§ 285.100Authority.

The authority for this part derives from the Outer Continental Shelf Lands Act (OCS Lands Act) (43 U.S.C. 1337). The Secretary of the Interior delegated to the Bureau of Safety and Environmental Enforcement (BSEE) the authority to regulate certain activities. These regulations specifically apply to activities that:

(a) Produce or support production, transportation, or transmission of energy from sources other than oil and gas; or

(b) Use, for energy-related purposes or for other authorized marine-related purposes, facilities currently or previously used for activities authorized under the OCS Lands Act.

§ 285.101What is the purpose of this part?

The purpose of this part is to:

(a) Inform you and third parties of your obligations when you undertake activities authorized in this part and 30 CFR parts 585 and 586; and

(b) Ensure that renewable energy activities on the OCS and activities involving the alternate use of OCS facilities for energy- or marine-related purposes are conducted in a safe and environmentally sound manner, in conformance with the requirements of subsection 8(p) of the OCS Lands Act, other applicable laws and regulations, and the terms of your lease, ROW grant, RUE grant, or Alternate Use RUE grant.

§ 285.102What are BSEE's responsibilities under this part?

(a) BSEE will ensure that any activities authorized in this part and 30 CFR parts 585 and 586 are carried out in a manner that provides for:

(1) Safety;

(2) Protection of the environment;

(3) Prevention of waste;

(4) Conservation of the natural resources of the OCS;

(5) Coordination with relevant Federal agencies (including, in particular, those agencies involved in planning activities that are undertaken to avoid conflicts among users and maximize the economic and ecological benefits of the OCS, including multifaceted spatial planning efforts);

(6) Protection of national security interests of the United States;

(7) Protection of the rights of other authorized users of the OCS; and

(8) Oversight, inspection, research, monitoring, and enforcement of activities authorized by a lease or grant issued under 30 CFR parts 585 or 586.

(b) BSEE will require compliance with all applicable laws, regulations, other requirements, and the terms of your lease or grant issued under 30 CFR parts 585 or 586, and approved plans. BSEE will approve, disapprove, or approve with conditions any applications or other documents submitted to BSEE for approval under the provisions of this part.

(c) Unless otherwise provided in this part, BSEE may give oral directives or decisions whenever prior BSEE approval is required under this part. BSEE will document in writing any such oral directives within 10 business days.

(d) BSEE will establish practices and procedures to govern the collection of all payments due under this part to the Federal Government, including any cost recovery fees and other fees or payments. BSEE will do this in accordance with the terms of this part, the leasing notice, the lease or grant under 30 CFR parts 585 or 586, and applicable Office of Natural Resources Revenue (ONRR) regulations or guidance.

§ 285.103When may BSEE prescribe or approve departures from the regulations in this part?

(a) BSEE may prescribe or approve departures from the provisions of this part when departures are necessary because the applicable provision(s) as applied to a specific circumstance:

(1) Are impractical or unduly burdensome and the departure is necessary to achieve the intended objectives of the renewable energy program;

(2) Fail to conserve the natural resources of the OCS;

(3) Fail to protect life (including human and wildlife), property, or the marine, coastal, or human environment; or

(4) Fail to protect sites, structures, or objects of historical or archaeological significance.

(b) Any departure approved under this section and its rationale must:

(1) Be consistent with subsection 8(p) of the OCS Lands Act;

(2) Protect the environment and the public health and safety to the same degree as if there was no approved departure from the regulations;

(3) Not impair the rights of third parties; and

(4) Be documented in writing.

§ 285.105What are my responsibilities under this part?

As a lessee, applicant, operator, or holder of a ROW grant, RUE grant, or Alternate Use RUE grant, you must:

(a) Design your projects and conduct all activities in a manner that ensures safety and will not cause undue harm or damage to natural resources, including their physical, atmospheric, and biological components to the extent practicable; and take measures to prevent unauthorized discharge of pollutants including marine trash and debris into the offshore environment.

(b) Submit requests, applications, notices, modifications, and supplemental information to BSEE as required by this part;

(c) Follow up, in writing, any oral request or notification you made, within 3 business days;

(d) Comply with all applicable laws and regulations, the terms of your lease or grant under 30 CFR part 585 or 586, reports, notices, and approved plans prepared under this part, 30 CFR part 585 or 586, and any conditions imposed by BOEM or BSEE through its review of any of these reports, notices, and approved plans, as provided in this part or in 30 CFR part 585 or 586;

(e) Make all applicable payments on time;

(f) Comply with the DOI's nonprocurement debarment regulations at 2 CFR part 1400;

(g) Include the requirement to comply with 2 CFR part 1400 in all contracts and transactions related to a lease or grant under this part;

(h) Conduct all activities authorized by the lease or grant in a manner consistent with the provisions of subsection 8(p) of the OCS Lands Act;

(i) Compile, retain, and make available to BSEE representatives, within the time specified by BSEE, any data and information related to the site assessment, design, and operations of your project; and

(j) Respond to requests from the Director in a timely manner.

§ 285.110How do I submit applications, reports, or notices required by this part?

Unless otherwise stated, you must submit one electronic copy of all plans, applications, reports, or notices required by this part to BSEE. BSEE will inform you if it requires paper copies of specific documents. Unless stated otherwise, documents should be submitted to the relevant contacts listed on the BSEE website.

[89 FR 42713, May 15, 2024]

§ 285.111When and how does BSEE charge me processing fees on a case-by-case basis?

(a) BSEE will charge a processing fee on a case-by-case basis under the procedures in this section with regard to any application or request under this part if we decide at any time that the preparation of a particular document or study is necessary for the application or request and it will have a unique processing cost.

(1) Processing costs will include contract oversight and efforts to review and approve documents prepared by contractors, whether the contractor is paid directly by the applicant or through BSEE.

(2) We may apply a standard overhead rate to direct processing costs.

(b) We will assess the ongoing processing fee for each individual application or request according to the following procedures:

(1) Before we process your application or request, we will give you a written estimate of the proposed fee based on reasonable processing costs.

(2) You may comment on the proposed fee.

(3) You may:

(i) Ask for our approval to perform, or to directly pay a contractor to perform, all or part of any document, study, or other activity according to standards we specify, thereby reducing our costs for processing your application or request; or

(ii) Ask to pay us to perform, or contract for, all or part of any document, study, or other activity.

(4) We will then give you the final estimate of the processing fee amount with payment terms and instructions after considering your comments and any BSEE-approved work you will do.

(i) If we encounter higher or lower processing costs than anticipated, we will re-estimate our reasonable processing costs following the procedures in paragraphs (b)(1) through (4) of this section, but we will not stop ongoing processing unless you do not pay in accordance with paragraph (b)(5) of this section.

(ii) Once processing is complete, we will refund to you the amount of money that we did not spend on processing costs.

(5)(i) Consistent with the payment and billing terms provided in the final estimate, we will periodically estimate what our reasonable processing costs will be for a specific period and will bill you for that period. Payment is due to us 30 days after you receive your bill. We will stop processing your document if you do not pay the bill by the date payment is due.

(ii) If a periodic payment turns out to be more or less than our reasonable processing costs for the period, we will adjust the next billing accordingly or make a refund. Do not deduct any amount from a payment without our prior written approval.

(6) You must pay the entire fee before we will issue the final document or take final action on your application or request.

