uk/act/uksi-2024-958

Contains public sector information licensed under the Open Government Licence v3.0.

OGL-3

本頁資料來源:legislation.gov.uk (The National Archives)·整理提供:法律人 LawPlayer· lawplayer.com