Statutory Instrument

The Access to the Countryside (Coastal Margin) (Birkenhead to the Welsh border) Order 2025

Citation
S.I. 2025/90
As at
Sections
2
Section 1Citation, commencement and interpretation

(1) This Order may be cited as the Access to the Countryside (Coastal Margin) (Birkenhead to the Welsh border) Order 2025 and comes into force on the day after the day on which it is made.

(2) In this Order—

“ the Act ” means the National Parks and Access to the Countryside Act 1949 ;

“ the relevant approval ” means the approval, by the Secretary of State under section 52(1) of the Act of the England Coast Path Birkenhead to the Welsh Border BHW2 Red Rocks Slipway, Stanley Road, Hoylake to ‘The Boat House’ Public House, Parkgate report on 23rd November 2023;

“ the relevant report ” means the report, submitted by Natural England to the Secretary of State under sections 51 and 55A of the Act on 16th December 2020 entitled “England Coast Path Birkenhead to the Welsh Border BHW2 Red Rocks Slipway, Stanley Road, Hoylake to ‘The Boat House’ Public House, Parkgate”.

Section 2End of access preparation period

In relation to land which is coastal margin, as a result of the relevant approval of the relevant report, the day appointed as the day on which the access preparation period ends is 29th January 2025.

2 sections

Cite this legislation

The Access to the Countryside (Coastal Margin) (Birkenhead to the Welsh border) Order 2025 (legislation.gov.uk, OGL v3.0). Retrieved via LawPlayer, https://lawplayer.com/uk/act/uksi-2025-90

Contains public sector information licensed under the Open Government Licence v3.0.

OGL-3

本頁資料來源:legislation.gov.uk (The National Archives)·整理提供:法律人 LawPlayer· lawplayer.com