(7) You may appeal our estimated processing costs in accordance with the regulations in 43 CFR part 4. We will not process the document further until the appeal is resolved, unless you pay the fee under protest while the appeal is pending. If the appeal results in a decision changing the proposed fee, we will adjust the fee in accordance with paragraph (b)(5)(ii) of this section. If we adjust the fee downward, we will not pay interest.

§ 285.112Definitions.

Terms used in this part have the meanings as defined in this section:

P> Affected State means with respect to any activities proposed, conducted, or approved under this part, any coastal State—

(1) That is, or is proposed to be, the site of gathering, transmitting, or distributing energy or is otherwise receiving, processing, refining, or transshipping products, or services derived from activities approved under this part;

(2) That is used, or is scheduled to be used, as a support base for activities approved under this part; or

(3) In which there is a reasonable probability of significant effect on land or water uses from activities approved under this part.

Alternate Use refers to the energy- or marine-related use of an existing OCS facility for activities not otherwise authorized by this title or other applicable law.

Alternate Use RUE means a right-of-use and easement issued for activities authorized under subpart J of this part or part 586.

Archaeological resource means any material remains of human life or activities that are at least 50 years of age and that are of archaeological interest ( i.e., which are capable of providing scientific or humanistic understanding of past human behavior, cultural adaptation, and related topics through the application of scientific or scholarly techniques, such as controlled observation, contextual measurement, controlled collection, analysis, interpretation, and explanation).

BOEM means the Bureau of Ocean Energy Management of the Department of the Interior.

BSEE means the Bureau of Safety and Environmental Enforcement of the Department of the Interior.

Certified Verification Agent (CVA) means an individual or organization, experienced in the design, fabrication, and installation of offshore marine facilities or structures, who will conduct specified third-party reviews, inspections, and verifications in accordance with this part.

Commercial activities means, under renewable energy leases and grants, all activities associated with the generation, storage, or transmission of electricity or other energy product from a renewable energy project on the OCS, and for which such electricity or other energy product is intended for distribution, sale, or other commercial use, except for electricity or other energy product distributed or sold pursuant to technology-testing activities on a limited lease. This term also includes activities associated with all stages of development, including initial site characterization and assessment, facility construction, and project decommissioning.

Commercial lease means a lease issued under 30 CFR part 585 that specifies the terms and conditions under which a person can conduct commercial activities.

Commercial operations means the generation of electricity or other energy product for commercial use, sale, transmission, or distribution from a commercial lease.

Critical Safety Systems and Equipment means safety systems and equipment designed to prevent or ameliorate fires, spillages, or other major accidents that could result in harm to health, safety, or the environment in the area of your facilities.

Decommissioning means removing BOEM and BSEE approved facilities and returning the site of the lease or grant to a condition that meets the requirements under subpart I of this part.

Director means the Director of the Bureau of Safety and Environmental Enforcement (BSEE), of the U.S. Department of the Interior, or an official authorized to act on the Director's behalf.

Fabrication means the cutting, fitting, welding, or other assembly of project elements.

Facility means an installation that is permanently or temporarily attached to the seabed of the OCS. Facilities include any structures; devices; appurtenances; gathering, transmission, and distribution cables; pipelines; and permanently moored vessels. Any group of OCS installations interconnected with walkways, or any group of installations that includes a central or primary installation with one or more satellite or secondary installations, is a single facility. BOEM and BSEE may decide that the complexity of the installations justifies their classification as separate facilities.

Grant means a right-of-way, right-of-use and easement, or alternate use right-of-use and easement issued under the provisions of 30 CFR parts 585 or 586.

Human environment means the physical, social, and economic components, conditions, and factors that interactively determine the state, condition, and quality of living conditions, employment, and health of those affected, directly or indirectly, by activities occurring on the OCS.

Lease means an agreement authorizing the use of a designated portion of the OCS for activities allowed under this part or 30 CFR part 585. The term also means the area covered by that agreement, when the context requires.

Lessee means the holder of a lease, a BOEM-approved assignee, and, when describing the conduct required of parties engaged in activities on the lease, it also refers to the operator and all persons authorized by the holder of the lease or operator to conduct activities on the lease.

Limited lease means a lease issued under 30 CFR part 585 that specifies the terms and conditions under which a person may conduct activities on the OCS that support the production of energy, but do not result in the production of electricity or other energy product for sale, distribution, or other commercial use exceeding a limit specified in the lease.

Natural resources include, without limiting the generality thereof, renewable energy, oil, gas, and all other minerals (as defined in section 2(q) of the OCS Lands Act), and marine animal and marine plant life.

Operator means the individual, corporation, or association having control or management of activities on the lease or grant issued under 30 CFR parts 585 or 586. The operator may be a lessee, grant holder, or a contractor designated by the lessee or holder of a grant issued under 30 CFR parts 585 or 586.

Outer Continental Shelf (OCS) means all submerged lands lying seaward and outside of the area of lands beneath navigable waters, as defined in section 2 of the Submerged Lands Act (43 U.S.C. 1301), whose subsoil and seabed appertain to the United States and are subject to its jurisdiction and control.

Person means, in addition to a natural person, an association (including partnerships and joint ventures); a Federal agency; a State; a political subdivision of a State; a Native American Tribal government; or a private, public, or municipal corporation.

Project, for the purposes of defining the source of revenues to be shared, means a lease ROW, RUE, or Alternate Use RUE on which the activities authorized under this part or 30 CFR parts 585 or 586 are conducted on the OCS. The term “project” may be used elsewhere in this rule to refer to these same authorized activities, the facilities used to conduct these activities, or to the geographic area of the project, i.e., the project area.

Project Design Envelope (PDE) means a reasonable range of design parameters proposed in a lessee's plan for components of the project, such as type, dimensions, and number of wind turbine generators; foundation type; location of the export cable route; location of an onshore substation; location of the grid connection point; and construction methods and timing.

Project easement means an easement to which, upon approval of your Construction and Operations Plan (COP) or General Activities Plan (GAP), you are entitled as part of the lease for the purpose of installing, gathering, transmission, and distribution cables, pipelines, and appurtenances on the OCS as necessary for the full enjoyment of the lease.

Renewable energy means energy resources other than oil and gas and minerals as defined in 30 CFR part 580. Such resources include, but are not limited to, wind, solar, and ocean waves, tides, and current.

Revenues mean bonuses, rents, operating fees, and similar payments made in connection with a project or project area. It does not include administrative fees such as those assessed for cost recovery, civil penalties, and forfeiture of financial assurance.

Right-of-use and easement (RUE) grant means an easement issued by BOEM under 30 CFR parts 585 or 586 that authorizes use of a designated portion of the OCS to support activities on a lease or other use authorization for renewable energy activities. The term also means the area covered by the authorization.

Right-of-way (ROW) grant means an authorization issued by BOEM under 30 CFR part 585 to use a portion of the OCS for the construction and use of a cable or pipeline for the purpose of gathering, transmitting, distributing, or otherwise transporting electricity or other energy product generated or produced from renewable energy, but does not constitute a project easement under 30 CFR part 585. The term also means the area covered by the authorization.

Secretary means the Secretary of the Interior or an official authorized to act on the Secretary's behalf.

Significant archaeological resource means an archaeological resource that meets the criteria of significance for eligibility for listing in the National Register of Historic Places, as defined in 36 CFR 60.4, or its successor.

Site assessment activities means those initial activities conducted to assess an area on the OCS, such as resource assessment surveys (e.g., meteorological and oceanographic) or technology testing, involving the installation of bottom-founded facilities.

We, us, and our refer to the Bureau of Safety and Environmental Enforcement of the Department of the Interior, or its possessive, depending on the context.

You and your means an applicant, lessee, the operator, or designated operator, ROW grant holder, RUE grant holder, or Alternate Use RUE grant holder under 30 CFR parts 585 or 586, or the designated agent of any of these, or the possessive of each, depending on the context. The terms you and your also include contractors and subcontractors of the entities specified in the preceding sentence.

§ 285.113How will data and information obtained by BSEE under this part be disclosed to the public?

(a) BSEE will make data and information available in accordance with the requirements and subject to the limitations of the Freedom of Information Act (FOIA) (5 U.S.C. 552) and the regulations contained in 43 CFR part 2.

(b) BSEE will not release such data and information that we have determined is exempt from disclosure under exemption 4 of FOIA. We will review such data and information and objections of the submitter by the following schedule to determine whether release at that time will result in substantial competitive harm or disclosure of trade secrets.

If you have a . . .

Then BSEE will review data and information for possible release:

(1) Commercial lease

At the earlier of: (i) 3 years after the commencement of commercial operations; or (ii) 3 years after the lease terminates.

(2) Limited lease

At 3 years after the lease terminates.

(3) ROW or RUE grant

At the earliest of:

(i) 10 years after the approval of the grant;

(ii) Grant termination; or

(iii) 3 years after the completion of construction activities.

(c) After considering any objections from the submitter, if we determine that release of such data and information will result in:

(1) No substantial competitive harm or disclosure of trade secrets, then the data and information will be released.

(2) Substantial competitive harm or disclosure of trade secrets, then the data and information will not be released at that time but will be subject to further review every 3 years thereafter.

§ 285.114Paperwork Reduction Act statements—information collection.

(a) The Office of Management and Budget (OMB) has approved the information collection requirements in 30 CFR part 285 under 43 U.S.C. 1331 et seq. and assigned OMB Control Number 1014-0034. The table in paragraph (e) of this section lists the subparts in the rule requiring the information and its title, summarizes the reasons for collecting the information, and summarizes how BSEE uses the information.

(b) Respondents are primarily renewable energy applicants, lessees, ROW grant holders, RUE grant holders, Alternate Use RUE grant holders, and operators. The requirement to respond to the information collection in this part is mandated under subsection 8(p) of the OCS Lands Act. Some responses are also required to obtain or retain a benefit, or may be voluntary.

(c) The Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq. ) requires us to inform the public that an agency may not conduct or sponsor, and you are not required to respond to, a collection of information unless it displays a currently valid OMB control number.

(d) Comments regarding any aspect of the collections of information under this part, including suggestions for reducing the burden, should be sent to the Information Collection Clearance Officer, Bureau of Safety and Environmental Enforcement, 45600 Woodland Road, Sterling, VA 20166.

(e) BSEE is collecting this information for the reasons given in the following table:

30 CFR 285 subpart and title

Reasons for collecting information and how used

(1) Subpart A—General Provisions

To inform BSEE of actions taken to comply with general operational requirements on the OCS. To ensure that operations on the OCS meet statutory and regulatory requirements, are safe and protect the environment, and result in diligent development on OCS leases.

(2) Subpart D—Lease and Grant Administration

To ensure compliance with regulations pertaining to a lease or grant, and suspension of leases and grants.

(3)Subpart F—Information Requirements

To enable BSEE to comply with Federal laws to ensure the safety of the environment on the OCS.

(4) Subpart G—Facility Design, Fabrication, and Installation

To enable BSEE to review the final design, fabrication, and installation of facilities on a lease or grant to ensure that these facilities are designed, fabricated, and installed according to appropriate standards in compliance with BSEE provisions, and where applicable, the approved plan.

(5) Subpart H—Environmental and Safety Management, Inspections, and Facility Assessments for Activities Conducted Under SAPs, COPs, and GAPs

To ensure that lease and grant operations are conducted in a manner that is safe and protects the environment. To ensure compliance with other Federal laws, these regulations, the lease or grant, and approved plans.

(6) Subpart I—Decommissioning

To determine that decommissioning activities comply with regulatory requirements and approvals. To ensure that site clearance and platform or pipeline removal are properly performed to protect marine life and the environment and do not conflict with other users of the OCS.

(7) Subpart J—Rights of Use and Easement for Energy- and Marine- Related Activities Using Existing OCS Facilities

To enable BSEE to review information regarding the design, installation, and operation of RUEs on the OCS, to ensure that RUE operations are safe and protect the human, marine, and coastal environment. To ensure compliance with other Federal laws, these regulations, the RUE grant, and where applicable, the approved plan.

§ 285.115Documents incorporated by reference.

Certain material is incorporated by reference into this part with the approval of the Director of the Federal Register under 5 U.S.C. 552(a) and 1 CFR part 51. All approved incorporation by reference (IBR) material is available for inspection at BSEE and at the National Archives and Records Administration (NARA). Contact BSEE at: BSEE, 45600 Woodland Road, Sterling, Virginia 20166, phone: 703-787-1665. For information on the availability of this material at NARA, visit www.archives.gov/federal-register/cfr/ibr-locations.html or email [email protected] . The material is available from the American Petroleum Institute (API), 200 Massachusetts Avenue NW, Suite 1100, Washington, DC 20001-5571; phone (202) 682-8000; website: www.api.org or https://publications.api.org .

(a) API RP 2A-WSD, Recommended Practice for Planning, Designing and Constructing Fixed Offshore Platforms—Working Stress Design; Twenty-first Edition, December 2000; Errata and Supplement 1, December 2002; Errata and Supplement 2, September 2005; Errata and Supplement 3, October 2007. IBR approved for § 285.825(a), (b).

(b) [Reserved]

§ 285.116Requests for information on the state of the offshore renewable energy industry.

BSEE may publish a request for information (RFI) in the Federal Register to solicit information from industry, State and local agencies, federally recognized Tribes, and other interested entities for evaluating the offshore renewable energy industry, including the identification of potential challenges or obstacles to its continued development. An RFI may relate to the identification of environmental, technical, regulatory, or economic matters that promote or detract from continued development of renewable energy technologies on the OCS. BSEE may use the information received to refine its renewable energy program, including to facilitate OCS renewable energy development in a safe and environmentally responsible manner and to ensure a fair return to the United States for use of the OCS.

§ 285.117Severability.

If a court holds any provisions of this subpart or their applicability to any persons or circumstances invalid, the remainder of the provisions and their applicability to any persons or circumstances will not be affected.

§ 285.118What are my appeal rights?

(a) Any party adversely affected by a final decision issued by BSEE under this part may appeal that decision to the Interior Board of Land Appeals (IBLA), under 30 CFR part 290 and 43 CFR part 4, subpart E.

(b) Any final decision will remain in full force and effect during the pendency of an appeal unless a stay is granted pursuant to 43 CFR part 4.

§ 285.400What happens if I fail to comply with this part?

(a) BSEE may take appropriate corrective action under this part if you fail to comply with applicable provisions of Federal law, the regulations in this part, other applicable regulations, any order of the Director, the provisions of a lease or grant issued under 30 CFR parts 585 or 586, or the requirements of an approved plan or other approval under this part or 30 CFR parts 585 or 586.

(b) BSEE may issue to you a notice of noncompliance if we determine that there has been a violation of the regulations in this part, any order of the Director, or any provision of your lease, grant or other approval issued under this part or 30 CFR parts 585 or 586. When issuing a notice of noncompliance, BSEE will serve you at your last known address.

(c) A notice of noncompliance will tell you how you failed to comply with this part, any order of either Director, and/or the provisions of your lease, grant or other approval, and will specify what you must do to correct the noncompliance and the time limits within which you must act.

(d) Failure of a lessee, operator, or grant holder under this part to take the actions specified in a notice of noncompliance within the time limit specified provides the basis for BSEE to issue a cessation order as provided in § 285.401, and/or a cancellation of the lease or grant as provided in § 285.437.

(e) If BSEE determines that any incident of noncompliance poses an imminent threat of serious or irreparable damage to natural resources; life (including human and wildlife); property; the marine, coastal, or human environment; or sites, structures, or objects of historical or archaeological significance, BSEE may include with its notice of noncompliance an order directing you to take immediate remedial action to alleviate threats and to abate the violation and, when appropriate, a cessation order.

(f) BSEE may assess civil penalties, as authorized by section 24 of the OCS Lands Act and as determined under the procedures set forth in 30 CFR part 250, subpart N, if you fail to comply with any provision of this part, or any term of a lease, grant, or order issued under the authority of this part:

(1) After notice of such failure and expiration of any reasonable period allowed for corrective action; or

(2) BSEE determines that the failure constitutes, or constituted, a threat of serious, irreparable, or immediate harm or damage to life (including fish and other aquatic life), property, or the marine, coastal, or human environment.

(g) You may be subject to criminal penalties as authorized by section 24 of the OCS Lands Act.

§ 285.401When may BSEE issue a cessation order?

(a) BSEE may issue a cessation order during the term of your lease or grant when you fail to comply with an applicable law; regulation; order; or provision of a lease, grant, plan, or BSEE or BOEM approval. Except as provided in § 285.400(e), BSEE will allow you a period of time to correct any noncompliance before issuing an order to cease activities.

(b) A cessation order will set forth what measures you are required to take, including reports you are required to prepare and submit to BSEE, to receive approval to resume activities on your lease or grant.

§ 285.402What is the effect of a cessation order?

(a) Upon receiving a cessation order, you must cease all activities on your lease or grant, as specified in the order. BSEE may authorize certain activities during the period of the cessation order.

(b) A cessation order will last for the period specified in the order or as otherwise specified by BSEE. If BSEE determines that the circumstances giving rise to the cessation order cannot be resolved within a reasonable time period, the Secretary may initiate cancellation of your lease or grant, as provided in § 285.437.

(c) A cessation order does not extend the term of your lease or grant for the period you are prohibited from conducting activities.

(d) You must continue to make all required payments on your lease or grant during the period a cessation order is in effect.

§ 285.406Who is responsible for fulfilling lease and grant obligations?

(a) When you are not the sole lessee or grantee, you and your co-lessee(s) or co-grantee(s) are jointly and severally responsible for fulfilling your obligations under the lease or grant and the provisions of this part or 30 CFR parts 585 or 586, unless otherwise provided in this part.

(b) If your designated operator fails to fulfill any of your obligations under the lease or grant and this part or 30 CFR parts 585 or 586, BSEE may require you or any or all of your co-lessees or co-grantees to fulfill those obligations or other operational obligations under the OCS Lands Act, the lease, grant, or the regulations.

(c) Whenever the regulations in this part or 30 CFR parts 585 or 586 require the lessee or grantee to conduct an activity in a prescribed manner, the lessee or grantee and operator (if one has been designated) are jointly and severally responsible for complying with the regulations.

§ 285.415What is a lease or grant suspension?

(a) A suspension is an interruption of the term of your lease or grant that may occur as ordered by BSEE, as provided in § 285.417; or as approved or ordered by BOEM, as provided in 30 CFR 585.416 and 585.417.

(b) A suspension extends the expiration date for the relevant period of your lease or grant for the length of time the suspension is in effect.

(c) Activities may not be conducted on your lease or grant during the period of a suspension except as expressly authorized under the terms of the suspension.

§ 285.417When may BSEE order a suspension?

(a) BSEE may order a suspension under the following circumstances:

(1) When necessary to comply with judicial decrees prohibiting some or all activities under your lease; or

(2) When continued activities pose an imminent threat of serious or irreparable harm or damage to natural resources; life (including human and wildlife); property; the marine, coastal, or human environment; or sites, structures, or objects of historical or archaeological significance.

(b) If BSEE orders a suspension under paragraph (a)(2) of this section, and if you wish to resume activities, we may require you to conduct a site-specific study that evaluates the cause of the harm, the potential damage, and the available mitigation measures. Other requirements and actions may occur:

(1) You may be required to pay for the study;

(2) You must furnish an electronic copy of the study and results to BSEE pursuant to § 285.110;

(3) We will make the results available to other interested parties and to the public; and

(4) We will use the results of the study and any other information that become available:

(i) To decide if the suspension order can be lifted; and

(ii) To determine any actions that you must take to mitigate or avoid any damage to natural resources; life (including human and wildlife); property; the marine, coastal, or human environment; or sites, structures, or objects of historical or archaeological significance.

§ 285.418How will BSEE issue a suspension?

(a) BSEE will issue a suspension order orally or in writing.

(b) BSEE will send you a written suspension order as soon as practicable after issuing an oral suspension order.

(c) The written order will explain the reasons for its issuance and describe the effect of the suspension order on your lease or grant and any associated activities. BSEE may authorize certain activities during the period of the suspension, as set forth in the suspension order.

§ 285.419What are my immediate responsibilities if I receive a suspension order?

You must comply with the terms of a suspension order upon receipt and take any action prescribed within the time set forth therein.

§ 285.420What effect does a suspension order have on my payments?

If BSEE orders a suspension, as provided in § 285.417, BOEM may waive or defer your payment obligations during the suspension. BOEM's decision to waive or defer payments will depend on the reasons for the suspension, including your responsibility for the circumstances necessitating a suspension.

§ 285.421How long will a suspension be in effect?

A suspension will be in effect for the period specified by BSEE. If BSEE determines that the circumstances giving rise to a suspension ordered under § 285.417 cannot be resolved within 5 years, the Secretary may initiate cancellation of the lease or grant, as provided in § 285.437.

§ 285.433What must I do after my lease or grant terminates?

(a) After your lease or grant terminates, you must:

(1) Make all payments due; and

(2) Perform any other outstanding obligations under the lease or grant within 6 months.

(b) Within 2 years following termination of a lease or grant, you must remove or dispose of all facilities, installations, and other devices permanently or temporarily attached to the seabed on the OCS in accordance with your Plan approved by BOEM under 30 CFR part 585, subpart F, and your application approved by BSEE under subpart I of this part.

(c) If you fail to comply with your approved decommissioning plan or application:

(1) BOEM may call for the forfeiture of your financial assurance; and

(2) You remain liable for removal or disposal costs and responsible for accidents or damages that might result from such failure.

§ 285.437When can my lease or grant be canceled?

(a) The Secretary will cancel any lease or grant issued under 30 CFR parts 585 or 586 upon proof that it was obtained by fraud or misrepresentation, and after notice and opportunity to be heard has been afforded to the lessee or grant holder.

(b) The Secretary may cancel any lease or grant issued under 30 CFR parts 585 or 586 when:

(1) The Secretary determines after notice and opportunity for a hearing that, with respect to the lease or grant that would be canceled, the lessee or grantee has failed to comply with any applicable provision of the OCS Lands Act or these regulations; any order of the Director; or any term, condition or stipulation contained in the lease or grant, and that the failure to comply continued 30 days (or other period BSEE specifies) after you receive notice from BSEE. The Secretary will mail a notice by registered or certified letter to the lessee or grantee at its record post office address;

(2) Required by national security or defense; or

(3) The Secretary determines after notice and opportunity for a hearing that continued activity under the lease or grant:

(i) Would cause serious harm or damage to natural resources; life (including human and wildlife); property; the marine, coastal, or human environment; or sites, structures, or objects of historical or archaeological significance;

(ii) That the threat of harm or damage would not disappear or decrease to an acceptable extent within a reasonable period of time; and

(iii) The advantages of cancellation outweigh the advantages of continuing the lease or grant in force.

§ 285.602What records must I maintain?

Until BOEM releases your financial assurance under 30 CFR 585.534, you must maintain and provide to BSEE, upon request, all data and information related to compliance with the required terms and conditions of your lease, grant, reports submitted under this part and approved plans.

§ 285.614When may I begin conducting activities under my approved SAP?

(a) You may begin conducting the activities approved in your SAP following BOEM approval of your SAP.

(b) If you are installing a facility or a combination of facilities deemed by BOEM to be complex or significant, as provided in 30 CFR 585.613(a)(1), you must comply with the requirements of subpart G of this part and submit the Safety Management System (SMS) description required by § 285.810 before construction may begin.

§ 285.615What other reports or notices must I submit to BSEE under my approved SAP?

(a) You must notify BSEE in writing within 30 days of completing installation activities approved in your SAP.

(b) You must submit a certification of compliance annually (or other frequency as determined by BOEM) with those terms and conditions of your SAP that BOEM identifies under 30 CFR 585.613(e)(1). Together with your certification, you must submit:

(1) Summary reports that show compliance with the terms and conditions which require certification; and

(2) A statement identifying and describing any mitigation measures and monitoring methods and their effectiveness. If you identified measures that were not effective, you must include your recommendations for new mitigation measures or monitoring methods.

§ 285.631When must I initiate activities under an approved COP?

After your COP is approved, you must commence construction by the date given in the construction schedule required by 30 CFR 585.626(b)(21), and included as a part of your approved COP, unless BOEM approves a deviation from your schedule.

§ 285.632What documents must I submit before I may construct and install facilities under my approved COP?

(a) You must submit to BSEE the documents listed in the following table:

Document:

Requirements are found in:

(1) Facility Design Report

§ 285.701

(2) Fabrication and Installation Report

§ 285.702

(b) You must submit your safety management system, as required by § 285.810.

(c) These activities must fall within the scope of your approved COP. If they do not fall within the scope of your approved COP, you will be required to submit a revision to your COP, under 30 CFR 585.634, for BOEM approval before commencing the activity.

§ 285.633How do I comply with my COP?

(a) You must submit a certification of compliance annually (or other frequency as determined by BOEM) with certain terms and conditions of your COP that BOEM identifies. Together with your certification, you must submit:

(1) Summary reports that show compliance with the terms and conditions which require certification; and

(2) A statement identifying and describing any mitigation measures and monitoring methods, and their effectiveness. If you identified measures that were not effective, then you must make recommendations for new mitigation measures or monitoring methods.

(b) As provided at § 285.105(i), BSEE may require you to submit any supporting data and information.

§ 285.636What notices must I provide BSEE following approval of my COP?

You must notify BSEE in writing of the following events, within the time periods provided:

(a) No later than 30 days after commencing activities associated with the placement of facilities on the lease area under a Fabrication and Installation Report.

(b) No later than 30 days after completion of construction and installation activities under a Fabrication and Installation Report.

(c) At least 7 days before commencing commercial operations.

§ 285.637When may I commence commercial operations on my commercial lease?

(a) If you are conducting activities on your lease that do not require a FERC license ( i.e., wind power projects), then you may commence commercial operations after:

(1) You submit information consistent with § 285.702(c) and (d) for facilities installed prior to commencing commercial operations;

(2) Your CVA submits the project verification report, as described in § 285.708(a)(5), including information required by § 285.708(b)(1), or interim report(s), as described in § 285.712(a) for facilities installed prior to commencing commercial operations;

(3) Your CVA submits the Critical Safety Systems and Equipment commissioning records, as described in § 285.708(a)(6) or interim report(s), as described in § 285.712(a), for facilities installed prior to commencing commercial operations; and

(4) BSEE has not notified you of any objections to the submittals in paragraphs (a)(1) and (3) of this section within the timeframes in §§ 285.700(d) and 285.712(a), as applicable. You may continue commercial operations while BSEE reviews your submittals.

(b) To continue commercial operations as additional facilities complete commissioning, you must submit information in paragraphs (a)(1) and (3) of this section for facilities installed after commercial operations have commenced.

(c) You must notify BSEE within 10 business days after you commence commercial operations.

§ 285.638What must I do upon completion of my commercial operations as approved in my COP or FERC license?

(a) Upon completion of your approved activities under your COP, you must decommission your project as set forth in subpart I of this part. You must submit your decommissioning application as provided in §§ 285.905 and 285.906.

(b) Upon completion of your approved activities under your FERC license, the terms of your FERC license will govern your decommissioning activities.

§ 285.650When may I begin conducting activities under my GAP?

After BOEM approves your GAP, you may begin conducting the approved activities that do not involve a project easement or the construction of facilities on the OCS that BOEM has deemed to be complex or significant.

§ 285.651When may I construct complex or significant OCS facilities on my limited lease or any facilities on my project easement proposed under my GAP?

If you are applying for a project easement, or installing a facility or a combination of facilities on your limited lease deemed by BOEM to be complex or significant, as provided in 30 CFR 585.648(a)(1), you also must comply with the requirements of subpart G of this part and submit your safety management system description required by § 285.810 before construction may begin.

§ 285.653What other reports or notices must I submit to BSEE under my approved GAP?

(a) You must notify BSEE in writing within 30 days after completing installation activities approved in your GAP

(b) You must annually (or other frequency as determined by BOEM) submit a certification of compliance with those terms and conditions of your GAP that BOEM identifies under 30 CFR 585.648(e)(1). Together with your certification, you must submit:

(1) Summary reports that show compliance with the terms and conditions which require certification; and

(2) A statement identifying and describing any mitigation measures and monitoring methods and their effectiveness. If you identified measures that were not effective, you must include your recommendations for new mitigation measures or monitoring methods.

§ 285.700What reports must I submit to BSEE before installing facilities described in my approved SAP, COP, or GAP?

(a) You must submit the following reports to BSEE before installing facilities described in your approved COP (30 CFR 585.632(a)) and, when required by 30 CFR part 585, in your approved SAP (30 CFR 585.614(b)) or GAP (30 CFR 585.651):

(1) A Facility Design Report (FDR); and

(2) A Fabrication and Installation Report (FIR).

(b) You may submit separate FDRs and FIRs for integrated asset packages unless otherwise agreed to by BSEE ( e.g., wind turbine generator (WTG), offshore substation/electrical service platform, array cables, export cables, and seabed preparation). If you submit separate FDRs and FIRs by integrated asset packages, you must:

(1) Ensure FDR(s) and FIR(s) for integrated asset package(s) are complete (e.g., the WTG package includes the RNA, blades, tower, foundation, and transition piece, if applicable);

(2) Explain to BSEE how all FDR(s) and FIR(s) for integrated asset packages will function together effectively in an integrated manner in accordance with your project design; and

(3) Demonstrate that such integration has been verified by your CVA.

(c) You may submit your FDRs and FIRs before or after SAP, COP, or GAP approval.

(d) Subject to the requirements in paragraph (b) of this section, you may commence fabrication and installation of the facilities on the OCS as described in each report:

(1) If BSEE deems your report submitted before SAP, COP, or GAP approval and notifies you of its non-objection to the FDR and FIR or does not respond with objections within 60 business days of SAP, COP, or GAP approval; or

(2) If BSEE deems your report submitted after SAP, COP, or GAP approval and notifies you of its non-objection to the FDR and FIR or does not respond with objections within 60 business days of the report being deemed submitted.

(e) You may commence procurement of discrete parts of the project that are commercially available in standardized form and type-certified components, or fabrication activities that do not take place on the OCS (e.g., manufacturing), prior to the submittal of the reports required under paragraph (a) of this section or any plans required under 30 CFR parts 585 and 586. The procurement and fabrication of facility components allowed under this section are subject to verification and certification by your CVA, and BSEE may object to the installation of said components on the OCS if it considers that the components or their fabrication are inconsistent with accepted industry or engineering standards, the approved SAP, COP, or GAP, the FDR or FIR, or BSEE's regulations.

(f) If BSEE has objections, we will notify you in writing within 60 business days of the report being deemed submitted. Following initial notification of any objections, BSEE may follow up with written correspondence detailing its objections to the report and requesting that certain actions be undertaken. You cannot commence fabrication or installation activities on the OCS that are addressed in such reports until you resolve all objections to BSEE's satisfaction.

§ 285.701What must I include in my Facility Design Report?

(a) Your Facility Design Report provides specific details of the design of any facilities, including cables and pipelines that are outlined in your BOEM-approved SAP, COP, or GAP. Your Facility Design Report must demonstrate that your design conforms to your responsibilities listed in § 285.105(a). You must include the following items in your Facility Design Report:

Required documents

Required contents

(1) Cover letter

(i) Proposed facility designations:

(ii) Lease, ROW grant or RUE grant number;

(iii) Area; name and block numbers; and

(iv) The type of facility.

(2) Location plat

(i) Latitude and longitude coordinates, Universal Mercator grid-system coordinates, State plane coordinates in the Lambert or Transverse Mercator Projection System;

(ii) Distances in feet from the nearest block lines. These coordinates must be based on the NAD (North American Datum) 83 datum plane coordinate system; and

(iii) The location of any project easements.

(3) Front, Side, and Plan View drawings

(i) Facility dimensions and orientation;

(ii) Elevations relative to Mean Lower Low Water; and

(iii) Pile sizes and penetration.

(4) Complete set of structural drawings

The approved for construction fabrication drawings should be submitted including, e.g.,

(i) Cathodic protections systems;

(ii) Jacket design;

(iii) Pile foundations;

(iv) Mooring, tendon and tethering systems;

(v) Foundations and anchoring systems; and

(vi) Associated cable and pipeline designs.

(5) Summary of environmental data used for design

A summary of the environmental data used in the design or analysis of the facility. Examples of relevant data include information on:

(i) Extreme weather;

(ii) Seafloor conditions; and

(iii) Waves, wind, current, tides, temperature, snow and ice effects, marine growth, and water depth.

(6) Summary of the engineering design data

(i) Loading information ( e.g., live, dead, environmental);

(ii) Structural information ( e.g., design-life; material types; cathodic protection systems; design criteria; fatigue life; jacket design; deck design; production component design; foundation pilings and templates, and mooring, tethering or tendon systems; fabrication and installation guidelines);

(iii) Location of foundation boreholes and foundation piles;

(iv) Foundation information (e.g., soil stability, design criteria); and

(v) For a floating facility, structural integrity, stability, and ballast information. This includes foundations, piles, templates, anchors or anchor systems, mooring, tethering and tendon systems.

(7) A complete set of design calculations

Self-explanatory.

(8) Project-specific studies used in the facility design or installation

All studies pertinent to facility design or installation, e.g., oceanographic and soil reports including the results of the survey required in 30 CFR 585.610(b), 585.626(b), or 585.645(b).

(9) Description of the loads imposed on the facility

(i) Loads imposed by the jacket;

(ii) Decks;

(iii) Production components;

(iv) Foundations, foundation pilings and templates, and anchoring systems; and

(v) Mooring, tendon or tethering systems.

(10) Geotechnical reports

Reports and supporting data from geotechnical surveys, in situ explorations, laboratory tests, analyses, burial or drivability assessments, and recommended design parameters.

(11) Design Standards

The industry standards you will apply to ensure the facilities are designed to meet § 285.105.

(12) Critical Safety Systems and Equipment

A risk assessment that identifies the Critical Safety Systems and Equipment and a description of the identified Critical Safety System and Equipment.

(13) Other information

Additional information required by BSEE.

(b) For any floating facility, your design must meet the requirements of the U.S. Coast Guard for structural integrity and stability ( e.g., verification of center of gravity) as listed in paragraph (a)(6)(v) of this section. The design must also consider:

(1) Foundations, foundation pilings and templates, and anchoring systems; and

(2) Mooring, tendon, or tethering systems.

(c) You must submit your FDR to BSEE pursuant to § 285.110 and provide the location of records, as required in § 285.714(c).

(d) If you are required to use a CVA, the FDR must include the following certification statement with accompanying justification: “The design of this structure has been certified by a BSEE-approved CVA to be in accordance with accepted engineering practices and the approved SAP, GAP, or COP, as applicable, and has been designed to provide for safety. The certified design and as-built plans and specifications will be on file at [provide location].”

§ 285.702What must I include in my Fabrication and Installation Report?

(a) Your Fabrication and Installation Report must describe how your facilities will be fabricated and installed in accordance with the design criteria identified in the Facility Design Report; your BOEM-approved SAP, COP, or GAP; and generally accepted industry standards and practices. Your Fabrication and Installation Report must demonstrate how your facilities will be fabricated and installed in a manner that conforms to your responsibilities listed in § 285.105(a). You must include the following items in your Fabrication and Installation Report:

Required documents

Required contents

(1) Cover letter

(i) Proposed facility designation, lease, ROW grant, or RUE grant number;

(ii) Area, name, and block number; and

(iii) The type of facility.

(2) Schedule

Fabrication and installation schedule information.

(3) Fabrication information

The industry standards you will use to ensure the facilities are fabricated to the design criteria identified in your Facility Design Report.

(4) Installation process information

Details associated with the deployment activities, equipment, and materials, including onshore and offshore equipment and support, and anchoring and mooring patterns.

(5) Federal, State, and local permits ( e.g., EPA, Army Corps of Engineers)

Either one copy of the permit or information on the status of the application.

(6) Quality assurance

Certificates ensuring adherence to a nationally or internationally recognized quality assurance standard. Alternate means of compliance must be approved on a case-by-case basis.

(7) Environmental information

Information about:

(i) Water discharge;

(ii) Waste disposal;

(iii) Vessel information;

(iv) Onshore waste receiving treatment or disposal facilities; and

(v) If you submitted this data as part of your SAP, COP, or GAP, you may incorporate the information by reference.

(8) Commissioning procedures for Critical Safety Systems and Equipment

Original equipment manufacturer procedures or other BSEE accepted engineering practices for commissioning of Critical Safety Systems and Equipment as identified in § 285.701(a)(12).

(9) Project easement

Information about installation of any cables, pipelines, or facilities. Information on burial methods and vessels.

(10) Other information

Additional information required by BSEE.

(b) You must submit your FIR to BSEE pursuant to § 285.110.

(c) You must provide the location of records, as required in § 285.714(c).

(d) If you are required to use a CVA, the FIR must include the following certification statement with accompanying justification: “The fabrication and installation of this structure has been certified by a BSEE-approved CVA to be in accordance with accepted engineering practices, the FDR, and the approved SAP, GAP, or COP, as applicable. The certified design and as-built plans and specifications will be on file at [provide location].”

§ 285.703What reports must I submit for project modifications and repairs?

(a) You must submit a Project Modification or Repair Report to BSEE in which you certify that major repairs and major modifications of renewable energy structures and crucial components to a completed project conform to accepted engineering practices.

(1) A “major repair” is a corrective action involving structural members affecting the structural integrity of all or a portion of the facility or substantial repair of a Critical Safety Systems and Equipment, including those identified in your FDR.

(2) A “major modification” is an alteration involving structural members affecting the structural integrity of all or a portion of the facility or substantial alteration of Critical Safety Systems and Equipment, including those as identified in your FDR.

(b) The report must also identify the location of all records pertaining to the major repairs or major modifications, as required in § 285.714(c).

(c) If you are required to use a CVA, the report described in paragraph (a) of this section must include the following certification statement with accompanying justification: “The [major modification or major repair] of this [structure or Critical Safety Systems and Equipment] has been certified by a BSEE-approved CVA to be in accordance with accepted engineering practices, the FDR, and the approved SAP, GAP, or COP as applicable.”

§ 285.704After receiving the FDR, FIR, or project verification reports, what will BSEE do?

(a) Determine whether the report is deemed submitted. Within 20 business days after receiving your proposed FDR, FIR, or project verification report, BSEE will review your submission. BSEE will deem your FDR, FIR, or project verification report submitted if BSEE determines it is sufficiently complete and accurate to fulfill the applicable requirements of § 285.701, § 285.702, or § 285.712.

(b) Identify problems and deficiencies. If BSEE determines that your submission has not met the conditions in paragraph (a) of this section, BSEE will notify you of the problem or deficiency within 20 business days after BSEE receives your FDR, FIR, or project verification report. BSEE will not deem your FDR, FIR, or project verification report submitted until you have corrected all problems or deficiencies identified in the notice.

(c) Notify you when the report is deemed submitted. BSEE will notify you when the FDR, FIR, or project verification reports are deemed submitted. If BSEE has not notified you within 20 business days that your report has problems or deficiencies, it is deemed submitted. Until your report is deemed submitted, the time period in § 285.700(d) does not begin running.

§ 285.705When must I use a Certified Verification Agent (CVA)?

(a) Unless BSEE waives this requirement under paragraph (c) of this section, you must use one or more CVAs to review and verify your FDRs, FIRs, and the Project Modification and Repair Reports.

(b) The purpose of a CVA is to:

(1) Ensure that your facilities are designed, fabricated, and installed in conformance with accepted engineering practices and the FDR(s) and FIR(s); and that the design of the facilities is suitable for the location where they will be installed;

(2) Ensure Critical Safety Systems and Equipment are commissioned in accordance with the procedures identified in § 285.702(a)(8);

(3) Ensure that major repairs and major modifications are completed in conformance with accepted engineering practices; and

(4) Provide BSEE and you with reports of all incidents that affect the facility design, fabrication, and installation, including commissioning of Critical Safety Systems and Equipment, for the project and its components.

(c) BSEE may waive in whole or in part the requirement that you use a CVA if you can demonstrate the following:

If you demonstrate that . . .

Then BSEE may waive the requirement for a CVA for the following:

(1) The facility design conforms to a standard design that has been used successfully in a similar environment, and the installation design conforms to accepted engineering practices

The design of your structure(s).

(2) The relevant fabricator has successfully fabricated similar facilities, and the facility will be fabricated in conformance with accepted engineering practices and to a nationally or internationally recognized quality assurance standard

The fabrication of your structure(s).

(3) The installation company has successfully installed similar facilities in a similar offshore environment, and your structures will be installed in conformance with accepted engineering practices

The installation of your structure(s).

(4) Major repairs or major modifications will be completed in conformance with accepted engineering practices and to a nationally or internationally recognized quality assurance standard

The major repair or major modification on your structure(s).

(d) You must submit a request to waive, in whole or in part, the requirement to use a CVA to BSEE in writing.

(1) BSEE will review your request to waive, in whole or in part, the use of the CVA and notify you of its decision.

(2) If BSEE does not waive, in whole or in part, the requirement for a CVA, you may file an appeal under § 285.118.

(3) If BSEE waives, in whole or in part, the requirement that you use a CVA, your project engineer must perform the same duties and responsibilities as would have the CVA, except as otherwise provided. You must submit the project engineer's qualifications to BSEE as a part of your waiver request to demonstrate that your project engineer is a professional engineer with relevant experience and expertise in the facilities they will be verifying/certifying.

§ 285.706How do I nominate a CVA for BSEE approval?

(a) A CVA must be nominated by the lessee and approved by BSEE before conducting any verification or certification activities for which they have been nominated. If you intend to use multiple CVAs, you must nominate a general project CVA who will manage the overall project verification and certification approach and who will ensure consistency and oversight among the CVAs, especially in transition areas between different CVAs. The general project CVA must be nominated no later than COP submission.

(b) For each CVA that you nominate, you must submit to BSEE a list of documents used in your design that you will forward to the CVA and a qualification statement that includes the following:

(1) Previous experience in third-party verification or experience in the design, fabrication, installation, or major modification of offshore energy facilities;

(2) Technical capabilities of the individual or the primary staff for the specific project, including relevant professional licenses, certifications, and accreditations;

(3) Size and type of organization or corporation;

(4) In-house availability of, or access to, appropriate technology (including computer programs, hardware, and testing materials and equipment);

(5) Ability to perform the CVA functions for the specific project considering current commitments;

(6) Previous experience with BOEM and BSEE requirements and procedures, if any; and

(7) The scope and level of work to be performed by the CVA, including all relevant reports and facilities that the CVA will verify or certify.

(c) Individuals or organizations acting as CVAs must not function in any capacity that will create a conflict of interest or the appearance of a conflict of interest. The CVA must not have prepared, or been directly involved in, any work related to the preparation of design, fabrication, installation, modification, or repair plans for which they will provide verification or certification services.

(d) The verification and certification must be conducted by or under the direct supervision of a registered professional engineer.

(e) BSEE will approve or disapprove your CVA as part of BOEM's review of your COP or, when required, of your SAP or GAP.

(f) You must nominate a new CVA for BSEE approval if the previously approved CVA:

(1) Is no longer able to serve in a CVA capacity for the project; or

(2) No longer meets the requirements for a CVA set forth in this subpart.

§ 285.707What are the CVA's primary duties for facility design review?

If you are required to use a CVA:

(a) The CVA must use good engineering judgment and practices in conducting an independent assessment of the design of the facility. The CVA must verify to BSEE that the facility is designed to withstand the environmental and functional load conditions appropriate for the intended service life at the proposed location and has been designed to minimize risk to personnel as required by § 285.105(a).

(b) The CVA must conduct an independent assessment of all proposed:

(1) Planning criteria;

(2) Operational requirements;

(3) Environmental loading data;

(4) Load determinations;

(5) Stress analyses;

(6) Material designations;

(7) Soil and foundation conditions;

(8) Safety factors;

(9) Risk assessments supporting the design for human safety and how the results are used in the design; and

(10) Other pertinent parameters of the proposed design.

(c) For any floating facility, the CVA or project engineer must also verify that any requirements of the U.S. Coast Guard for structural integrity and stability (e.g., verification of center of gravity), have been met. The CVA must also consider:

(1) Foundations, foundation pilings and templates, and anchoring systems; and

(2) Mooring, tendon or tethering systems.

§ 285.708What are the CVA's or project engineer's primary duties for fabrication and installation review?

(a) The CVA or project engineer must do all of the following:

(1) Use good engineering judgment and practice in conducting an independent assessment of the fabrication and installation activities and of the commissioning of Critical Safety Systems and Equipment;

(2) Monitor the fabrication and installation of the facility and the commissioning of Critical Safety Systems and Equipment as required by paragraph (b) of this section;

(3) Make periodic onsite inspections while fabrication is in progress and verify the items required by § 285.709;

(4) Make periodic onsite inspections while installation is in progress and satisfy the requirements of § 285.710;

(5) Certify in Project Verification Reports that project components are fabricated and installed in accordance with accepted engineering practices and to a nationally or internationally recognized quality assurance standard or to an equivalent alternate means of quality assurance considered on a case-by-case basis, your BOEM-approved SAP, COP, or GAP (as applicable), and your FIR. If multiple CVAs are involved in your project, the general project CVA must submit the final report containing such certification for the project. The Project Verification Report must identify the location of all records pertaining to facility fabrication and installation as required in § 285.714(c);

(6) Provide records documenting that Critical Safety Systems and Equipment are commissioned in accordance with the procedures identified in § 285.702(a)(8); and

(7) Identify the location of all records pertaining to commissioning of Critical Safety Systems and Equipment, as required in § 285.714(c).

(b) To comply with paragraphs (a)(4) and (5) of this section, the CVA or project engineer must monitor the fabrication and installation of the facility and the commissioning of Critical Safety Systems and Equipment to certify that they have been built and installed according to your FDRs and FIRs.

(1) If the CVA or project engineer finds that either fabrication and installation procedures or Critical Safety Systems and Equipment commissioning procedures, or both, have been changed or design specifications have been modified, the CVA or project engineer must inform you and BSEE; and

(2) If you accept the modifications, you must also inform BSEE.

§ 285.709When conducting onsite fabrication inspections, what must the CVA or project engineer verify?

(a) To comply with § 285.708(a)(3), the CVA or project engineer must make periodic onsite inspections while fabrication is in progress and must verify the following fabrication items, as appropriate:

(1) Quality control by lessee (or grant holder) and builder;

(2) Fabrication site facilities;

(3) Material quality and identification methods;

(4) Fabrication procedures specified in your FIRs and adherence to such procedures;

(5) Welder and welding procedure qualification and identification;

(6) Structural tolerances specified, and adherence to those tolerances;

(7) Nondestructive examination requirements and evaluation results of the specified examinations;

(8) Destructive testing requirements and results;

(9) Repair procedures;

(10) Installation of corrosion-protection systems and splash-zone protection;

(11) Erection procedures to ensure that overstressing of structural members does not occur;

(12) Alignment procedures;

(13) Dimensional check of the overall structure, including any turrets, turret-and-hull interfaces, any mooring line and chain and riser tensioning line segments, and tendon or tethering systems; and

(14) Status of quality-control records at various stages of fabrication.

(b) For any floating facility, the CVA or project engineer must also verify that any requirements of the U.S. Coast Guard for structural integrity and stability (e.g., verification of center of gravity) have been met. The CVA or project engineer must also consider:

(1) Foundations, foundation pilings and templates, and anchoring systems; and

(2) Mooring, tendon, or tethering systems.

§ 285.710When conducting onsite installation inspections, what must the CVA or project engineer do?

(a) To comply with § 285.708(a)(4), the CVA or project engineer must make periodic onsite inspections while installation is in progress and must, as appropriate, verify, witness, survey, or check the installation and commissioning of items required by this section.

(b) The CVA or project engineer must verify, as appropriate, all of the following:

(1) Loadout and initial flotation procedures;

(2) Towing operation procedures to the specified location, including a review of the towing records;

(3) Launching and uprighting activities;

(4) Submergence activities;

(5) Pile or anchor installations;

(6) Installation of mooring, tendon, and tethering systems;

(7) Final deck and component installations;

(8) Installation at the locations set forth in your FDR(s) and FIR(s); and

(9) Commissioning of Critical Safety Systems and Equipment.

(c) For a fixed or floating facility, the CVA or project engineer must verify that proper procedures were used during the following:

(1) The loadout of the jacket, decks, piles, or structures from each fabrication site;

(2) The actual installation of the facility or major modification and the related installation activities; and

(3) Commissioning of Critical Safety Systems and Equipment.

(d) For a floating facility, the CVA or project engineer must verify structural integrity, stability, and ballast, and that proper procedures were used during the following:

(1) The loadout of the facility;

(2) The installation of foundation pilings and templates, and anchoring systems; and

(3) The installation of the mooring and tethering and tendon systems.

(e) The CVA or project engineer must conduct an onsite inspection of the installed facility as approved in your CVA scope of work.

(f) The CVA or project engineer must make periodic onsite inspections to witness the commissioning of Critical Safety Systems and Equipment in order to verify that:

(1) The Critical Safety Systems and Equipment function as designed; and

(2) The final commissioning Critical Safety Systems and Equipment records are complete.

(g) The CVA or project engineer must spot-check the equipment, procedures, and recordkeeping as necessary to determine compliance with the applicable documents incorporated by reference and the regulations under this part.

§ 285.712What are the CVA's or project engineer's reporting requirements?

(a) The CVA or project engineer must prepare and submit to you and BSEE all reports and records required by this subpart. The CVA or project engineer must also submit interim reports to you and BSEE, as requested by BSEE. BSEE will review and respond within 30 days.

(b) For each report required by this subpart, the CVA or project engineer must submit the final report to BSEE pursuant to § 285.110. In each report, the CVA or project engineer must:

(1) Give details of how, by whom, and when the CVA or project engineer activities were conducted;

(2) Describe the CVA's or project engineer's activities during the verification process;

(3) Summarize the CVA's or project engineer's findings; and

(4) Provide any additional comments that the CVA or project engineer deems necessary.

(5) Summarize any issues with the design and any incidents during facility fabrication and installation, or Critical Safety System and Equipment commissioning, and how those issues were resolved.

89 sections

Cite this law

RENEWABLE ENERGY AND ALTERNATE USES OF EXISTING FACILITIES ON THE OUTER CONTINENTAL SHELF (U.S.C.). Retrieved via LawPlayer, https://lawplayer.com/us/act/cfr-title-30-part-285

United States government works (U.S. Code, Code of Federal Regulations) are in the public domain under 17 U.S.C. § 105.

US-Gov-PublicDomain

本頁資料來源:GPO govinfo / eCFR·整理提供:法律人 LawPlayer· lawplayer.com